CN206656035U - Boom hoisting is installed suitable for the petroleum pipeline of field different-diameter - Google Patents

Boom hoisting is installed suitable for the petroleum pipeline of field different-diameter Download PDF

Info

Publication number
CN206656035U
CN206656035U CN201720423926.0U CN201720423926U CN206656035U CN 206656035 U CN206656035 U CN 206656035U CN 201720423926 U CN201720423926 U CN 201720423926U CN 206656035 U CN206656035 U CN 206656035U
Authority
CN
China
Prior art keywords
clip
petroleum pipeline
boom hoisting
drive mechanism
cross bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720423926.0U
Other languages
Chinese (zh)
Inventor
谭正怀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Laibao Petroleum Equipment Co Ltd
Original Assignee
Chengdu Laibao Petroleum Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Laibao Petroleum Equipment Co Ltd filed Critical Chengdu Laibao Petroleum Equipment Co Ltd
Priority to CN201720423926.0U priority Critical patent/CN206656035U/en
Application granted granted Critical
Publication of CN206656035U publication Critical patent/CN206656035U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model discloses the petroleum pipeline suitable for field different-diameter to install boom hoisting, including support frame, cross bar and drive mechanism, cross bar is provided with expansion link, expansion link is connected with drive mechanism, the bottom of expansion link is provided with the first clip and the second clip, rotatable parts are provided between first clip and the second clip, and the bottom of the first clip and the second clip is additionally provided with boss, boss is provided with screw, motion bar is equipped with the side wall of first clip and the second clip, motion bar both ends are respectively equipped with handle and fixed block, the bottom of support frame as described above is additionally provided with the gland of cone shape, support column is additionally provided with cross bar, support column is provided with solar panel, drive mechanism is provided with battery, battery is connected with drive mechanism with solar panel respectively.The utility model can avoid petroleum pipeline from rocking when being lifted by crane to petroleum pipeline, while meet the lifting of different-diameter petroleum pipeline, and can also be used in the jiggly section in ground.

Description

Boom hoisting is installed suitable for the petroleum pipeline of field different-diameter
Technical field
It the utility model is related to a kind of pipeline boom hoisting, and in particular to pacify suitable for the petroleum pipeline of field different-diameter Load device for hoisting.
Background technology
Oil, also referred to as crude oil, it is a kind of sticky, dark brown (sometimes a little green) liquid.Upper crustal is partly There is petroleum storage in area.The property of oil is different because of the place of production, and range of viscosities is very wide, and freezing point difference is very big (30-60 degrees Celsius), boiling Point range be normal temperature to more than 500 degrees Celsius, dissolve in a variety of organic solvents, it is not soluble in water, but can with water formed emulsion.No The composition and appearance for the oil for crossing different oil fields can be distinguished very big.Oil is mainly used as fuel oil and gasoline, fuel oil and One of current primary energy most important in the world of gasoline composition.Oil is also many chemical industries such as solvent, chemical fertilizer, killed The raw material of worm agent and plastics etc..During the long history that the earth constantly develops, there is " special " period, such as the Paleozoic Era and In Mesozoic Era, after substantial amounts of plant and animal death, the organic substance for forming its body constantly decomposes, and is precipitated with silt or carbonic acid matter The material mixings such as thing form sedimentary.Because deposit constantly accumulates thickening, temperature and pressure is caused to rise, with this mistake The continuous progress of journey, sedimentary is changed into sedimentary rock, and then forms sedimentary basin, and this just provides basic ground for the generation of oil Matter environment.The composition of crude oil mainly has:Oily (this is its main component), colloid (a kind of sticky semi-solid material), pitch Matter (crineous or black brittle solid material), carbonaceous (a kind of nonhydrocarbon).Oil is by mixing based on hydrocarbon Form, there is special odor, coloured flammable oily liquid, natural gas is each based on gaseous hydrocarbon Kind gas composition, there is special odor, colourless inflammability mixed gas.
Oil carries out transfer oil by petroleum pipeline, and for petroleum pipeline when installation, generally requiring boom hoisting will Petroleum pipeline is hung to setting height(from bottom) and installed, and because petroleum pipeline is typically set up in the wild, some local geological environments are recessed Convex injustice, and traditional boom hoisting needs to be operated in stable location, and most of traditional boom hoisting is all It is enclosed on petroleum pipeline and is operated with rope, petroleum pipeline easily shakes during lifting, can not be accurately by stone Oil-piping installs, and reduces operating efficiency.
Utility model content
When technical problem to be solved in the utility model is that traditional boom hoisting hangs petroleum pipeline using rope, stone Oil-piping easily shakes so that and workmen, which accurately can not align petroleum pipeline, to install, and in face of rough During location, boom hoisting also can not work well, and it is an object of the present invention to provide being installed suitable for the petroleum pipeline of field different-diameter Device for hoisting, when being lifted by crane to petroleum pipeline, petroleum pipeline can be avoided to shake, meet the petroleum pipeline to different-diameter The lifting in road, while can be also operated in rough section.
The utility model is achieved through the following technical solutions:
Boom hoisting is installed suitable for the petroleum pipeline of field different-diameter, including support frame, is connected at the top of support frame Cross bar and the drive mechanism that is located on cross bar, the cross bar be provided with expansion link, it is axle that expansion link one end, which is interspersed in cross bar, On line, and with the output axis connection of drive mechanism, the other end of expansion link be provided be circular shape the first clip and the Two clips, rotatable parts are provided between the first clip and the second clip, the first clip and the second clip can be around rotatable parts Activity, and motion bar is equipped with the axis of the first clip and the second clip, the first clip and the second clip are and motion bar It is connected through a screw thread, the bottom of the first clip and the second clip is equipped with boss, and screw is provided with boss.
Further, the bottom of support frame as described above is provided with the gland of cone.Oil is carried out in rough section During the installation of pipeline, the gland of cone is inserted into inside soil, whole device can be fixed, device when ensureing use It will not shake.
Further, two support columns are additionally provided with the top of the cross bar, two support columns are located at the axis of cross bar respectively Both sides, and solar panel is equipped with the top of two support columns, solar panel slant setting is in cross bar and support Between post, battery is additionally provided with the top of drive mechanism, battery is connected with solar panel and drive mechanism respectively.It is out of office During outer operation, usually occur there is no the situation of electricity, therefore the solar panel on cross bar can turn luminous energy Electric energy is turned to, is stored in battery, the electric energy of battery storage can provide electricity for drive mechanism.
Further, the drive mechanism is cylinder, hydraulic cylinder or push-rod electric machine.Drive mechanism is common driving side Formula, it is easy to operation with repairing while laborsaving.
Further, one end of the motion bar is provided with handle, and the other end is provided with fixed block, and fixed block is located at the first clip In the annulus of the second clip composition, and the cross section of fixed block is arc.By rotating regulation handle, when motion bar promote Fixed block clamps petroleum pipeline, because the cross section of fixed block is arc, therefore can preferably with petroleum pipeline outer wall Fit together, improve the fastening to petroleum pipeline.
Further, the rotatable parts are hinge, and the first clip and the second clip can be convenient around articulate Petroleum pipeline is arranged between the first clip and the second clip.
The utility model compared with prior art, has the following advantages and advantages:
1st, the utility model is applied to the petroleum pipeline installation boom hoisting of field different-diameter, and petroleum pipeline is in lifting During, due to being lifted by crane using expansion link, petroleum pipeline can be effectively prevented from double swerve occurs during lifting, made Obtaining petroleum pipeline can quick and precisely be sent to institute's height to be mounted, improve operating efficiency;
2nd, the utility model is applied to the petroleum pipeline installation boom hoisting of field different-diameter, meets to different-diameter The lifting of petroleum pipeline, and when rough section is operated in the wild, can be fixed stably with ground, prevent from using During tilt and collapse.
Brief description of the drawings
Accompanying drawing described herein is used for providing further understanding the utility model embodiment, forms the one of the application Part, the restriction to the utility model embodiment is not formed.In the accompanying drawings:
Fig. 1 is the utility model structure diagram.
Mark and corresponding parts title in accompanying drawing:
1- solar panels, 2- support columns, 3- batteries, 4- drive mechanisms, 5- expansion links, 6- rotatable parts, 7- One clip, 8- motion bars, 9- support frames, 10- glands, 11- boss, 12- screws, 13- fixed blocks, 14- handles, 15- cross bars, The clips of 16- second.
Embodiment
For the purpose of this utility model, technical scheme and advantage is more clearly understood, with reference to embodiment and accompanying drawing, The utility model is described in further detail, and exemplary embodiment of the present utility model and its explanation are only used for explaining this Utility model, it is not intended as to restriction of the present utility model.
Embodiment 1
As shown in figure 1, the utility model is applied to the petroleum pipeline installation boom hoisting of field different-diameter, including two Support frame 9, the cross bar 15 being connected at the top of two support frames 9 and the drive mechanism 4 being arranged on cross bar 15, the cross bar 15 central position is provided with expansion link 5, and expansion link 5 is interspersed on cross bar 15, and with the output axis connection of drive mechanism 4, Drive mechanism 4 is preferably push-rod electric machine, and expansion link 5 is connected with the push rod of push-rod electric machine, when drive mechanism 4 works, can driven Dynamic expansion link 5 is lifted in perpendicular, and to lift by crane petroleum pipeline, the one end of expansion link 5 is connected with drive mechanism 4, on the other end Provided with the first clip 7 and the second clip 16, the first clip 7 and the second clip 16 are circular shape, and the first clip 7 and second Clip 16 can make up a toroidal, and rotatable parts 6, rotation section are provided between the clip 16 of the first clip 7 and second Part 6 is hinge, and the first clip 7 and the second clip 16 can be around articulates, typically with petroleum pipeline is put into first Between the clip 16 of clip 7 and second, the bottom of the first clip 7 and the second clip 16 is equipped with boss 11, the boss of the first clip 7 11 and second clip 16 boss 11 on be equipped with screw 12, screw 12 is by the clip 16 of boss 11 and second of the first clip 7 Boss 11 is fixed together, in use, adjusting screw 12, screw 12 is taken off from boss 11, between boss 11 by stone Oil-piping is put between the first clip 7 and the second clip 16, and petroleum pipeline method, the method are wrapped in rope compared to tradition Quickly petroleum pipeline can be loaded and unloaded, improve operating efficiency, first clip 7 in the side wall of the second clip 16 with being all provided with There is motion bar 8, motion bar 8 is interspersed on the axis of the first clip 7 and on the axis of the second clip 16, and motion bar 8 is equal It is connected by screw thread with the first clip 7 with the second clip 16, the one end of motion bar 8 is provided with handle 14, and the other end is provided with fixed block 13, fixed block 13 is located in the annulus of the first clip 7 and the second clip 16 composition, and the cross section of fixed block 13 is arc, arc Fixed block 13 when being clamped to petroleum pipeline, outer wall that can be preferably with petroleum pipeline fits together, improve pair The fixation of petroleum pipeline, and regulation handle can when motion bar 8 along horizontal direction activity, meet the petroleum pipeline to different-diameter Lifted by crane in road.
In use, rotary screw 12 first, screw 12 is removed from boss 11, pulls the first clip 7 and the second clip 16, the first clip 7 and the second clip 16, which are enclosed on, to be needed on petroleum pipeline to be mounted, again first-class screw 12, by the first clip 7 It is fixed together with the second clip 16, by rotating handles 14, motion bar 8 promotes fixed block 13 that petroleum pipeline is clamped in into first In the annulus of the clip 16 of clip 7 and second composition, start drive mechanism 4, drive mechanism 4 is drawn expansion link 5 and shunk upward, will press from both sides The petroleum pipeline held is sent to the height of required installation, and during lifting, left and right will not occur petroleum pipeline for petroleum pipeline Rock, while improve operating efficiency.
Embodiment 2
As shown in figure 1, the utility model is applied to the petroleum pipeline installation boom hoisting of field different-diameter, in embodiment On the basis of 1, the bottom of support frame as described above 9 is additionally provided with the gland 10 of cone shape, is constructed in rough section When, the gland 10 of cone shape is easy to support frame 9 being inserted into ground so that support frame 9 is fixed with ground, prevents from making During present apparatus run-off the straight, collapse, while the top of cross bar 15 is additionally provided with two support columns 2, and two support columns 2 divide Not Wei Yu cross bar 15 axis both sides, the top of two support columns 2 is equipped with solar panel 1, and solar panel 1 It is tiltedly mounted between cross bar 1 and support column 2, solar panel 1 can gather sunlight, and convert sunlight into electric energy, institute The top for stating drive mechanism 4 is provided with battery 3, and battery 3 is connected with solar panel 1 with drive mechanism 4 respectively, solar energy Cell panel 1 converts light energy into electrical power storage in battery 3, and battery 3 provides work institute subfam. Spiraeoideae for drive mechanism 4.
Above-described embodiment, the purpose of this utility model, technical scheme and beneficial effect are entered One step describes in detail, should be understood that and the foregoing is only specific embodiment of the present utility model, is not used to limit Determine the scope of protection of the utility model, it is all within the spirit and principles of the utility model, any modification for being made, equally replace Change, improve, should be included within the scope of protection of the utility model.

Claims (8)

1. suitable for the petroleum pipeline installation boom hoisting of field different-diameter, including support frame (9), it is connected to support frame (9) The cross bar (15) at top and the drive mechanism (4) being located on cross bar (15), it is characterised in that:The cross bar (15), which is provided with, stretches Contracting bar (5), expansion link (5) one end, which is interspersed in cross bar (15), is on axis, and with the output axis connection of drive mechanism (4), stretch The other end of bar (5) is provided with the first clip (7) and the second clip (16) that are circular shape, the first clip (7) and second Rotatable parts (6) are provided between clip (16), the first clip (7) and the second clip (16) can be movable around rotatable parts (6), And motion bar (8), the first clip (7) and the second clip are equipped with the axis of the first clip (7) and the second clip (16) (16) it is connected through a screw thread with motion bar (8), the bottom of the first clip (7) and the second clip (16) is equipped with boss (11), Screw (12) is provided with boss (11).
2. the petroleum pipeline according to claim 1 suitable for field different-diameter installs boom hoisting, it is characterised in that: The bottom of support frame as described above (9) is provided with the gland (10) of cone.
3. the petroleum pipeline according to claim 1 suitable for field different-diameter installs boom hoisting, it is characterised in that: Two support columns (2) are additionally provided with the top of the cross bar (15), two support columns (2) are located at the axis two of cross bar (15) respectively Side, and solar panel (1) is equipped with the top of two support columns (2), solar panel (1) slant setting is in cross bar (15) between support column (2).
4. the petroleum pipeline according to claim 3 suitable for field different-diameter installs boom hoisting, it is characterised in that: Be additionally provided with battery (3) at the top of the drive mechanism (4), battery (3) respectively with solar panel (1) and drive mechanism (4) connect.
5. the petroleum pipeline according to claim 1 suitable for field different-diameter installs boom hoisting, it is characterised in that: The drive mechanism (4) is cylinder, hydraulic cylinder or push-rod electric machine.
6. the petroleum pipeline according to claim 1 suitable for field different-diameter installs boom hoisting, it is characterised in that: One end of the motion bar (8) is provided with handle (14), and the other end is provided with fixed block (13), and fixed block (13) is located at the first clip (7) in the annulus formed with the second clip (16).
7. the petroleum pipeline according to claim 6 suitable for field different-diameter installs boom hoisting, it is characterised in that: The cross section of the fixed block (13) is arc.
8. the petroleum pipeline according to claim 1 suitable for field different-diameter installs boom hoisting, it is characterised in that: The rotatable parts (6) are hinge.
CN201720423926.0U 2017-04-21 2017-04-21 Boom hoisting is installed suitable for the petroleum pipeline of field different-diameter Expired - Fee Related CN206656035U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720423926.0U CN206656035U (en) 2017-04-21 2017-04-21 Boom hoisting is installed suitable for the petroleum pipeline of field different-diameter

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720423926.0U CN206656035U (en) 2017-04-21 2017-04-21 Boom hoisting is installed suitable for the petroleum pipeline of field different-diameter

Publications (1)

Publication Number Publication Date
CN206656035U true CN206656035U (en) 2017-11-21

Family

ID=60319158

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720423926.0U Expired - Fee Related CN206656035U (en) 2017-04-21 2017-04-21 Boom hoisting is installed suitable for the petroleum pipeline of field different-diameter

Country Status (1)

Country Link
CN (1) CN206656035U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107055358A (en) * 2017-04-21 2017-08-18 成都来宝石油设备有限公司 Reduce the outdoor installation mechanism rocked during petroleum pipeline lifting
CN110701162A (en) * 2018-01-22 2020-01-17 吴碧玉 Anti-sticking hand type bonding equipment for drainage pipeline
CN112984217A (en) * 2021-03-01 2021-06-18 黄河水利职业技术学院 Water conservancy building pipe laying fixing equipment

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107055358A (en) * 2017-04-21 2017-08-18 成都来宝石油设备有限公司 Reduce the outdoor installation mechanism rocked during petroleum pipeline lifting
CN110701162A (en) * 2018-01-22 2020-01-17 吴碧玉 Anti-sticking hand type bonding equipment for drainage pipeline
CN110701162B (en) * 2018-01-22 2021-12-21 钱小英 Anti-sticking hand type bonding equipment for drainage pipeline
CN112984217A (en) * 2021-03-01 2021-06-18 黄河水利职业技术学院 Water conservancy building pipe laying fixing equipment

Similar Documents

Publication Publication Date Title
CN107055358A (en) Reduce the outdoor installation mechanism rocked during petroleum pipeline lifting
CN206654651U (en) It is capable of the lifting appliance of Fast Installation petroleum pipeline
CN206656035U (en) Boom hoisting is installed suitable for the petroleum pipeline of field different-diameter
CN106927359A (en) Petrochemical pipe installs boom hoisting
CN206054946U (en) Shockproof type hydraulically extensible pipeline support equipment
CN206054925U (en) Adjustable multifunctional petroleum pipeline fixing device
CN103938588A (en) Movable and foldable water stopping device
CN207566729U (en) A kind of petroleum pipeline suitable for different-diameter is laid with installation boom hoisting
CN207568638U (en) A kind of fully-mechanized mining working withdraws frame
CN203782657U (en) Movable folding type water retaining device
CN104192277B (en) The liftable of the anti-popin platform of a kind of floating strengthens continuation control method
CN206645342U (en) Conveniently it is sampled and there is the oil storage tank of shockproof function
CN108914993B (en) A kind of works is by uneven settlement of foundation and the pilot system of horizontal loads
CN208007756U (en) A kind of container body of movable type chemical waste liquid processing equipment
CN203452077U (en) Steering mechanism of pile driver and pile driver provided with steering mechanism
CN209469456U (en) A kind of tunnel ditch template
CN207060111U (en) Device for petroleum storage storehouse oil barrel conveyor
CN204529148U (en) Cement electric pole press-rod apparatus
CN104005392B (en) Jack-up unit truss leg semi-circular plate more exchange device and replacing options thereof
CN206939934U (en) Based on the chemical industry oil drum switching mechanism vertically placed
CN206815346U (en) A kind of supporting construction of supporting foundation pit
CN105499457B (en) Large-scale wind electricity flange forging stock underground attemperator
CN205676914U (en) A kind of device of Fast Installation cement kiln end pylon pre-embedded bolt
CN107284492A (en) Carrying mechanism based on petroleum storage bucket in storehouse
CN203938414U (en) A kind of tier pole frame for electric pole welding

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171121

Termination date: 20180421

CF01 Termination of patent right due to non-payment of annual fee