CN206655181U - A kind of combined type anchorage piling wall structure - Google Patents

A kind of combined type anchorage piling wall structure Download PDF

Info

Publication number
CN206655181U
CN206655181U CN201720187103.2U CN201720187103U CN206655181U CN 206655181 U CN206655181 U CN 206655181U CN 201720187103 U CN201720187103 U CN 201720187103U CN 206655181 U CN206655181 U CN 206655181U
Authority
CN
China
Prior art keywords
anchorage
stake
wall
pile
combined type
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720187103.2U
Other languages
Chinese (zh)
Inventor
吴辉
朱林祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Third Harbor Consultants
Original Assignee
CCCC Third Harbor Consultants
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Third Harbor Consultants filed Critical CCCC Third Harbor Consultants
Priority to CN201720187103.2U priority Critical patent/CN206655181U/en
Application granted granted Critical
Publication of CN206655181U publication Critical patent/CN206655181U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of combined type anchorage piling wall structure, it is made up of Compound Anchorage stake and anchorage wall.Described combined type anchorage stake is upper section anchorage stake and lower section anchorage stake composition, and upper section anchoring pile uses the bored concrete pile with inside and outside steel bushing, and lower section anchorage stake is bored concrete pile.Outer sleeve is Large-diameter Steel sleeve, is placed on the outside of inner sleeve, and pea gravel concreten is irrigated between inner and outer sleeves.Anchorage wall is stake top nose girder, can double as the land siding track beam of rail mounted handling facilities, and wall is formed anchorage system, born external loads jointly based on stake.This Compound Anchorage piling wall structure gives full play to section, and anchorage stake rigidity is big, horizontal resist forces are strong and lower section anchorage pile is by the loading characteristic of vertical load, reduces anchorage stake quantity, reduces engineering cost, suitable for reconstruction or newly-built large-scale sheet-pile wharf engineering.

Description

A kind of combined type anchorage piling wall structure
Technical field
The utility model belongs to port engineering field, and in particular to a kind of new combined type anchorage structures.
Background technology
Sheet-pile wharf is a kind of wharf structure commonly used in port engineering, and it is mainly by sheet pile, anchorage, pull bar, chest Wall etc. forms.Conventional sheet-pile wharf applies in general to berth below ton, with the maximization of ship and the deep water in berth Development, harbour grade step up, and are proposed new window shade sheet pile, steel-pipe pile combination sheet-pile wharf, berth grade is up to 10 It is more than ton.
Sheet-pile wharf development amplitude is slow all the time, is primarily limited to front sheet-piled wall and anchorage structures stress and harbour and bankets height Difference is in geometric index relation, and the key for solving its development bottleneck is according to sheet-pile structure loading characteristic, releases new sheet pile knot Configuration formula.Front sheet-piled wall uses window shade sheet pile or steel pipe combination sheet-pile structure, solves the problems, such as the structure stress of front wall substantially.Anchor Heavy stone used as an anchor carries the stress of whole dock structure as one of agent structure in sheet-pile wharf, affects engineering safety, stably Property, it is always the vulnerable area in sheet-pile wharf design.
Anchorage structures can use anchorage wall, anchor plate, anchorage pilework.The horizontal bending resistance of anchorage pilework is poor, vertical Bearing capacity is higher, and for high-grade berth, pull bar horizontal force is big, acts on anchorage stake top, and only pilework can not bear big level Load, such as increase stake diameter and reduce stake spacing, engineering cost will be increased.Anchorage wall and anchorage harden structure horizontal force resistant it is good, Vertical bearing capacity is small, to bear horizontal loading, is usually taken and increases anchorage wall(Plate)Height, thickness solve, but add out Digging amount and difficulty of construction, engineering cost are high.Conventional anchorage structures are more single, can not adapt to large-scale sheet-pile wharf construction, are this This patent proposes a kind of combined type anchorage piling wall structure.
The content of the invention
The technical problems to be solved in the utility model is to provide a kind of combined type anchorage piling wall structure, applied to reconstruction or new Large-scale sheet-pile wharf engineering is built, can be applied to the reconstruction of complex condition or newly-built Wharf Engineering, berth grade is up to 10 tons More than and.
The utility model is realized by following technical scheme:
A kind of combined type anchorage piling wall structure, is made up of Compound Anchorage stake and anchorage wall;Described combined type anchorage stake is Upper section anchorage stake 1, lower section anchorage stake 2 form;The upper section anchorage stake 1 is made up of the bored concrete pile 5 with inner and outer sleeves 4,3, described Lower section anchorage stake 2 is bored concrete pile 5;The outer sleeve 3 is placed on the outside of inner sleeve 4, and the inner sleeve 4 is placed on the upper section anchor On the outside of heavy stone used as an anchor stake 1, pea gravel concreten 6 is irrigated between the inner and outer sleeves 4,3;The upper stake top of section anchorage stake 1 gos deep into the anchorage wall 7 bottoms simultaneously consolidate, and being anchored in anchorage wall 7 has the one end of reinforcing pull rod 8, and the other end of reinforcing pull rod 8 is connected with front sheet-piled wall;The anchor Heavy stone used as an anchor wall 7 is stake top nose girder, and as the land siding track beam of rail mounted handling facilities, wall forms anchorage system, altogether based on stake It is same to bear external loads.This anchorage piling wall structure gives full play to section, and anchorage 1 rigidity of stake is big, horizontal force resistant is strong and lower section anchorage stake 2 bear the loading characteristic of vertical load, reduce anchorage stake quantity, engineering cost are reduced, suitable for large-scale sheet-pile wharf engineering.
As preferable, described Compound Anchorage stake, base of the rail plinth after front sheet-piled wall anchorage and rail mounted handling facilities is undertaken Function;Described Compound Anchorage stake agent structure is bored concrete pile 5, or using steel-pipe pile, concrete tubular pile.
The horizontal force of the transmission of reinforcing pull rod 8 is undertaken as preferable, described upper section anchorage stake 1, steel pipe is pressed in upper section anchorage stake Concrete-pile designs.
Be located at the outside of inner sleeve 4 as preferable, described outer sleeve 3, by irrigate pea gravel concreten 6 and inner sleeve 4, Bored concrete pile 5 connects integral, common performance anchorage effect.
Formed as preferable, described upper section anchorage stake 1 using the bored concrete pile with inner and outer sleeves 4,3, inner sleeve 4 is 16~24mm of wall thickness steel-pipe pile, the upper structure of section anchorage stake 1 are designed by steel tube concrete pile.
It is bored concrete pile 5 as preferable, described lower section anchorage stake 2.
The outside of inner sleeve 4 is wrapped in as preferable, described outer sleeve 3, microlith coagulation is irrigated between inner and outer sleeves 4,3 Soil 6, further lift the overall structure drag of anchorage stake.
, the commensurate structure vertical bearing capacity long by adjusting stake as preferable, described lower section anchorage stake 2.
As preferable, anchorage wall 7 uses cast in situ ferroconcrete wall, can adjust wall height degree commensurate structure stress, wall Based on stake, rail mounted handling facilities basis can be used as.
As preferable, for reconstruction project, for former revetment structure as anchorage system base fixed part, new construction can Revetment and land-based area are formed in advance.
Compared with existing product, combined type anchorage piling wall Structure adaptation of the present utility model is in complex condition reconstruction or new Large pier engineering is built, is especially suitable for harbour reconstruction, avoids the excavation to former revetment, reduce the influence to periphery engineering, be A kind of environmentally friendly structure.Anchorage piling wall is combining structure, using bearing capacity of pile foundation is high, rigidity is big, bending resistance is strong Advantage, the grade of sheet-pile wharf and the stability of anchorage system can be greatly improved.This combined type anchorage piling wall structure has safety The features such as property height, construction is simple, short time limit, engineering economy.
Brief description of the drawings
The utility model is illustrated below in conjunction with the accompanying drawings.
Fig. 1 is the profile of this new structure.
Fig. 2 is the top view of this new structure.
Fig. 3 is section anchorage stake profile on this.
1 is upper section anchorage stake in figure, and 2 be lower section anchorage stake, and 3 be outer sleeve, and 4 be inner sleeve, and 5 be bored concrete pile, and 6 be microlith Concrete, 7 be anchorage wall, and 8 be reinforcing pull rod.
Embodiment
Combined type anchorage piling wall structure as shown in Figure 1, Figure 2, Figure 3 shows, is made up of Compound Anchorage stake and anchorage wall;Compound anchor Heavy stone used as an anchor stake is by upper section anchorage stake 1, and lower section anchorage stake 2, anchorage wall 7, reinforcing pull rod 8 forms.Upper section anchorage stake 1 is composite pile, by overcoat Cylinder 3, inner sleeve 4, bored concrete pile 5, pea gravel concreten 6 are formed.Combined type anchorage piling wall structure is by the more upper sections equidistantly arranged Anchorage stake 1, lower section anchorage stake 2, anchorage wall 7 form.Upper and lower section anchorage stake 1,2 is connected by whole bored concrete pile 5, inner and outer sleeves 4th, 3 connected by pea gravel concreten 6, all upper stake tops of section anchorage stake 1 are goed deep into anchorage wall 7 and consolidated.Anchorage wall 7 is Compound Anchorage All piles are connected into an overall structure by stake superstructure.The one end of reinforcing pull rod 8 is anchored in anchorage wall 7, the other end and foreboard Piling wall connects.Outer sleeve 3, the material of inner sleeve 4 is steel.
This anchorage structures, which calculates, can use finite element software modeling analysis, and stake, wall are with soil effect according to linear elasticity ground Method calculates, and external load is draw-bar pull and handling facilities load.
The described anchorage piling wall structure stress construction time only considers upper and lower section anchorage stake 1,2 bearing loads, validity period by Upper and lower section anchorage stake 1,2 and anchorage wall 7 are born jointly.It can be adapted to by adjusting anchorage stake stake footpath, spacing and anchorage wall height Different brackets sheet-pile wharf, reduce engineering cost.
For reconstruction project, the implementation order of this structure is:1. before construction, first carry out former revetment part and excavate.2. overcoat Cylinder 3 sinks.After 3. outer sleeve 3 sinks, borehole cleaning in cylinder.4. inner sleeve 4 sinks, bored concrete pile 5 is poured.5. pour inside and outside set Pea gravel concreten 6 between in cylinder 4,3, upper and lower section anchorage stake 1,2 piles are completed.6. placement layer by layer armored concrete anchorage wall 7.⑦ Reinforcing pull rod 8 is installed.
For new construction, no step 1. former revetment structural excavation, instead applied for rear revetment and land-based area backfill Work, form anchorage piling wall basis, the same reconstruction project of subsequent step.
Anchorage wall 7 is rail mounted handling facilities basis, during cast-in-place concrete, answers placement layer by layer, reconciles sheet pile Wharf Construction Phase displacement.After anchorage System forming, after sheet pile wall backfill should be layered, phase in, dredge stage excavation before wall, backfill and dredge Construction speed should be controlled by dredging, and keep a close eye on harbour displacement.
Combined type anchorage piling wall structure is made up of Compound Anchorage stake and anchorage wall 7.Steel tube concrete pile is pressed in upper section anchorage stake 1 Design, outer sleeve 3 are placed on the outside of inner sleeve 4 and further enhance anchorage structures drag.Anchorage wall 7 is stake top nose girder, can be doubled as The land siding track beam of rail mounted handling facilities, bears horizontal and vertical load.This anchorage structures system can be by adjusting anchorage stake The height of diameter, spacing and anchorage wall adapts to large-scale sheet-pile wharf construction requirements.It is firm that this structure gives full play to section anchorage stake Spend loading characteristic of big, the strong and lower section anchorage pile of horizontal force resistant by vertical load.
Described above structural principle of the present utility model and embodiment, but be not restricted to the described embodiments.It is above-mentioned Simply illustrate structural principle of the present utility model described in embodiment and specification, before the utility model category is not departed from Put, the utility model also has various changes and modifications, and these changes and improvements both fall within claimed the utility model In the range of.The utility model requires protection scope is by appended claims and its equivalent thereof.

Claims (5)

  1. A kind of 1. combined type anchorage piling wall structure, it is characterised in that:It is made up of Compound Anchorage stake and anchorage wall;Described combined type Anchorage stake is upper section anchorage stake, lower section anchorage stake composition;The upper section anchorage stake is made up of the bored concrete pile with inside and outside steel bushing, The lower section anchorage stake is bored concrete pile;The outer sleeve is placed on the outside of the inner sleeve, and the inner sleeve is placed on the upper section anchor On the outside of heavy stone used as an anchor stake, pea gravel concreten is irrigated between the inner and outer sleeves;The upper section anchorage stake stake top gos deep into the anchorage wall bottom simultaneously Consolidation, anchorage have anchored reinforcing pull rod one end within the walls, and the reinforcing pull rod other end is connected with front sheet-piled wall;The anchorage wall is in stake Portion's nose girder, as the land siding track beam of rail mounted handling facilities, wall is formed anchorage system, is born outside jointly based on stake Load.
  2. 2. combined type anchorage piling wall structure as claimed in claim 1, it is characterised in that:Described Compound Anchorage stake, before undertaking Rail basic function after sheet pile wall anchorage and rail mounted handling facilities;Described Compound Anchorage stake agent structure is bored concrete pile, or is adopted With steel-pipe pile, concrete tubular pile.
  3. 3. combined type anchorage piling wall structure as claimed in claim 1, it is characterised in that:Described upper section anchorage pile load steel is drawn The horizontal force of bar transmission, upper section anchorage stake are designed by steel tube concrete pile.
  4. 4. combined type anchorage piling wall structure as claimed in claim 1, it is characterised in that:Described outer sleeve is located at outside inner sleeve Side, integral, common performance anchorage effect is connected with inner sleeve, bored concrete pile by irrigating pea gravel concreten.
  5. 5. the combined type anchorage piling wall structure as described in claim 1 or 4, it is characterised in that:Described inner sleeve 4 is wall thickness 16 ~24mm steel-pipe pile.
CN201720187103.2U 2017-02-28 2017-02-28 A kind of combined type anchorage piling wall structure Expired - Fee Related CN206655181U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720187103.2U CN206655181U (en) 2017-02-28 2017-02-28 A kind of combined type anchorage piling wall structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720187103.2U CN206655181U (en) 2017-02-28 2017-02-28 A kind of combined type anchorage piling wall structure

Publications (1)

Publication Number Publication Date
CN206655181U true CN206655181U (en) 2017-11-21

Family

ID=60314728

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720187103.2U Expired - Fee Related CN206655181U (en) 2017-02-28 2017-02-28 A kind of combined type anchorage piling wall structure

Country Status (1)

Country Link
CN (1) CN206655181U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109235359A (en) * 2018-10-22 2019-01-18 中交第三航务工程勘察设计院有限公司 Narrow Engineering Zone revetment structure and its construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109235359A (en) * 2018-10-22 2019-01-18 中交第三航务工程勘察设计院有限公司 Narrow Engineering Zone revetment structure and its construction method

Similar Documents

Publication Publication Date Title
CN102518135B (en) Horizontal jet grouting soil anchor and castinplace pile Composite Foundation Pit supporting construction engineering method
CN205530114U (en) To drawing formula steel pipe sheet pile wharf structure
CN105862663A (en) Bulkhead wall type supporting and blocking structure with oblique piles and relieving slabs combined
CN102535263B (en) Roadbed having pile-net combination structure and construction method thereof
CN202898930U (en) By-river reinforced roadbed structure
CN1837511A (en) Double-rowed cofferdam and method for manufacturing the same
CN101457526A (en) Circular deep foundation ditch concrete pile arranging support and major structure inversing construction method
CN106759442A (en) A kind of single-pile elevated bearing-platform and anchor cable tower-crane foundation structure and its construction method
CN110042715A (en) The construction method of the hard and soft combination soil stabilization system of Abutment Back
CN202323865U (en) Novel revetment combined structure
CN203834422U (en) Novel high-pile wharf
CN103898868A (en) Novel high-pile wharf
CN207003421U (en) A kind of steel plate pilework for being seated hard rock top surface
CN110055973B (en) Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method
CN208472592U (en) Close to the steel pipe pile reinforced construction of deep basal pit bridge friction pile
CN206655181U (en) A kind of combined type anchorage piling wall structure
CN204849734U (en) Prefabricated sheet pile and manger plate fender building structure for soil
CN208472713U (en) A kind of composite structure mini pile for administering small-sized landslide
CN201351279Y (en) Circular deep foundation pit support
CN109555078A (en) A kind of Gravity Type Casisson Berth and its construction method
CN206052770U (en) A kind of use cast-in-situ bored pile combines the retaining wall of compaction grouting
CN111305050B (en) Protection process for existing piers on two sides in tunnel construction
CN204875664U (en) A retaining wall structure for interim pier in bay
CN107338760A (en) A kind of low tide Cha Gang areas bulkhead wall caisson wharf structure and its method of construction
CN209958290U (en) Take shore protection structure of pile foundation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171121

Termination date: 20200228

CF01 Termination of patent right due to non-payment of annual fee