CN206646547U - Piping lane prefabricated component and assembled pipe gallery - Google Patents

Piping lane prefabricated component and assembled pipe gallery Download PDF

Info

Publication number
CN206646547U
CN206646547U CN201720356670.6U CN201720356670U CN206646547U CN 206646547 U CN206646547 U CN 206646547U CN 201720356670 U CN201720356670 U CN 201720356670U CN 206646547 U CN206646547 U CN 206646547U
Authority
CN
China
Prior art keywords
pipe
piping lane
prefabricated component
room
lane prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720356670.6U
Other languages
Chinese (zh)
Inventor
罗李鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Julong Pipe Industry Co Ltd
Original Assignee
Chongqing Julong Pipe Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Julong Pipe Industry Co Ltd filed Critical Chongqing Julong Pipe Industry Co Ltd
Priority to CN201720356670.6U priority Critical patent/CN206646547U/en
Application granted granted Critical
Publication of CN206646547U publication Critical patent/CN206646547U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Quick-Acting Or Multi-Walled Pipe Joints (AREA)

Abstract

The utility model discloses a kind of piping lane prefabricated component, including piping lane body, the piping lane body, pipe room is provided with the piping lane body, the pipe room is divided into left pipe room and right pipe room by the pipe interior provided with dividing wall, the both ends of the piping lane body are respectively equipped with the bellmouth and socket of mutual cooperation, and the bellmouth inwall is provided with seal groove;The bottom surface of the piping lane body is respectively arranged on the left side and the right side the chute being parallel to each other.The invention also discloses a kind of assembled pipe gallery, including two track piers being parallel to each other, it is fixedly mounted on the track pier and is provided with sliding rail, installation is provided with least two as described above and mutually splices the piping lane prefabricated component being integrated on the sliding rail, and two chutes are slidably matched with two sliding rails respectively;In the two neighboring pipe prefabrication part, in the bellmouth of socket insertion another pipe prefabrication part of one of them pipe prefabrication part, and installation is provided with sealing ring in the seal groove.

Description

Piping lane prefabricated component and assembled pipe gallery
Technical field
A kind of piping lane is the utility model is related to, is specifically a kind of piping lane prefabricated component and assembled pipe gallery.
Background technology
Pipe gallery is that underground urban duct integrates corridor.A tunnel space is built in Urban Underground, by electric power, is led to News, the various utilities pipelines such as combustion gas, heat supply, plumbing are integrated in one, provided with special access hole, hoisting port and monitoring system, Implement unified planning, Uniting, the unified important infrastructure and " lifeline " built and managed, be guarantee city operations. It is to implement unified planning, design, construction and maintenance, is built in Urban Underground and is set for laying the municipal public use of municipal public use pipeline Apply.
Pipe gallery is typically assembled using piping lane prefabricated component, because piping lane prefabricated component volume is big, weight weight, therefore It is extremely inconvenient during construction and installation, the problems such as installation difficulty, construction speed is slow be present.
The content of the invention
In view of this, the purpose of this utility model is to provide a kind of piping lane prefabricated component and assembled pipe gallery, has The advantages of easy to assembly, is installed, efficiency of construction can be greatly improved.
To reach above-mentioned purpose, the utility model provides following technical scheme:
The utility model first proposed a kind of piping lane prefabricated component, including piping lane body, the piping lane body, the piping lane Pipe room is provided with body, the pipe room is divided into left pipe room and right pipe room, the piping lane body by the pipe interior provided with dividing wall Both ends be respectively equipped with the bellmouth and socket of mutual cooperation, the bellmouth inwall is provided with seal groove;The bottom of the piping lane body Face is respectively arranged on the left side and the right side the chute being parallel to each other.
Further, the left pipe is indoor is provided with communication cable pipe support and feedwater pipe pier;The right pipe is indoor to be provided with thermal pipe Pier.
Further, the communication cable pipe support is vertically-mounted on the left side wall of the left pipe room including being disposed in parallel in Frame, horizontal communication cable pipe support frame is interval with the vertically-mounted frame, the communication cable pipe support frame is away from institute The one end for stating vertically-mounted frame is provided with upward block.
Further, the left pipe room and right pipe interior are respectively equipped with emergency light.
Further, the left pipe room and right pipe interior are respectively equipped with supervising device.
Further, the supervising device includes the processor electrically connected with remote monitoring center, is electrically connected on the processor It is equipped with monitoring camera, temperature sensor and humidity sensor.
Further, the dividing wall is provided with UNICOM's door, and electro-magnetic screen layer is provided with UNICOM's door.
The utility model also proposed a kind of assembled pipe gallery, including two track piers being parallel to each other, the rail It is fixedly mounted on road pier and is provided with sliding rail, is installed on the sliding rail and be provided with least two as described above and be mutually spliced into The piping lane prefabricated component of one, two chutes are slidably matched with two sliding rails respectively;The two neighboring pipeline In prefabricated component, the bellmouth of socket insertion another pipe prefabrication part of one of them pipe prefabrication part It is interior, and installation is provided with sealing ring in the seal groove.
Further, the top surface both sides of the track pier are respectively provided with the slider roller for supporting the piping lane prefabricated component.
The beneficial effects of the utility model are:
Assembled pipe gallery of the present utility model, by setting bellmouth and socket respectively at the both ends of piping lane body, and Chute is set to be slidably matched with sliding rail on the bottom surface of piping lane body, during assembling, it is only necessary to which piping lane prefabricated component is placed on into cunning On dynamic rail road, piping lane prefabricated component is promoted to be slided along sliding rail using other power set, you can to realize piping lane prefabricated component Bellmouth or socket and other piping lane prefabricated components coordinate, realize assembling, have and assemble the advantages of simple and convenient, can effectively improve Efficiency of assembling and efficiency of construction.
Brief description of the drawings
In order that the purpose of this utility model, technical scheme and beneficial effect are clearer, the utility model provides as follows Accompanying drawing illustrates:
Fig. 1 is the structural representation of the utility model assembled pipe gallery embodiment;
Fig. 2 is Fig. 1 left view;
Fig. 3 is the structural representation of piping lane prefabricated component;
Fig. 4 is Fig. 3 A-A sectional views.
Embodiment
The utility model is described in further detail with specific embodiment below in conjunction with the accompanying drawings, so that those skilled in the art The utility model can be better understood from and can be practiced, but illustrated embodiment is not as to restriction of the present utility model.
As shown in figure 1, the structural representation for the utility model assembled pipe gallery embodiment.The assembling of the present embodiment Formula pipe gallery, including two track piers 1 being parallel to each other, it is fixedly mounted on the track pier 1 and is provided with sliding rail 2, it is described Installation mutually splices the piping lane prefabricated component 3 being integrated provided with least two on sliding rail 2.The piping lane prefabricated component of the present embodiment, Including piping lane body 4, the piping lane body 4, the piping lane body 4 is interior to be provided with pipe room, and the indoor dividing wall 5 that is provided with of the pipe is by institute To state pipe room and be divided into left pipe room 6 and right pipe room 7, the both ends of the piping lane body 4 are respectively equipped with the bellmouth 8 and socket 9 of mutual cooperation, The inwall of bellmouth 8 is provided with seal groove 10;The bottom surface of the piping lane body 4 is respectively arranged on the left side and the right side the cunning being parallel to each other Groove 11.Two chutes 11 are slidably matched with two sliding rails 2 respectively.In the two neighboring pipe prefabrication part 3, The socket 9 of one of them pipe prefabrication part 3 is inserted in the bellmouth 8 of another pipe prefabrication part 3, and institute State installation in seal groove 10 and be provided with sealing ring 12.
Further, communication cable pipe support and feedwater pipe pier 13 are provided with the left pipe room 6 of the present embodiment;The right pipe room Heating power pipe pier 14 is provided with 7.The communication cable pipe support of the present embodiment includes being disposed in parallel on the left side wall of the left pipe room 6 Vertically-mounted frame 15, horizontal communication cable pipe support frame 16, the communication cable are interval with the vertically-mounted frame 15 The one end of pipe support frame 16 away from the vertically-mounted frame is provided with upward block.It disclosure satisfy that the installation requirement of communication cable.
Further, emergency light 17 is respectively equipped with the left pipe room 6 and right pipe room 7, for emergency lighting.And left pipe Supervising device 18 is respectively equipped with room 6 and right pipe room 7.The supervising device of the present embodiment includes what is electrically connected with remote monitoring center Processor, on the processor electrical connection be provided with monitoring camera, temperature sensor and humidity sensor, can realize to piping lane Internal real-time detection.
Further, the dividing wall 5 is provided with UNICOM's door 19, and electro-magnetic screen layer is provided with UNICOM's door 19, convenient left Intercommunication between pipe room 6 and right pipe room 7, is easily installed pipeline and maintenance.
Further, the top surface both sides of the track pier 1 are respectively provided with the slider roller for supporting the piping lane prefabricated component 3 20, i.e. piping lane prefabricated component 3 is rolled with sliding rail 2 and coordinated, and is easy to drive its movement.
The assembled pipe gallery of the present embodiment, by setting bellmouth and socket respectively at the both ends of piping lane body, and Chute is set to be slidably matched with sliding rail on the bottom surface of piping lane body, during assembling, it is only necessary to which piping lane prefabricated component is placed on into slip On track, piping lane prefabricated component is promoted to be slided along sliding rail using other power set, you can to realize piping lane prefabricated component Bellmouth or socket coordinate with other piping lane prefabricated components, realize assembling, have and assemble the advantages of simple and convenient, can effectively improve dress With efficiency and efficiency of construction.
Embodiment described above is only the preferred embodiment to absolutely prove the utility model and being lifted, the utility model Protection domain not limited to this.The equivalent substitute or change that those skilled in the art are made on the basis of the utility model Change, within the scope of protection of the utility model.The scope of protection of the utility model is defined by claims.

Claims (9)

1. a kind of piping lane prefabricated component, including piping lane body, the piping lane body, the piping lane body is interior to be provided with pipe room, the pipe The pipe room is divided into left pipe room and right pipe room by interior provided with dividing wall, it is characterised in that:The both ends difference of the piping lane body Bellmouth and socket provided with mutual cooperation, the bellmouth inwall are provided with seal groove;The left and right two of the bottom surface of the piping lane body Side is respectively equipped with the chute being parallel to each other.
2. piping lane prefabricated component according to claim 1, it is characterised in that:The left pipe is indoor be provided with communication cable pipe support and Feed water pipe pier;The right pipe is indoor to be provided with heating power pipe pier.
3. piping lane prefabricated component according to claim 2, it is characterised in that:The communication cable pipe support includes being disposed in parallel in Vertically-mounted frame on the left side wall of the left pipe room, horizontal communication cable pipe support is interval with the vertically-mounted frame Frame, the one end of the communication cable pipe support frame away from the vertically-mounted frame are provided with upward block.
4. piping lane prefabricated component according to claim 2, it is characterised in that:The left pipe room and right pipe interior are respectively equipped with should Anxious illuminating lamp.
5. piping lane prefabricated component according to claim 2, it is characterised in that:The left pipe room and right pipe interior are respectively equipped with prison Control device.
6. piping lane prefabricated component according to claim 5, it is characterised in that:The supervising device includes and remote monitoring center The processor of electrical connection, on the processor electrical connection be provided with monitoring camera, temperature sensor and humidity sensor.
7. according to the piping lane prefabricated component described in claim any one of 1-6, it is characterised in that:The dividing wall is provided with UNICOM Door, UNICOM's door is interior to be provided with electro-magnetic screen layer.
A kind of 8. assembled pipe gallery, it is characterised in that:It is fixed on the track pier including two track piers being parallel to each other Installation is provided with sliding rail, is installed on the sliding rail and is provided with least two as described in claim 1-7 and is mutually spliced into The piping lane prefabricated component of one, two chutes are slidably matched with two sliding rails respectively;The two neighboring pipeline In prefabricated component, the bellmouth of socket insertion another pipe prefabrication part of one of them pipe prefabrication part It is interior, and installation is provided with sealing ring in the seal groove.
9. assembled pipe gallery according to claim 8, it is characterised in that:The top surface both sides of the track pier are set respectively There is the slider roller for supporting the piping lane prefabricated component.
CN201720356670.6U 2017-04-07 2017-04-07 Piping lane prefabricated component and assembled pipe gallery Expired - Fee Related CN206646547U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720356670.6U CN206646547U (en) 2017-04-07 2017-04-07 Piping lane prefabricated component and assembled pipe gallery

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720356670.6U CN206646547U (en) 2017-04-07 2017-04-07 Piping lane prefabricated component and assembled pipe gallery

Publications (1)

Publication Number Publication Date
CN206646547U true CN206646547U (en) 2017-11-17

Family

ID=60274857

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720356670.6U Expired - Fee Related CN206646547U (en) 2017-04-07 2017-04-07 Piping lane prefabricated component and assembled pipe gallery

Country Status (1)

Country Link
CN (1) CN206646547U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110230322A (en) * 2019-06-10 2019-09-13 孙自强 A kind of pipe gallery prefabricated component
CN110359491A (en) * 2019-07-03 2019-10-22 鞍山三冶建筑工程有限公司 A kind of installation translating device of large scale prefabricated piping lane
CN110359489A (en) * 2019-07-03 2019-10-22 鞍山三冶建筑工程有限公司 A kind of large scale prefabricated piping lane incremental launching construction structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110230322A (en) * 2019-06-10 2019-09-13 孙自强 A kind of pipe gallery prefabricated component
CN110359491A (en) * 2019-07-03 2019-10-22 鞍山三冶建筑工程有限公司 A kind of installation translating device of large scale prefabricated piping lane
CN110359489A (en) * 2019-07-03 2019-10-22 鞍山三冶建筑工程有限公司 A kind of large scale prefabricated piping lane incremental launching construction structure
CN110359489B (en) * 2019-07-03 2024-04-26 鞍山三冶建筑工程有限公司 Large prefabricated pipe gallery pushing construction structure
CN110359491B (en) * 2019-07-03 2024-04-26 鞍山三冶建筑工程有限公司 Installation translation device of large-scale prefabricated piping lane

Similar Documents

Publication Publication Date Title
CN107044136A (en) Piping lane prefabricated component and assembled pipe gallery
CN206646547U (en) Piping lane prefabricated component and assembled pipe gallery
CN202969415U (en) Multifunctional assembled comprehensive pipe gallery
CN204927913U (en) Transformer substation
CN107191880A (en) One kind is based on underground pipe gallery solar illumination apparatus
CN112031022A (en) Formula of sinking utility tunnel
CN205822238U (en) Underground pipe gallery structure
CN205746584U (en) A kind of photoconduction daylight illuminating system
CN205156958U (en) Device is patrolled and examined in automation in utility tunnel
CN207053151U (en) A kind of pipe gallery cable line outlet arrangement
CN205560518U (en) Retractable LED street lamp
CN207094486U (en) Based on underground pipe gallery solar illumination apparatus
CN205370599U (en) Self -draining structural waterproof furred ceiling board
CN102661568A (en) Light-guide lighting system for factory building in cigarette industry
CN207920198U (en) A kind of underground garage truck space guiding system and the mounting structure of illumination
CN206616592U (en) Lighting device is penetrated at a kind of bottom constructed for pipe gallery
CN203686864U (en) Daylight illumination system with adjustable angle of light guide pipe
CN207094485U (en) One kind is based on underground pipe gallery solar energy sealing device
CN201713863U (en) Anti-dewing structure for two continuous bent pipes of water supply and drainage pipeline of building
CN206736961U (en) A kind of Novel steel-plastic composite pipe corridor
CN102392256A (en) Wind/solar/electric complementary network anticorrosion system for buried steel pipelines
CN206361634U (en) A kind of illuminator and pipe gallery
CN205688864U (en) The Room, ground, integrated photovoltaic subway gateway
CN102661571B (en) Light guide tube connector of light-guide lighting system for factory building in cigarette industry
CN208281928U (en) A kind of rail traffic overlapping assembled integrates the lighting system of prefabricated piping lane

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171117

Termination date: 20180407

CF01 Termination of patent right due to non-payment of annual fee