CN206646513U - A kind of excavation and filling combines the earth material field slag field composite construction of construction - Google Patents

A kind of excavation and filling combines the earth material field slag field composite construction of construction Download PDF

Info

Publication number
CN206646513U
CN206646513U CN201720227084.1U CN201720227084U CN206646513U CN 206646513 U CN206646513 U CN 206646513U CN 201720227084 U CN201720227084 U CN 201720227084U CN 206646513 U CN206646513 U CN 206646513U
Authority
CN
China
Prior art keywords
field
earth material
construction
slag
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720227084.1U
Other languages
Chinese (zh)
Inventor
魏行
魏一行
程瑞林
邱焕峰
郝鹏
敖卫兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201720227084.1U priority Critical patent/CN206646513U/en
Application granted granted Critical
Publication of CN206646513U publication Critical patent/CN206646513U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses the earth material field slag field composite construction that a kind of excavation and filling combines construction, include slag field(3)With earth material field(1), slag field(3)Occupation of land is the part that earth material field is taken up an area.The utility model can reduce engineering and take up an area and reduce construction investment temporarily.

Description

A kind of excavation and filling combines the earth material field slag field composite construction of construction
Technical field
A kind of earth material field slag field structure is the utility model is related to, the earth material field slag field that particularly a kind of excavation and filling combines construction is answered Close structure.
Background technology
Build hydraulic engineering to be related to the excavation of a large amount of cubic metres of earth and stone and fill, therefore be necessarily required to arrangement and meet that design capacity will The Dumping Sites asked and stock ground.In Practical Project, Dumping Sites and stock ground are generally arranged in diverse location, but in some valleys The hydraulic engineering that area is built often face the problem of construction site layout difficulty, particularly Dumping Sites and stock ground because take up an area compared with Greatly, it is difficult to choose correct position.Slag field is combined with earth material field and can effectively solve the problem that slag field Layout Problem.
The content of the invention
The purpose of this utility model is, there is provided a kind of excavation and filling combines earth material field and the slag field composite construction of construction.This reality Engineering, which is reduced, with New Energy takes up an area and reduce construction investment temporarily.
The technical solution of the utility model:A kind of excavation and filling combines the earth material field slag field composite construction of construction, includes slag field With earth material field, the occupation of land of slag field is the part that earth material field is taken up an area.
Foregoing excavation and filling combines the earth material field slag field composite construction of construction, excavates earth material on the earth material field, slag field is located at The side of the heatable adobe sleeping platform formed after earth material is excavated in earth material field, and the earth material of excavation is located at the opposite side of heatable adobe sleeping platform.
Foregoing excavation and filling combines the earth material field slag field composite construction of construction, and the slag field demand can be divided into multilayer by measure, It is trapezoidal per layer cross section, is highly 10-15m, interlayer is provided with packway.
Foregoing excavation and filling combines the earth material field slag field composite construction of construction, and the slope ratio of the earth material filling building is 1:1.5-2.
Foregoing excavation and filling combines the earth material field slag field composite construction of construction, and the slope ratio that the slag field is filled is 1:1.5-2.
The beneficial effects of the utility model:
1st, the utility model uses earth material field and slag field composite construction, and the occupation of land of slag field is the part that earth material field is taken up an area, and is solved Many hydraulic engineerings of having determined are difficult to the problem for arranging slag field, while reduce land area, save engineering cost, have huge Economic benefit;
2nd, earth material is arranged in the side of composite construction, slag field is arranged in into composite construction opposite side by the utility model, just To the excavation of earth material when hydraulic engineering is filled and needs to utilize earth material;
3rd, the layer height of composite construction first of the present utility model is 10-15m, is ensured while composite construction capacity is ensured Directly structural top can be constructed;Slag field segments first layer can be set packway after filling and continue the second layer and fill.
Brief description of the drawings
Accompanying drawing 1 is structural representation of the present utility model;
Accompanying drawing 2 is construction technology figure of the present utility model;
Accompanying drawing 3 is construction technology figure of the present utility model;
Accompanying drawing 4 is construction technology figure of the present utility model;
Accompanying drawing 5 is construction technology figure of the present utility model;
Accompanying drawing 6 is the structural representation after earth material is transported.
Description of reference numerals:1- earth materials field, 2- earth materials, 3- slags field, 4- original places upper thread, above-ground route after 5- is excavated.
Embodiment
The utility model is further described with reference to the accompanying drawings and examples, but is not intended as to the utility model The foundation of limitation.
Embodiment of the present utility model:A kind of excavation and filling combines the earth material field slag field composite construction of construction, as shown in Figure 1, Include slag field 3 and earth material field 1, the occupation of land of slag field 3 is the part that earth material field is taken up an area.
Earth material 2 is excavated on the earth material field 1, slag field 3 is located at the side that the heatable adobe sleeping platform formed after earth material 2 is excavated in earth material field 1, opened The earth material 2 of digging is located at the opposite side of heatable adobe sleeping platform.
The slag field 3 demand can be divided into multilayer by measure(It is general to set 2 layers), it is trapezoidal per layer cross section, is highly 10- 15m, interlayer are provided with packway.
The slope ratio that the earth material 2 fills is 1:1.5-2.
The slope ratio that the slag field 3 is filled is 1:1.5-2.
The construction process of the utility model structure is as follows:First before not yet slag charge is filled using slag field 3, according to earth material Design yield and mining depth determine the outside line position of earth material field 1, and are opened from the outer edge of earth material field 1 to inner side by projected depth Cut the earth and expect 2(As shown in figures 1 to 6, above-ground route 5 after excavating is excavated to from original place upper thread 4)The side of earth material field 1 is filled, earth material 2 is filled out Slope ratio is built as 1:1.5-1:2, composite structural design height is highly must not exceed, stops excavating when earth material 2 can not continue to fill; Start after filling slag charge, slag charge is transported to and tamps and continue to fill slag in the ground above section of heatable adobe sleeping platform scope at the heatable adobe sleeping platform dug out Material, slag charge fill slope ratio with earth material filling building slope than identical, are 1:1.5-1:2, it highly must not exceed composite structural design height;With This continue simultaneously by earth material field 1 do not excavate part from outside to inner side gradually all excavate finish, excavated material fill to earth material 2 with The region vacated among slag charge, finished until design earth material filling building region is filled, be at the same time constantly transported to the slag charge of slag field 3 Also the space being newly excavated can be utilized to attack and occupy from outside to inner side to fill, until it is compound to complete overall earth material field 1 and slag field 3 Structure;Finally the earth material 2 that outside is filled is transported by design requirement, and reinforced to slag field is domatic, if demand in engineering Part earth material can be arranged in after end at the top of slag field and carry out second ploughing, so as to reach the utilizing status best to soil.

Claims (5)

1. a kind of excavation and filling combines the earth material field slag field composite construction of construction, it is characterised in that:Include slag field(3)With earth material field (1), slag field(3)Occupation of land is the part that earth material field is taken up an area.
2. excavation and filling according to claim 1 combines the earth material field slag field composite construction of construction, it is characterised in that:The earth material (1)Upper excavation earth material(2), slag field(3)Positioned at earth material field(1)Excavate earth material(2)The side of the heatable adobe sleeping platform formed afterwards, the soil of excavation Material(2)Positioned at the opposite side of heatable adobe sleeping platform.
3. excavation and filling according to claim 2 combines the earth material field slag field composite construction of construction, it is characterised in that:The slag field (3)It demand can be divided into multilayer by measure, be trapezoidal per layer cross section, be highly 10-15m, interlayer is provided with packway.
4. excavation and filling according to claim 2 combines the earth material field slag field composite construction of construction, it is characterised in that:The earth material (2)The slope ratio filled is 1:1.5-2.
5. excavation and filling according to claim 2 combines the earth material field slag field composite construction of construction, it is characterised in that:The slag field (3)The slope ratio filled is 1:1.5-2.
CN201720227084.1U 2017-03-09 2017-03-09 A kind of excavation and filling combines the earth material field slag field composite construction of construction Active CN206646513U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720227084.1U CN206646513U (en) 2017-03-09 2017-03-09 A kind of excavation and filling combines the earth material field slag field composite construction of construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720227084.1U CN206646513U (en) 2017-03-09 2017-03-09 A kind of excavation and filling combines the earth material field slag field composite construction of construction

Publications (1)

Publication Number Publication Date
CN206646513U true CN206646513U (en) 2017-11-17

Family

ID=60280991

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720227084.1U Active CN206646513U (en) 2017-03-09 2017-03-09 A kind of excavation and filling combines the earth material field slag field composite construction of construction

Country Status (1)

Country Link
CN (1) CN206646513U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106836229A (en) * 2017-03-09 2017-06-13 中国电建集团贵阳勘测设计研究院有限公司 A kind of excavation and filling combines the earth material slag composite construction and construction technology of construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106836229A (en) * 2017-03-09 2017-06-13 中国电建集团贵阳勘测设计研究院有限公司 A kind of excavation and filling combines the earth material slag composite construction and construction technology of construction

Similar Documents

Publication Publication Date Title
CN102124163B (en) Method for constructing a chair-type, self-supported earth retaining wall
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN105178327A (en) Composite retaining structure of foundation pit project and construction method thereof
CN105155558A (en) Combined retaining structure and construction method thereof
CN104763433A (en) Underground excavation construction method of large-span subway station in flexible-top and hard-bottom stratum
CN105696427A (en) Construction method for reinforcing newly-built railway karst foundation and roadbed structure thereof
CN103775110A (en) Underground excavation construction method for multilayer underground space of soft soil area
CN204401385U (en) A kind of road structure processing Deep Thick Soft Ground karst foundation
CN109898520A (en) A kind of heavy wall construction method
CN102505704A (en) Large open caisson construction method in soft geological shaft
CN102943488A (en) Soft soil area large area greening non-excavation implementing underground space construction method
CN104895111B (en) The construction method of integrated pipe canal in weak soil ground
CN110080169A (en) A kind of construction method reclaimed fields from the sea utilized based on basement
CN104532714B (en) Roadbed structure for treating deep soft soil karst foundation
CN211500658U (en) Shallow tunnel supporting construction that nearly connects that buries suitable for sand ground
CN204940298U (en) A kind of Composite Enclosure Structure of base pit engineering
CN104929142A (en) Combined cofferdam structure and building construction method thereof
CN204753262U (en) A fender structure on high embankment of existing railway
CN109371919A (en) The native stone water-retaining structure of seepage prevention of core wall
CN206646513U (en) A kind of excavation and filling combines the earth material field slag field composite construction of construction
CN109268063A (en) The method for constructing gob side entry retaining shield lane wall using drift-sand filling net cage
CN205382942U (en) Multilayer underground space curtain posture subsurface excavated construction's supporting construction under existing facility
CN107881987A (en) Deep covering layer top panel Rockfill Dam based moisture barrier structure
CN209429056U (en) The native stone water-retaining structure of seepage prevention of core wall
CN208293588U (en) A kind of Cut Slopes of Expansive Soil reinforcement formula, which is changed, fills out compages

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant