CN206636234U - Highland and severe cold cut-pff wall winter construction slurry feeding device - Google Patents
Highland and severe cold cut-pff wall winter construction slurry feeding device Download PDFInfo
- Publication number
- CN206636234U CN206636234U CN201720367825.6U CN201720367825U CN206636234U CN 206636234 U CN206636234 U CN 206636234U CN 201720367825 U CN201720367825 U CN 201720367825U CN 206636234 U CN206636234 U CN 206636234U
- Authority
- CN
- China
- Prior art keywords
- slurry
- mud
- mud pit
- slurry pipeline
- highland
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
A kind of highland and severe cold cut-pff wall winter construction slurry feeding device, including the first mud pit, the second mud pit is provided with outside first mud pit, " people " font slurry pipeline is equipped with along impervious wall construction axis, form the gradient >=10% on the slope that first slurry pipeline of " people " font slurry pipeline and the second slurry pipeline are formed with horizontal plane, second mud pit is connected by mud slurry pipeline with the slurry supply pump on the second mud pit, the gradient >=10% on the slope that mud slurry pipeline is formed with horizontal plane.Highland and severe cold cut-pff wall winter construction slurry feeding device provided by the utility model, can solve the problems, such as that pulp feeding system freezes, it is ensured that frigid plateau region cut-pff wall and the supply of diaphram wall winter construction mud, improve the requirement of efficiency of construction and construction speed.
Description
Technical field
Impervious wall construction field is the utility model is related to, especially a kind of highland and severe cold cut-pff wall winter construction is used for slurry dress
Put.
Background technology
Cut-pff wall and diaphram wall winter construction, not only tend to be universal interiorly, and it is high on plateaus such as Xinjiang, Tibet
It is related to extensively in cold area.Construction occurs for systems such as slurries in frigid plateau region cut-pff wall and diaphram wall winter construction
Situation about freezing, but temperature long in the frigid plateau region sunshine-duration is relatively low, and annual frost-free period is shorter, and day and night temperature is big to wait spy
Point, the temperature most of the time, often pulp feeding system occurred in cut-pff wall and diaphram wall winter construction below -28 degrees Celsius
Seriously freeze, its cut-pff wall and diaphram wall winter is not constructed, have a strong impact on construction speed.Particularly Xinjiang, Tibet
Deng winter construction in the cut-pff wall and diaphram wall of frigid plateau region.Construction to cut-pff wall and diaphram wall is brought very
Big difficulty.
The content of the invention
Technical problem to be solved in the utility model is to provide a kind of highland and severe cold cut-pff wall winter construction and filled for slurry
Put, can solve the problems, such as that pulp feeding system freezes, it is ensured that frigid plateau region cut-pff wall and diaphram wall winter construction mud
Slurry supply, improve the requirement of efficiency of construction and construction speed.
In order to solve the above technical problems, technical scheme is used by the utility model:A kind of highland and severe cold cut-pff wall winter
Season construction slurry feeding device, including the first mud pit, the first mud pit is provided with the second mud pit outside, along impervious wall construction axis
" people " font slurry pipeline is equipped with, forms first slurry pipeline and the second slurry pipeline and level of " people " font slurry pipeline
Gradient >=10%, the second mud pit on the slope that face is formed is connected by mud slurry pipeline with the slurry supply pump on the second mud pit,
The gradient >=10% on the slope that mud slurry pipeline is formed with horizontal plane.
Impervious wall construction axis is located at the top of " people " font slurry pipeline.
Another structure of the present utility model is:
A kind of highland and severe cold cut-pff wall winter construction slurry feeding device, including the first mud pit, the first mud pit are set outside
There is the second mud pit, " one " font slurry pipeline is equipped with along impervious wall construction axis, the slope of " one " font slurry pipeline
Gradient >=10%, the second mud pit is connected by mud slurry pipeline with the slurry supply pump on the second mud pit, " one " font flow inlet
The gradient >=10% on the slope that road is formed with horizontal plane.
Preferably, impervious wall construction axis is located at the lower section of " one " font slurry pipeline.
Preferably, the grout outlet of mud pulper connects with the second mud pit.
Preferably, it is provided with butterfly valve on mud pulper.
Preferably, multiple iodine-tungsten lamps are installed in the second mud pit.
Highland and severe cold cut-pff wall winter construction slurry feeding device provided by the utility model, has the beneficial effect that:
1st, " people " font or " one " font slurry pipeline of the gradient >=10% are laid along impervious wall construction axis, is terminated for slurry
Afterwards, the remaining slurry in pipeline is flowed automatically in cut-pff wall slotted eye or in mud pit, in pipeline will not surplus mud, in frigid plateau region
Construction can effectively be provided for slurry, ensure that cut-pff wall and diaphram wall winter normally construct.
2nd, butterfly valve is provided with mud pulper, closes its valve during slurrying, slurrying makes its valve after terminating
Open, the remaining mud in pulper is excluded, avoids remaining mud in mud pulper from freezing in the case of microthermal climate, solve
The low easy freezing of frigid plateau region temperature of having determined supplies the damage of slurry equipment to impervious wall construction, improves the utilization rate of equipment.
3rd, it is simple to operate, it is easy for construction, improve operating efficiency.
4th, the frozen slurry pipeline of daily processing is avoided.Efficiency of construction is greatly improved, the work for reducing employee is strong
Degree.
Brief description of the drawings
The utility model is described in further detail with reference to the accompanying drawings and examples:
Fig. 1 is the structural representation of the utility model embodiment one;
Fig. 2 is the structural representation of the utility model embodiment two.
Embodiment
Embodiment one
As shown in figure 1, a kind of highland and severe cold cut-pff wall winter construction slurry feeding device, including the first mud pit 1, the first mud
The second mud pit 2 is provided with outside stock tank 1, " people " font slurry pipeline is equipped with along impervious wall construction axis 5, forms " people " font
Gradient >=10%, the second mud on the slope that the first slurry pipeline 6 of slurry pipeline and the second slurry pipeline 7 are formed with horizontal plane
Pond 2 is connected by mud slurry pipeline 8 with the slurry supply pump 9 on the second mud pit 2, and mud slurry pipeline 8 is formed with horizontal plane
The gradient >=10% on slope.
Impervious wall construction axis 5 is located at the top of " people " font slurry pipeline.
First slurry pipeline 6, the second slurry pipeline 7 and mud slurry pipeline 8 use specification for DN150 steel pipe laying and
Into.
The peak of " people " font slurry pipeline is arranged at the point midway of impervious wall construction axis 5.
After terminating for slurry, the remaining slurry in " people " font slurry pipeline is flowed automatically in cut-pff wall slotted eye or in the second mud pit 2,
Will not surplus mud in pipeline.
When impervious wall construction place physical features than it is shallower or broad when use structure described in embodiment one.
Embodiment two
As shown in Fig. 2 a kind of highland and severe cold cut-pff wall winter construction slurry feeding device, including the first mud pit 1, its feature
It is:The second mud pit 2 is provided with outside first mud pit 1, " one " font slurry pipeline is equipped with along impervious wall construction axis 5
10, gradient >=10%, the second mud pit 2 on the slope of " one " font slurry pipeline 10 passes through the mud of mud slurry pipeline 8 and second
Slurry supply pump 9 on pond 2 connects, the gradient >=10% on the slope that " one " font slurry pipeline 10 is formed with horizontal plane.
Impervious wall construction axis 5 is located at the lower section of " one " font slurry pipeline 10.
After terminating for slurry, the remaining slurry in " one " font slurry pipeline 10 flows automatically in cut-pff wall slotted eye or the second mud pit 2
It is interior, will not surplus mud in pipeline.
When impervious wall construction place is narrow, the second mud pit need to be built on the hillside of cut-pff wall platform, its position
When higher than cut-pff wall platform, using structure described in embodiment two.
In the various embodiments described above,
The grout outlet 4 of mud pulper 3 connects with the second mud pit 2.
Butterfly valve 11 is provided with mud pulper 3, closes butterfly valve 11 during slurrying, slurrying terminate after by butterfly valve
11 are opened, and the remaining mud in mud pulper 3 is excluded, and avoid in mud pulper 3 remaining mud in the feelings of microthermal climate
Freeze under condition.
The iodine-tungsten lamp that 3~4 power are 1000 kilowatts is installed in the second mud pit 2 to warm oneself.
The storage slurry amount of second mud pit 2 is about 100 cubic metres, and is up capped the insulation of foam color steel tile.
Second mud pit 2 is the special mud pit of winter construction.
Claims (7)
1. a kind of highland and severe cold cut-pff wall winter construction slurry feeding device, including the first mud pit(1), it is characterised in that:First
Mud pit(1)It is provided with the second mud pit outside(2), along impervious wall construction axis(5)" people " font slurry pipeline is equipped with, is formed
First slurry pipeline of " people " font slurry pipeline(6)With the second slurry pipeline(7)The gradient on the slope formed with horizontal plane >=
10%, the second mud pit(2)Pass through mud slurry pipeline(8)With the second mud pit(2)On slurry supply pump(9)Connection, mud is for slurry
Pipeline(8)The gradient >=10% on the slope formed with horizontal plane.
2. highland and severe cold cut-pff wall winter construction slurry feeding device according to claim 1, it is characterised in that:Cut-pff wall is applied
Work axis(5)Positioned at the top of " people " font slurry pipeline.
3. a kind of highland and severe cold cut-pff wall winter construction slurry feeding device, including the first mud pit(1), it is characterised in that:First
Mud pit(1)It is provided with the second mud pit outside(2), along impervious wall construction axis(5)It is equipped with " one " font slurry pipeline(10),
" one " font slurry pipeline(10)Slope gradient >=10%, the second mud pit(2)Pass through mud slurry pipeline(8)With second
Mud pit(2)On slurry supply pump(9)Connection, " one " font slurry pipeline(10)The gradient >=10% on the slope formed with horizontal plane.
4. highland and severe cold cut-pff wall winter construction slurry feeding device according to claim 3, it is characterised in that:Cut-pff wall is applied
Work axis(5)Positioned at " one " font slurry pipeline(10)Lower section.
5. the highland and severe cold cut-pff wall winter construction slurry feeding device according to claim 1 or 3, it is characterised in that:Mud
Pulper(3)Grout outlet(4)With the second mud pit(2)Connection.
6. the highland and severe cold cut-pff wall winter construction slurry feeding device according to claim 1 or 3, it is characterised in that:Mud
Pulper(3)On be provided with butterfly valve(11).
7. the highland and severe cold cut-pff wall winter construction slurry feeding device according to claim 1 or 3, it is characterised in that:Second
Mud pit(2)Multiple iodine-tungsten lamps are inside installed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720367825.6U CN206636234U (en) | 2017-04-10 | 2017-04-10 | Highland and severe cold cut-pff wall winter construction slurry feeding device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720367825.6U CN206636234U (en) | 2017-04-10 | 2017-04-10 | Highland and severe cold cut-pff wall winter construction slurry feeding device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206636234U true CN206636234U (en) | 2017-11-14 |
Family
ID=60247873
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720367825.6U Active CN206636234U (en) | 2017-04-10 | 2017-04-10 | Highland and severe cold cut-pff wall winter construction slurry feeding device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206636234U (en) |
-
2017
- 2017-04-10 CN CN201720367825.6U patent/CN206636234U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104605740A (en) | Anti-freezing water dispenser cold cylinder | |
CN102410686A (en) | Subcooling water circulating system | |
CN206636234U (en) | Highland and severe cold cut-pff wall winter construction slurry feeding device | |
CN203336881U (en) | Improved evaporative type condenser water supply cycling system | |
CN105444305A (en) | Supercooling relieving device adopting high-pressure gas jet mode | |
CN104764230A (en) | Anti-freezing solar water supply device | |
CN208024993U (en) | Flat section is flow automatically water-bound under a kind of pressure pipeline | |
CN105953289A (en) | Heat pump system utilizing latent heat of solidification | |
CN101017017A (en) | Regional building air-conditioning system capable of transferring cool capacity of ocean by underground water-bearing layers in coastal area | |
CN204080938U (en) | There is the siphonic water-collecting well of hot water return passage | |
CN204141778U (en) | Sprinkler in a kind of chilled water storage system | |
CN204574656U (en) | A kind of de-supercooling device adopting high pressure gas jet flow mode | |
CN205776125U (en) | Spillway gate recess ice breaker in winter | |
CN201828067U (en) | Intelligent antifreeze draining device of solar water heater pipeline | |
CN204080939U (en) | A kind of siphonic water-collecting well | |
CN204648717U (en) | Anti-freeze solar water supply installation | |
CN208917920U (en) | Anti-freezing device of running water pipe | |
CN206919499U (en) | Water circulation freezer | |
CN204141772U (en) | Constant-current stabilizer in a kind of chilled water storage system | |
CN205842068U (en) | A kind of exchange joint in earth-source hot-pump system | |
CN206905294U (en) | A kind of heat-energy recovering apparatus of quick heating cold water | |
CN204445429U (en) | A kind of water dispenser cooling cylinder of making ice | |
CN207018259U (en) | A kind of efficient device for being pressurized water circulating pump fluid energy-saving | |
CN201715617U (en) | Surface intake and automatic emptying solar water heater | |
CN202432789U (en) | Low-temperature cooling water circulation system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |