CN206618013U - Heating system family end temperature controller test platform - Google Patents

Heating system family end temperature controller test platform Download PDF

Info

Publication number
CN206618013U
CN206618013U CN201720338775.9U CN201720338775U CN206618013U CN 206618013 U CN206618013 U CN 206618013U CN 201720338775 U CN201720338775 U CN 201720338775U CN 206618013 U CN206618013 U CN 206618013U
Authority
CN
China
Prior art keywords
heating
test platform
end temperature
interface
family end
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720338775.9U
Other languages
Chinese (zh)
Inventor
黄进
张晓琴
杨承志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Industry Polytechnic College
Original Assignee
Chongqing Industry Polytechnic College
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Industry Polytechnic College filed Critical Chongqing Industry Polytechnic College
Priority to CN201720338775.9U priority Critical patent/CN206618013U/en
Application granted granted Critical
Publication of CN206618013U publication Critical patent/CN206618013U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of heating system family end temperature controller test platform, including test platform, heating simulation system is provided with test platform, the simulation system that heats includes heating water tank and building model, fin and temperature detector are provided with building model, the delivery port of the heating water tank is connected by the feed water inlet of water supply line and fin, the discharge outlet of fin is connected by drainage pipeline with heating the water inlet of water tank, and water circulating pump, calorimeter and flow control valve are provided with water supply line;Control unit interface includes host computer interface, data acquisition interface and control interface, and controller is connected by controller machine interface with host computer, temperature detector, calorimeter, water circulating pump and flow control valve.Beneficial effect:Using heating system family of the present utility model end temperature controller test platform, the convenient heating system family end temperature controller to big quantity is detected, and can carry out various instruction testings to controller, is easy to tester to be judged.

Description

Heating system family end temperature controller test platform
Technical field
The utility model is related to heating system field, and a kind of more particularly to heating system family end temperature controller test is flat Platform.
Background technology
Heating temperature control system is to utilize automatic control technology and mechanics of communication, facilitates user's control heat supply valve to open Close, transfer the files, while can enter the collection and display of the signals such as trip temperature, flow, user can also be according to the situation of oneself voluntarily Indoor temperature is set, controller carries out room temperature regulation automatically.Central heating temperature control system in city is also required to carry out far Range monitoring and network management, realize the intellectuality of heating system.
So, heating system family end temperature controller finds broad application in Modern Smart Home control.But, to protect Testimony warms up temperature control system and can effectively worked, it is necessary to be detected to it before heating temperature control system is installed.It is existing Mostly in technology is the detection to whole heating system, also the test dress without specially test heating system family end temperature controller Put.
Utility model content
To solve above technical problem, the utility model provides a kind of heating system family end temperature controller test platform, Heating system family end temperature controller can be tested by the test platform.
Technical scheme is as follows:
A kind of heating system family end temperature controller test platform, its key is:Including test platform, on test platform Heating simulation system and control unit interface are provided with, heating simulation system is included in heating water tank and building model, building model Fin and temperature detector are provided with, the delivery port of the heating water tank is connected by the feed water inlet of water supply line and fin, The discharge outlet of fin is connected by drainage pipeline with heating the water inlet of water tank, and water circulating pump, heat are provided with water supply line Scale and flow control valve;
The control unit interface includes host computer interface, data acquisition interface and control interface, and controller passes through host computer Interface is connected with host computer, and controller is connected by data acquisition interface with temperature detector and calorimeter, and controller passes through control Interface processed is connected with water circulating pump and flow control valve.
Said structure is used, as long as controller is inserted in control interface, host computer can just be entered the operating instructions to controller, So, it is easy to quickly test substantial amounts of controller.Also, by host computer to controller input instruction, it is easy to tester defeated Enter various instructions, it is convenient that controller is tested in all directions.
Controller supplies water according to operational order driving cycle water pump and flow control valve to fin.Controller is according to temperature Temperature in the temperature information control flow control valve that detector is detected in real time, regulation building model.
The caloric information for the hot water that the calorimeter in the house that controller detects temperature detector is detected is sent to Position machine is shown.It is easy to tester to judge whether controller is working properly.
Further, the recirculated water is set gradually between the delivery port of the heating water tank and the feed water inlet of fin Pump, temperature detector, calorimeter and flow control valve.
Using said structure, one end that calorimeter is arranged on into feed water inlet can more accurately detect the heat of supply fin Information, the influence of discharge water circulating pump and flow control valve to caloric information.It is easy to tester to be judged.
Further, detector is provided with the test platform, the detector is oscillograph, oscillograph is used to detect The waveform of the control signal of flow control valve.
Using said structure, whether the input that can judge flow control valve by detector has control signal input, It is avoided that flow control valve occur is not turned on, and water circulating pump continuous firing, cause the hydraulic pressure in water supply line to raise, damage Bad test platform.
Further, temperature sensor is provided with outside the building model, the temperature sensor and the controller Interface is connected.
Using said structure, temperature sensor can obtain the environment temperature around building model, and upper function is according to the ring Influence of the border temperature discharge environment to test data.
Further, the model YG-RLMC-20 of calorimeter ultrasonic calorimeter.
Using said structure, the small power consumption of calorimeter, precision is high, and the real current in channel of acoustic wave areflexia face are without hindrance Gear, particularly suitable Chinese heating water quality and working condition requirement, crushing are small;Completely not by impurity, chemical substance and magnetic in medium Effect of Materials, runs sufficiently stable reliable.
Further, the model WRV-8220B of the flow control valve electronic two-way valve of two-position formula.
Using said structure, the WRV-8220B electronic two-way valve of two-position formula uses synchronous machine drives, in place automatically Power-off, power consumption is low, flexible movements, is avoided that water hammer when there is closing valve;And valve inner is using unique bullet Property double-layer sealing structure, leakage is few, long lifespan;Valve body has the discharge characteristic of equal percentage.
Further, digital thermometer is provided with the heating water tank, the display screen of the digital thermometer is located at described On the outer wall for heating water tank.
Using said structure, the temperature in heating water tank can be detected, as long as reaching that test is needed to the temperature in heating water tank Ask, you can start test, saved energy resource consumption.
Further, the water circulating pump is hot and cold water protected type pressurization cycle pump.
Using said structure, the noise of water circulating pump can be reduced, is easy to experiment test to use, and service life is long.
Beneficial effect:It is convenient to big quantity using heating system family of the present utility model end temperature controller test platform Heating system family end temperature controller detected, and various instruction testings can be carried out to controller, be easy to tester Judged.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model;
Fig. 2 is controller system block diagram of the present utility model;
Fig. 3 is the schematic diagram of heating simulation system of the present utility model.
Embodiment
With reference to embodiment and accompanying drawing, the utility model is described in further detail.
As Figure 1-3, a kind of heating system family end temperature controller test platform, including test platform 1, test platform Heating simulation system and control unit interface 9 are provided with 1.
The simulation system that heats includes heating water tank 2 and building model 3, and building model 3 is internally provided with fin 3a and temperature Spend outside detector 3b, building model 3 and be provided with temperature sensor 3c.
Heat and digital thermometer 2a is provided with water tank 2, digital thermometer 2a display screen is located at the heating water tank 2 On outer wall.The delivery port of heating water tank 2 is connected by water supply line 4 with fin 3a feed water inlet, fin 3a discharge outlet It is connected by drainage pipeline 5 with heating the water inlet of water tank 2.
The water circulating pump 6, temperature are set gradually between the delivery port of the heating water tank 2 and fin 3a feed water inlet Detector 3b, calorimeter 7 and flow control valve 8.The water circulating pump 6 is hot and cold water protected type pressurization cycle pump, and calorimeter 7 is YG-RLMC-20 ultrasonic calorimeter, flow control valve is the electronic two-way valve of WRV-8220B two-positions formula.
The control unit interface 9 includes host computer interface, data acquisition interface and control interface, and controller passes through host computer Interface is connected with host computer, and controller is connected by data acquisition interface with temperature detector 3b, temperature sensor 3c and calorimeter 7 Connect, controller is connected by control interface with water circulating pump 6 and flow control valve 8.
Detector 10 is provided between the flow control valve 8 and control interface, the detector 10 is oscillograph, the inspection Surveying device is used for the waveform of control signal of detection flows control valve 8.
Specific workflow is as follows:First, by controller inserting controller interface 9, controller and host computer, temperature are made Detector 3b, temperature sensor 3c, calorimeter 7, water circulating pump 6 and flow control valve 8 are connected.
Then, start heating water tank 2, heated to the water in heating water tank 2, observation digital thermometer 2a reading, When the temperature of water reaches 60 degrees Celsius, control instruction is inputted to controller by host computer.Controller is instructed according to controller Start water circulating pump 6 to fin 3a water fillings.Controller controls to flow into fin 3a water by flow control valve 8, so that Control flows into fin 3a heat, and controller gathers injection fin 3a caloric information by calorimeter 7.
Controller gathers building model internal temperature and outside temperature respectively by temperature detector 3b and temperature sensor 3c Degree, and these temperature informations and caloric information are sent to host computer, host computer carries out data by these information to controller Analysis, draws the test result of controller.
Finally it should be noted that foregoing description is only preferred embodiment of the present utility model, the common skill of this area Art personnel on the premise of without prejudice to the utility model objective and claim, can make under enlightenment of the present utility model Represented as multiple types, such conversion is each fallen within protection domain of the present utility model.

Claims (8)

1. a kind of heating system family end temperature controller test platform, it is characterised in that:Including test platform (1), test platform (1) heating simulation system and control unit interface (9) are provided with, heating simulation system includes heating water tank (2) and building model (3) fin (3a) and temperature detector (3b), are provided with building model (3), the delivery port of the heating water tank (2) is by supplying Waterpipe (4) is connected with the feed water inlet of fin (3a), and the discharge outlet of fin (3a) passes through drainage pipeline (5) and heating water tank (2) water circulating pump (6), calorimeter (7) and flow control valve (8) are provided with water inlet connection, water supply line (4);
The control unit interface (9) includes host computer interface, data acquisition interface and control interface, and controller is connect by host computer Mouth is connected with host computer, and controller is connected by data acquisition interface with temperature detector (3b) and calorimeter (7), and controller leads to Control interface is crossed to be connected with water circulating pump (6) and flow control valve (8).
2. heating system family end temperature controller test platform according to claim 1, it is characterised in that:The heating water tank (2) water circulating pump (6), temperature detector (3b), heat are set gradually between delivery port and the feed water inlet of fin (3a) Scale (7) and flow control valve (8).
3. heating system family end temperature controller test platform according to claim 1, it is characterised in that:The test platform (1) detector (10) is provided with, the detector (10) is oscillograph, oscillograph is used for the control of detection flows control valve (8) The waveform of signal.
4. according to any heating system family end temperature controller test platforms of claim 1-3, it is characterised in that:The room Temperature sensor (3c) is provided with outside room model (3), the temperature sensor (3c) is connected with the control unit interface (9).
5. according to any heating system family end temperature controller test platforms of claim 1-3, it is characterised in that:The heat The model YG-RLMC-20 of scale (7) ultrasonic calorimeter.
6. according to any heating system family end temperature controller test platforms of claim 1-3, it is characterised in that:The stream The model WRV-8220B of control valve (8) the electronic two-way valve of two-position formula.
7. according to any heating system family end temperature controller test platforms of claim 1-3, it is characterised in that:It is described to add Digital thermometer (2a) is provided with boiler (2), the display screen of the digital thermometer (2a) is located at the outer of the heating water tank (2) On wall.
8. according to any heating system family end temperature controller test platforms of claim 1-3, it is characterised in that:It is described to follow Ring water pump (6) is hot and cold water protected type pressurization cycle pump.
CN201720338775.9U 2017-04-01 2017-04-01 Heating system family end temperature controller test platform Expired - Fee Related CN206618013U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720338775.9U CN206618013U (en) 2017-04-01 2017-04-01 Heating system family end temperature controller test platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720338775.9U CN206618013U (en) 2017-04-01 2017-04-01 Heating system family end temperature controller test platform

Publications (1)

Publication Number Publication Date
CN206618013U true CN206618013U (en) 2017-11-07

Family

ID=60235130

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720338775.9U Expired - Fee Related CN206618013U (en) 2017-04-01 2017-04-01 Heating system family end temperature controller test platform

Country Status (1)

Country Link
CN (1) CN206618013U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110375381A (en) * 2019-08-07 2019-10-25 山东交通学院 A kind of intelligent temperature control system and its control method based on flow control

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110375381A (en) * 2019-08-07 2019-10-25 山东交通学院 A kind of intelligent temperature control system and its control method based on flow control

Similar Documents

Publication Publication Date Title
CN100578186C (en) Ground source heat pump heat exchanger heat-transfer performance test device and its measuring and controlling method
CN204359758U (en) A kind of simulation coal yard determining coal ignitability device
CN205352721U (en) Heat pump set comprehensive properties testing system
CN201508338U (en) Soil thermal property parameter measuring device
CN204203709U (en) A kind of ground thermal property tester based on PLC
CN201166615Y (en) Tester for exchanging heat of buried tube of earth source heat pump
CN101887040A (en) Synchronous cold/thermal response ground thermal property tester
CN106885377A (en) Water heater and its control method
CN107940762A (en) A kind of leakage detection method for water heater and water heater
CN106839417A (en) A kind of burnt gas wall hanging furnace and its supplying hot water method
CN106871457A (en) Water heater and its control method
CN102901588B (en) Heat quantity calculating device and heating ventilation air conditioning system
CN206618013U (en) Heating system family end temperature controller test platform
CN203587534U (en) Detection device for buried pipe system of ground source heat pump
CN103616405B (en) A kind of pick-up unit to ground buried pipe of ground source heat pump system
CN202631464U (en) Buried pipe field heat exchange performance detecting and testing device
CN107101775A (en) Experimental rig for testing cooling water pump
CN105387506B (en) The safe heat-exchange system of deep-well low temperature nuclear heating reactor
CN204964306U (en) Testing platform of gas heater circulation pressure boost function
CN206637836U (en) A kind of burnt gas wall hanging furnace
CN202599618U (en) Device for testing tightness of geothermal pipelines in housing construction
CN203299154U (en) Variable-frequency heat pump type rock-soil thermophysical property tester
CN102087234B (en) Soil thermophysical property measuring instrument realizing constant power
CN101587023A (en) Tester of buried tube heat exchange capability and resistance based on earth source heat pump and testing method
CN210690095U (en) Closed energy well energy measurement appearance

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171107

Termination date: 20180401