CN206607553U - Improve waterproof dykes and dams of impact resistance - Google Patents

Improve waterproof dykes and dams of impact resistance Download PDF

Info

Publication number
CN206607553U
CN206607553U CN201720227090.7U CN201720227090U CN206607553U CN 206607553 U CN206607553 U CN 206607553U CN 201720227090 U CN201720227090 U CN 201720227090U CN 206607553 U CN206607553 U CN 206607553U
Authority
CN
China
Prior art keywords
water filling
filling port
domatic
dams
drainage channel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720227090.7U
Other languages
Chinese (zh)
Inventor
姚亮
赵守义
冉龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201720227090.7U priority Critical patent/CN206607553U/en
Application granted granted Critical
Publication of CN206607553U publication Critical patent/CN206607553U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model belongs to the technical field of dykes and dams technique and specifically relates to an improve water dam of impact resistance, including the dam body, the dam body is provided with first domatic and preceding slope, preceding domatic is divided into first domatic, perpendicular, second by last under to in proper order domatic, first domatic first water filling port that is equipped with a plurality of in line range, be equipped with the second water filling port that the in line was arranged on the perpendicular surface, second water filling port below is equipped with the second domatic, the dam body is inside to be equipped with dam body terminal surface looks vertically drainage channel, drainage channel communicates with each other with first water filling port, second water filling port. The utility model discloses set up a plurality of water filling port in the front on domatic, make the rivers impact force obtain certain decomposition to can reach the purpose of buffering the impact force, with water filling port and drainage channel intercommunication, make rivers get back to the river again, this kind of dyke and dam's design not only shock resistance is strong, saves a large amount of raw materials moreover, has reduced the construction cost of dyke and dam.

Description

A kind of waterproof dykes and dams for improving anti-impact force
Technical field
The utility model is related to dykes and dams technical field, more particularly to a kind of waterproof dykes and dams for improving anti-impact force.
Background technology
Dykes and dams refer to that waterproof blocks the building and structures of water, and modern dam mainly has two major classes:Earth and rockfill dam and coagulation Earth dam, in recent years, large-scale dykes and dams all use high-tech reinforced concrete construction.
The quality of dykes and dams affects the life of the people close to current, and the quality of dykes and dams largely depends on dykes and dams resistance water The ability of impulsive force is flowed, prior art is improves dam impact resistance, frequently with putting some crushed stones beside dam Mode, to alleviate the impulsive force of current, is also exactly the cylinder that circular arc is set on dykes and dams, the impulsive force of current is scatter Come, but there are some drawbacks in these these methods, the first, crushed stone is easily washed away by current, growth over time, stone Block is fewer and fewer, causes dam impact resistance more and more weaker, wastes very much raw material second, increases the manufacturing cost of dykes and dams Plus.
Utility model content
The purpose of this utility model is to solve the indifferent and dyke construction of dykes and dams anti-impact force in the prior art The shortcoming wasted raw material, and a kind of waterproof dykes and dams of the raising anti-impact force proposed.
To achieve these goals, the utility model employs following technical scheme:
A kind of waterproof dykes and dams for improving anti-impact force of design, including dam body, the dam body are provided with the first domatic and scarp slope Face, it is described it is preceding it is domatic be divided into first domatic, vertical plane from top to bottom, it is second domatic, described first domatic is provided with several First water filling port of arrangement in a row, the vertical plane is provided with below the second water filling port of arrangement in a row, second water filling port It is domatic provided with second, the drainage channel perpendicular with dam body end face, the drainage channel and the first note are provided with inside the dam body The mouth of a river, the second water filling port are communicated, and Accrete clearing device is additionally provided with the drainage channel, and one end of the dam body is provided with flood discharge passage, Provided with flood discharge door in the flood discharge passage.
It is preferred that, it is designed with shunting cylinder between the second water filling port described in each two, the shunting cylinder is fixed in vertically On face.
It is preferred that, first water filling port, the position of the second water filling port are correspondingly arranged.
It is preferred that, first water filling port, the second water filling port cross sectional shape are circular arc.
It is preferred that, the Accrete clearing device includes screw agitation shaft, and the screw agitation shaft two ends are fixed on by support bar In drainage channel, bearing is provided between the screw agitation shaft and support bar, the belt pulley of described screw agitation shaft one end passes through Belt pulley on the output shaft of belt and motor is connected, and drainage channel is connected with flood discharge passage, and screw agitation shaft is extended In flood discharge passage.
It is preferred that, first water filling port, the second water filling port are piled up by concrete and formed, and the most inner sleeve of water filling port There are PE pipes.
The utility model proposes a kind of raising anti-impact force waterproof dykes and dams, beneficial effect is:The utility model is adopted Used in the domatic of preceding domatic setting different gradient, and several water filling ports are set on domatic, water flow impact pressure is obtained necessarily Decomposition, and the purpose of cushion impact forces can be reached, water filling port is connected with drainage channel, current is come back to river, should The design not only strong shock resistance, and save big content of starting materials of dykes and dams is planted, the construction cost of dykes and dams is reduced.
Brief description of the drawings
Fig. 1 be the utility model proposes a kind of raising anti-impact force waterproof dykes and dams structural representation;
Fig. 2 be the utility model proposes a kind of raising anti-impact force waterproof dykes and dams profile.
In figure:Drainage channel 1, rear domatic 2, dam body 3, the first water filling port 4, first domatic 5, shunting cylinder 6, second it is domatic 7th, the second water filling port 8, vertical plane 9, dam body end face 10, flood discharge door 11, motor 12, screw agitation shaft 13.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the utility model embodiment is carried out Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of the utility model, rather than whole Embodiment.
Reference picture 1-2, a kind of waterproof dykes and dams of raising anti-impact force, including dam body 3, dam body 3 be provided with first domatic 2 and It is preceding domatic.
It is preceding it is domatic be divided into first domatic 5, vertical plane 9, second domatic 7 from top to bottom, first domatic 5 is provided with several First water filling port 4 of arrangement in a row, vertical plane 9 be provided with arrangement in a row the second water filling port 8, the second water filling port of each two 8 it Between be designed with shunting cylinder 6, shunting cylinder 6 is fixed on vertical plane 9, the impulsive force for decomposing current, under the second water filling port 8 Side is provided with second domatic 7, and the inside of dam body 3 is provided with the drainage channel 1 perpendicular with dam body end face 10, the note of drainage channel 1 and first The mouth of a river 4, the second water filling port 8 are communicated, and the first water filling port 4, the position of the second water filling port 8 are correspondingly arranged, when simultaneously current enter the When one water filling port 4, the second water filling port 8, two strands of different current of direction mutually impact, and the impulsive force of current is spread out, the One water filling port 4, the cross sectional shape of the second water filling port 8 are circular arc, have certain cushioning effect, first water filling to current The 4, second water filling port 8 of mouth is piled up by concrete to be formed, and the most inner side of water filling port is cased with PE pipes, prevents that water filling port from being invaded throughout the year Erosion, cause opening it is increasing, rubber ring is fixed by screws in the edge of water filling port, drainage channel 1 and is additionally provided with desilting Device, for clearing up the sludge that current are taken on dykes and dams, Accrete clearing device includes screw agitation shaft 13, and the two ends of screw agitation shaft 13 lead to Cross support bar to be fixed in drainage channel 1, bearing is provided between screw agitation shaft 13 and support bar, the one end of screw agitation shaft 13 Belt pulley is connected by belt with the belt pulley on the output shaft of motor 12, and drainage channel 1 is connected with flood discharge passage, and spiral shell Rotation agitating shaft 13 is extended in flood discharge passage, and one end of dam body 3 is provided with flood discharge passage, the flood discharge passage provided with flood discharge door 11, water When flowing through many, for flood discharge.
Operation principle:If the utility model is in use, when domatic before less water impact dykes and dams, current are first by Two domatic 7 bufferings, are then split cylinder 6 and separate, and inject the second water filling port 8, then again by the second of circular arc The buffering of water filling port 8 enters in drainage channel 1, finally comes back to river;When current it is more when bringing, current respectively enter One water filling port 4, the second water filling port 8, because two water filling port positions are corresponding, the current of both direction mutually hit, and make current Impulsive force disperseed, finally enter drainage channel 1, flow back in river.
It is described above, only the utility model preferably embodiment, but protection domain of the present utility model is not This is confined to, any one skilled in the art is in the technical scope that the utility model is disclosed, according to this practicality New technical scheme and its utility model design are subject to equivalent substitution or change, should all cover in protection model of the present utility model Within enclosing.

Claims (6)

1. a kind of waterproof dykes and dams for improving anti-impact force, including dam body(3), the dam body(3)It is provided with first domatic(2)And it is preceding It is domatic, it is characterised in that described preceding domatic to be divided into first from top to bottom domatic(5), vertical plane(9), it is second domatic(7), Described first is domatic(5)The first water filling port provided with several arrangement in a row(4), the vertical plane(9)It is provided with arrangement in a row The second water filling port(8), second water filling port(8)Lower section is domatic provided with second(7), the dam body(3)Inside is provided with and dam Body end face(10)Perpendicular drainage channel(1), the drainage channel(1)With the first water filling port(4), the second water filling port(8)Phase It is logical, the drainage channel(1)Inside it is additionally provided with Accrete clearing device, the dam body(3)One end be provided with flood discharge passage, in the flood discharge passage Provided with flood discharge door(11).
2. a kind of waterproof dykes and dams for improving anti-impact force according to claim 1, it is characterised in that second described in each two Water filling port(8)Between be designed with shunt cylinder(6), the shunting cylinder(6)It is fixed in vertical plane(9)On.
3. a kind of waterproof dykes and dams for improving anti-impact force according to claim 1, it is characterised in that first water filling port (4), the second water filling port(8)Position be correspondingly arranged.
4. a kind of waterproof dykes and dams for improving anti-impact force according to claim 3, it is characterised in that first water filling port (4), the second water filling port(8)Cross sectional shape is circular arc.
5. a kind of waterproof dykes and dams for improving anti-impact force according to claim 1, it is characterised in that the Accrete clearing device bag Include screw agitation shaft(13), the screw agitation shaft(13)Two ends are fixed on drainage channel by support bar(1)It is interior, the spiral Agitating shaft(13)Bearing, the screw agitation shaft are provided between support bar(13)The belt pulley of one end passes through belt and motor (12)Output shaft on belt pulley connection, and drainage channel(1)Connected with flood discharge passage, and screw agitation shaft(13)Extend In flood discharge passage.
6. a kind of waterproof dykes and dams for improving anti-impact force according to claim 1, it is characterised in that first water filling port (4), the second water filling port(8)Piled up and formed by concrete, and the most inner side of water filling port is cased with PE pipes.
CN201720227090.7U 2017-03-09 2017-03-09 Improve waterproof dykes and dams of impact resistance Expired - Fee Related CN206607553U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720227090.7U CN206607553U (en) 2017-03-09 2017-03-09 Improve waterproof dykes and dams of impact resistance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720227090.7U CN206607553U (en) 2017-03-09 2017-03-09 Improve waterproof dykes and dams of impact resistance

Publications (1)

Publication Number Publication Date
CN206607553U true CN206607553U (en) 2017-11-03

Family

ID=60164870

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720227090.7U Expired - Fee Related CN206607553U (en) 2017-03-09 2017-03-09 Improve waterproof dykes and dams of impact resistance

Country Status (1)

Country Link
CN (1) CN206607553U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107476354A (en) * 2017-08-11 2017-12-15 上海岩土工程勘察设计研究院有限公司 Using etc. for pier base model prediction overlength Settlement of Pile Groups amount computational methods

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107476354A (en) * 2017-08-11 2017-12-15 上海岩土工程勘察设计研究院有限公司 Using etc. for pier base model prediction overlength Settlement of Pile Groups amount computational methods

Similar Documents

Publication Publication Date Title
KR101579302B1 (en) It is a natural eco-friendly method to purify contaminated river water while producing natural ecosystem by utilizing the automatic sludge sedimentation sludge discharge passage.
CN101514547B (en) Technology for protecting slope of dam
CN203782664U (en) Anti-scour structure of sandy foundation water gate
CN206607553U (en) Improve waterproof dykes and dams of impact resistance
CN103882838A (en) Sediment releasing method for water intake of low-head river channel pivotal power station
CN103882839B (en) A kind of sand flushing system of low water head river channel hinge powerplant intakes
CN209873738U (en) A manger plate dam for hydraulic and hydroelectric engineering
CN206635847U (en) A kind of foundation ditch dredging markets embankment structure
CN208039174U (en) Flume steep slope section energy dissipater
CN216839641U (en) River course dredging device for hydraulic engineering
CN204810884U (en) Saline -alkali soil improves structure
CN202559296U (en) Hollow triangular cone of river dyke shore closure
CN207672647U (en) Hydraulic engineering dredger
CN103938585A (en) Arrangement structure of mixed dam composed of earth dams and gravity dam
CN204703121U (en) Urban catchments river course stores up sustained release sponge bank structure soon
CN203668879U (en) Automatic siltation promotion device for mud flat
CN211621453U (en) Assembled river bank protector based on frame permeates water
CN211421051U (en) Water gate for hydraulic engineering of double linkage mechanism formula
CN204051097U (en) A kind of groove dam formula riffler and adopt husky system
CN206570772U (en) A kind of ecological earth and rockfill dam
CN207405590U (en) The sluice structure of water is filtered, divided suitable for fully-loaded stream
CN105649140A (en) Water taking structure, water taking system, circulating water system and construction method of water taking structure
CN203821345U (en) Three-side inflowing flush gallery structure
CN205399364U (en) Whole check gate of irrigation and water conservancy
CN219508783U (en) Anti-backflow drainage structure of sluice wing wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171103