A kind of indoor glass curtain wall of vacuum suction
Technical field
The utility model is related to a kind of curtain wall construction, particularly a kind of room in vacuum suction of readily replaceable damaged panel
Interior glass curtain wall.
Background technology
At present, existing indoor curtain wall includes keel, panel, and wherein keel include crossbeam and column, and panel passes through structure
Glue sticking on framework after be articulated on keel.But, existing curtain wall block is installed because structure is more complicated, when curtain wall block is broken
During damage, if thinking that maintenance effect is good, it is necessary to spend longer time just to carry out breakage after removing the curtain wall block more than Area comparison
The replacing of curtain wall block, is changed if carrying out scene to damaged panel, it is necessary to is first carried out structure glue and is cut off, operation is extremely not
Just, framework surface residual debris cleaning is also carried out after slicing off, is operated cumbersome;If when encountering harsh climate very
It can not extremely construct.After re-replacing, because the structure glue adhesion strength of site operation may not reach code requirement, so as to leave
Potential safety hazard.And structure glue needs certain maintenance time limit after construction is finished, scene carry out structure glue injecting glue can by illumination,
Temperature, the condition such as humidity may not reach the requirement of structure glue maintenance, cause maintenance effect undesirable.
The content of the invention
The purpose of this utility model is to provide a kind of indoor glass curtain wall of vacuum suction, and the technical problem to be solved is to make
Obtain curtain wall block and change simple, it is easy to maintenance.
To solve the above problems, a kind of indoor glass curtain wall of vacuum suction, including the grid being made up of crossbeam and column
The keel of shape, are respectively equipped with curtain wall block, the curtain wall block is made up of aluminum alloy frame 4 and panel, described in the grid hole of keel
Cavity is communicated with aluminum alloy frame, the sucker of one week is evenly distributed with the front end face of aluminum alloy frame and plate contact, is inhaled
Hole is additionally provided with aluminum alloy frame with connecting cavity connection and vacuumizes hole for what is vacuumized, vacuumizes hole and connects with connecting cavity
It is logical, provided with the vacuum valve being tightly connected on hole is vacuumized, seal cap is provided with vacuum valve, between aluminum alloy frame and panel
Provided with sealing gasket, on sealing gasket it is corresponding with sucker position go out provided with hole, connection cavity is vacuumized when by vacuum valve
When, aluminum alloy frame by sucker by panel adsorbed close, so as to realize fixation.
Further, the hole that vacuumizes is on the medial surface of aluminum alloy frame.
Further, the column side side relative with curtain wall block is provided with two hooks of opening direction identical first
The side side relative with curtain wall block is provided with the second upward hook portion of two opening directions on portion, crossbeam, in aluminum alloy frame
The opening of the first pin being fixedly connected, the opening direction of the first pin and the first hook portion is respectively equipped with the rear end face left and right sides
Direction is relative, is respectively equipped with the second pin being fixedly connected above and below the rear end face of the aluminum alloy frame on both sides, and described second inserts
Pin is relative with the opening direction of the second hook portion, between adjacent two pieces of curtain wall blocks, the front end of the front end face of column and crossbeam
The U-shaped fixture being connected by self-tapping screw, the two ends pin and aluminium alloy of the U-shaped fixture are respectively equipped with the middle part of face
The lateral surface of frame surrounding contacts with each other, and the front end of the U-shaped fixture is provided with groove, with groove on the lateral surface of aluminum alloy frame
Position corresponding section is respectively equipped with raised line, and raised line is set in a groove.
Further, first pin and the second pin are provided with shock-absorbing sleeve.
Further, first pin is separately positioned on the frame bar of the aluminum alloy frame left and right sides, the second pin difference
It is arranged on the frame bar of both sides above and below aluminum alloy frame.
Further, it is packed with waterproof adhesive tape between the aluminum alloy frame and column and crossbeam.
The utility model compared with prior art, carries out adsorbing solid by vacuum suction mode counter plate and aluminum alloy frame
It is fixed so that when panel damage needs to change, offset printing is will not leave behind on aluminum alloy frame, only need to be with evacuator to aluminum alloy frame
Connection cavity is vacuumized, you can panel is attracted on aluminium alloy frame body, not only changes simple, and can be shortened and be applied
Between man-hour, cost of labor is reduced.
Brief description of the drawings
Fig. 1 is the structural representation of the utility model curtain wall block.
Fig. 2 is the structural representation of the utility model aluminum alloy frame.
Fig. 3 is the partial cross-section schematic diagram of the cell curtain wall of the utility model fast demountable.
Fig. 4 is that the part of the cell curtain wall of the utility model fast demountable perpendicular cuts open schematic diagram.
Embodiment
The utility model is described in further detail with reference to the accompanying drawings and examples.
As depicted in figs. 1 and 2, the indoor glass curtain wall of vacuum suction of the present utility model is included by crossbeam 1 and column 2
The latticed keel of composition, are respectively equipped with curtain wall block 3 in the grid hole of keel.
As shown in figure 1, of the present utility model the improvement is that curtain wall block 3, specifically, the curtain wall block 3 is by aluminium alloy
Frame 4 and panel 5 are constituted, and cavity 17 is communicated with the aluminum alloy frame 4, the side front end contacted in aluminum alloy frame 4 with panel 5
The sucker 16 of one week is evenly distributed with face, sucker 16 is connected with connecting cavity 17, is additionally provided with aluminum alloy frame 4 for taking out
Vacuum vacuumizes hole 18, vacuumizes hole 18 and is connected with connecting cavity 17, provided with the vacuum being tightly connected on hole 18 is vacuumized
Valve 20, is provided with seal cap 14 on vacuum valve 20, and sealing gasket 19 is provided between aluminum alloy frame 4 and panel 5, on sealing gasket 19 with
The position of sucker 16 it is corresponding go out provided with hole, when being vacuumized by 20 pairs of connection cavitys 17 of vacuum valve, aluminum alloy frame 4 is logical
Sucker 16 is crossed by the adsorbed close of panel 5, so as to realize fixation.
The hole 18 that vacuumizes is on the medial surface of aluminum alloy frame 4.
As shown in Fig. 2 sucker 16 is evenly distributed on side front end face relative with panel 5 on aluminum alloy frame 4.
As shown in Figure 3 and Figure 4, provided with two opening direction identicals on the side side relative with curtain wall block 3 of column 2
Second hook portion 11 of the side side relative with curtain wall block 3 provided with two opening directions upwards on first hook portion 6, crossbeam 1,
The first pin 7 being fixedly connected, the openings of the first pin 7 are respectively equipped with the rear end face left and right sides frame bar of aluminum alloy frame 4
To relative with the opening direction of the first hook portion 6 and be arranged on corresponding position, above and below the rear end face of the aluminum alloy frame 4
The second pin 12 being fixedly connected, the opening direction of the hook portion 11 of the second pin 12 and second are respectively equipped with two side frame bars
It is relative and be arranged on corresponding position, between adjacent two pieces of curtain wall blocks 3, the front end face of column 2 and crossbeam 1
The U-shaped fixture 8 being connected by self-tapping screw, the two ends pin and aluminium of the U-shaped fixture 8 are respectively equipped with the middle part of front end face
The lateral surface of the surrounding of alloy frame 4 contacts with each other, and the front end of the U-shaped fixture 8 is provided with groove 9, aluminum alloy frame 4 it is upper and lower,
Raised line 10 is respectively equipped with the position corresponding section of groove 9 on left and right four lateral surfaces, raised line 10 is arranged in groove 9, curtain wall
Block 3 at the gap of keel with can be packed with marine glue.
During installation, the aluminum alloy frame 4 of curtain wall block 3 is first passed through into the first pin 7, the second pin 12 and the first hook portion 6 respectively
After the mutually mounting of the second hook portion 11, U-shaped fixture 8 is arranged between adjacent two pieces of curtain wall blocks 3, when U-shaped fixture 8 is installed
After finishing, raised line 10 is together with the mutual inlay card of groove 9, so as to make curtain wall block 3 is firm to be arranged on keel.Then pacify
Panel 5 is filled, first sealing gasket 19 is placed on the front end face of aluminum alloy frame 4, and makes the hole on sealing gasket 19 and aluminum alloy frame 4
The sucker 16 of upper correspondence position is alignd, and panel-mounted is led on aluminum alloy frame 4, and aluminium is closed by vacuum valve 20 by evacuator
The connection cavity 17 of golden frame 4 is vacuumized, and makes the adsorbed close panel 5 of sucker 16, so as to complete to install.During replacing, to connection
Cavity 17 goes vacuum, loses the absorption of counter plate 5, the step of repeating to install panel 5, so as to be changed.
Shock-absorbing sleeve 13 is also provided with the first pin 7 and the second pin 12, for reducing noise.
Waterproof adhesive tape 15 is packed between aluminum alloy frame 4 and column 2 and crossbeam 1, so as to play a part of waterproof.
The utility model is easy to removal and installation, when being changed when needing repairing, only needs counter plate to be changed, you can, no
Only without removing residual colloid, and install also simpler, directly change.It need not be tapped rubber in building site, injecting glue etc.