CN206538784U - Prefabrication and assembly construction box culvert - Google Patents

Prefabrication and assembly construction box culvert Download PDF

Info

Publication number
CN206538784U
CN206538784U CN201621348343.8U CN201621348343U CN206538784U CN 206538784 U CN206538784 U CN 206538784U CN 201621348343 U CN201621348343 U CN 201621348343U CN 206538784 U CN206538784 U CN 206538784U
Authority
CN
China
Prior art keywords
box culvert
prefabrication
assembly construction
main body
construction box
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621348343.8U
Other languages
Chinese (zh)
Inventor
王改清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhaohui Electric (beijing) Technology Development Co Ltd
Original Assignee
Zhaohui Electric (beijing) Technology Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhaohui Electric (beijing) Technology Development Co Ltd filed Critical Zhaohui Electric (beijing) Technology Development Co Ltd
Priority to CN201621348343.8U priority Critical patent/CN206538784U/en
Application granted granted Critical
Publication of CN206538784U publication Critical patent/CN206538784U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model provides a kind of prefabrication and assembly construction box culvert, it is in the box culvert main body of cube that it, which includes, be located at bellmouth, the socket of the box culvert main body both sides respectively, several through holes that direction is located at the box culvert main wall surrounding are laid along the prefabrication and assembly construction box culvert, the central part of the box culvert main body inner wall along its length is provided with link slot, and the link slot is located on the through hole.Bellmouth, the socket of the box culvert both sides are mainly used in being mutually linked between box culvert, and close linking can realize waterproof effect good inside box culvert.Link slot in box culvert main body can realize the further fixation being connected with each other between box culvert.The prefabrication and assembly construction box culvert is easily installed and constructed, and inner space is big, pipeline can be overhauled in the case where not influenceing pipeline environment.

Description

Prefabrication and assembly construction box culvert
Technical field
The utility model is related to a kind of prefabrication and assembly construction box culvert, belongs to building material field.
Background technology
It is commonly used for laying the municipal pipeline tunnels such as Urban Buried Pipeline Network electric power, communication, feedwater, draining in the market Material is generally cast-in-place pipeline, and it exists following not enough:(1) complicated construction technique, engineering time length are, it is necessary to which a large amount of manpowers, long Time takes road;(2) pollution in work progress to environment, such as airborne dust, noise, construction raw material are dropped.
Utility model content
In order to overcome above-mentioned technical problem, the utility model provides that a kind of lifting is convenient, is easily installed and constructs, internal Space is big, the engineering time is short, save manpower, environmental pollution is preferably minimized, and can realize is not influenceing pipeline environment In the case of complete to pipeline overhaul the prefabrication and assembly construction box culvert using armored concrete as main material.
To achieve these goals, prefabrication and assembly construction box culvert described in the utility model, it includes the box culvert master in cube Body, bellmouth, the socket for being located at the box culvert main body both sides respectively, the case is located at along prefabrication and assembly construction box culvert laying direction Contain several through holes of main wall surrounding, the central part of the box culvert main body inner wall along its length is provided with link slot, and institute Link slot is stated on the through hole.
Wherein, convex pavement is provided with along its length in the bottom center of the box culvert body interior.
The box culvert body top is provided with suspension ring, and the suspension ring are preferably 4, are separately positioned on top planes corner attached Closely.
Four through holes are preferably provided with, respectively on the corner of the box culvert, are spread along the prefabrication and assembly construction box culvert Set direction runs through whole box culvert body.
The socket relative to box culvert main body protrude 3-50 centimetres, preferably 10 centimetres, the box culvert main body with it is described A circle groove is provided with end face between socket, the groove is used to place adhesive tape.
Inwall in the box culvert main body both sides is provided with some nuts or parallels.
The bellmouth is relative to recessed 3-50 centimetres of the box culvert main body, preferably 10 centimetres.
The length of the box culvert main body refers to length of the box culvert along laying direction.
The length-width ratio of the box culvert main body is (0.5-5):1.
The ratio of width to height of the box culvert main body is (0.5-2):1.
The thickness of the box culvert main wall is 15-60 centimetres.
Prefabrication and assembly construction box culvert described in the utility model has that lifting is convenient, is easily installed and constructs, good water-proof effect, apply Short between man-hour, saving manpower, environmental pollution are preferably minimized, and can realize the completion pair in the case where not influenceing pipeline environment The prefabrication and assembly construction box culvert using armored concrete as main material of pipeline maintenance.It has advantages below:
1. described in the suspension ring that set at the top of prefabrication and assembly construction box culvert more easily lift box culvert when can realize construction.
2. described in prefabrication and assembly construction box culvert both sides bellmouth, socket and box culvert main body on link slot be used for box culvert between phase Mutually linking, close linking can realize waterproof effect good inside box culvert.
3. described in the convex pavement of prefabrication and assembly construction box culvert main body inner bottom part be used to ensure staff when overhauling pipeline Safety.
Brief description of the drawings
Fig. 1 is the base plate plane figure of prefabrication and assembly construction box culvert described in the utility model.
Fig. 2 is the socket elevation of prefabrication and assembly construction box culvert described in the utility model.
Fig. 3 is the interior side elevational view of prefabrication and assembly construction box culvert described in the utility model.
Fig. 4 is the bell and spigot detail drawing of prefabrication and assembly construction box culvert described in the utility model.
Fig. 5 is the link slot schematic diagram of prefabrication and assembly construction box culvert described in the utility model.
Embodiment
Below with reference to the accompanying drawings embodiment of the present utility model is illustrated.In an accompanying drawing of the present utility model or a kind of implementation Element and feature described in mode can be with the elements and feature that are shown in one or more other accompanying drawings or embodiment It is combined.It should be noted that it is general to eliminate, this area unrelated with the utility model for purposes of clarity, in accompanying drawing and explanation The expression and description of part or processing known to logical technical staff.
The utility model is described further below in conjunction with the accompanying drawings.
As shown in figure 1, the prefabrication and assembly construction box culvert described in the present embodiment includes the box culvert main body 1 in cube, it is located at respectively The socket 2 and bellmouth 3 of the both sides of box culvert main body 1.
Fig. 2 is the socket elevation of the prefabrication and assembly construction box culvert.As shown in Fig. 2 the prefabrication and assembly construction described in the present embodiment Change box culvert, in addition to several through holes that direction is located at the wall surrounding of box culvert main body 1 are laid along the prefabrication and assembly construction box culvert 4, and the link slot 5 on the through hole, the link slot 5 is located at the central part of the inwall of box culvert main body 1 along its length.
Preferably, the present embodiment is provided with four through holes 4, respectively on the corner of the prefabrication and assembly construction box culvert.
Convex pavement 6, the ratio of width to height of the convex pavement 6 can also be set in the bottom center inside the box culvert main body 1 For (3-15):1, the height of the convex pavement 6 is preferably arranged to 10cm.The convex pavement 6 is used for staff to the line in pipeline Overhauled on road.
At the top of box culvert main body 1 suspension ring 7 in suspension ring 7, the present embodiment can also be set to be preferably arranged to 4, point It is not arranged near top planes corner, the suspension ring 7 are used for the convenient lifting to the prefabrication and assembly construction box culvert.
As shown in figure 3, can be with pre-buried some nuts 8 or parallels 9, the nut 8 in the inside both sides of box culvert main body 1 For as needed in box culvert main body inner wall both sides fixed support, the support to be used for the pipeline for placing actual laying, the pad Iron 9 is used to be grounded to protect the safety of whole pipeline internal pipeline and staff.
The socket 2 protrudes 3~50 centimetres, preferably 10 centimetres relative to box culvert main body 1.
The bellmouth 3 is relative to 1 recessed 3~50 centimetre, preferably 10 centimetres of the box culvert main body.
In the present embodiment, a length of 200cm, a width of 200cm, a height of 210cm of the box culvert main body 1, the box culvert main body 1 Wall thickness be 30cm.
This prefabrication and assembly constructionization box culvert has plurality of specifications, and length of its length, thickness and socket 2 etc. can be Value in certain limit.
Wherein, a length of 50-800 centimetres of the box culvert main body 1.
A width of 150-1200 centimetres of the box culvert main body 1.
A height of 150-1200 centimetres of the box culvert main body 1.
The thickness of the wall of box culvert main body 1 is 15-60 centimetres.
As shown in figure 4, being provided with a circle groove 10 on end face between the box culvert main body 1 and the socket 2, this is recessed Groove 10 is used to place adhesive tape, plays the squeezing action for slowing down and being brought by effect of expanding with heat and contract with cold between two prefabrication and assembly construction box culverts, Sealing function can also be played simultaneously.
Fig. 5 is the operating diagram of the link slot 5, including lock banking stop 51, pad 52 and steel strand wires 53, the steel Twisted wire 53 is passed through from the through hole 4 of adjacent several prefabrication and assembly construction box culverts, is fixed steel strand wires 53 with lock banking stop 51 and pad 52 At link slot 5.
Preparing the prefabrication and assembly construction box culvert processed needs to carry out in-site installation, and detailed process is as follows:
Hoisting machine suspension hook is put into the suspension ring 7 at the top of prefabrication and assembly construction box culvert first, then the unlatching hoisting machine that switches on power Elevating lever, while prefabrication and assembly construction box culvert is transported to above the groove that has dug, in the common of workmen and hoisting machine Under effect, prefabrication and assembly construction box culvert is placed on specified location and realizes that bellmouth 3, socket 2 are mutually linked.Again by steel strand wires 53 In the through hole 4 that several adjacent prefabrication and assembly construction box culverts are pierced at the link slot 5 inside box culvert, and lead at link slot 5 Cross pad 52 and lock banking stop 51 fixes steel strand wires 53.Several prefabrication and assembly construction box culverts are that can be achieved by above-mentioned repetition operation Fast spreading, after completion is mated formation, loads sandy soil by burying pipeline.
Pre-buried nut 8 is used to place pipeline inside box culvert.The need for according to actual installation pipeline, secure the stand to On pre-buried nut 8, then different pipelines is individually placed to the corresponding position of support.
Prefabrication and assembly construction box culvert described in the utility model has that lifting is convenient, is easily installed and constructs, good water-proof effect, apply Short between man-hour, saving manpower, environmental pollution are preferably minimized, the advantages of facilitating the maintenance of pipeline.
Although the utility model and its advantage has been described in detail it should be appreciated that without departing from by appended right It is required that various changes can be carried out in the case of the spirit and scope of the present utility model limited, substitute and convert.Moreover, this The scope of application is not limited only to process described by specification, equipment, means, the specific embodiment of method and steps.This area Interior those of ordinary skill will readily appreciate that from disclosure of the present utility model, according to the utility model can use execution with The essentially identical function of corresponding embodiment described herein or acquisition result, the existing and future essentially identical with it will quilts Process, equipment, means, method or the step of exploitation.Therefore, appended claim includes this in the range of being directed at them Process, equipment, means, method or the step of sample.

Claims (8)

1. a kind of prefabrication and assembly construction box culvert, it is characterised in that it is in the box culvert main body of cube that it, which includes, be located at the box culvert master respectively Bellmouth, the socket of body both sides, several of the box culvert main wall surrounding are located at along prefabrication and assembly construction box culvert laying direction Through hole, the central part of the box culvert main body inner wall along its length is provided with link slot, and the link slot is located at the through hole On.
2. prefabrication and assembly construction box culvert according to claim 1, it is characterised in that the prefabrication and assembly construction box culvert inner bottom part center Convex pavement is provided with along its length.
3. prefabrication and assembly construction box culvert according to claim 1, it is characterised in that the box culvert body top is provided with suspension ring.
4. prefabrication and assembly construction box culvert according to claim 1, it is characterised in that between the box culvert main body and the socket End face on be provided with a circle groove.
5. prefabrication and assembly construction box culvert according to claim 1, it is characterised in that the inwall in the box culvert main body both sides is set There are nut or parallels.
6. the prefabrication and assembly construction box culvert according to claim 1 to 5 any one, it is characterised in that the length of the box culvert main body Width is than being (0.5-5):1.
7. the prefabrication and assembly construction box culvert according to claim 1 to 5 any one, it is characterised in that the width of the box culvert main body Height is than being (0.5-2):1.
8. the prefabrication and assembly construction box culvert according to claim 1 to 5 any one, it is characterised in that the wall of the box culvert main body 15~60 centimetres of thickness.
CN201621348343.8U 2016-12-09 2016-12-09 Prefabrication and assembly construction box culvert Expired - Fee Related CN206538784U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621348343.8U CN206538784U (en) 2016-12-09 2016-12-09 Prefabrication and assembly construction box culvert

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621348343.8U CN206538784U (en) 2016-12-09 2016-12-09 Prefabrication and assembly construction box culvert

Publications (1)

Publication Number Publication Date
CN206538784U true CN206538784U (en) 2017-10-03

Family

ID=59937346

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621348343.8U Expired - Fee Related CN206538784U (en) 2016-12-09 2016-12-09 Prefabrication and assembly construction box culvert

Country Status (1)

Country Link
CN (1) CN206538784U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108643064A (en) * 2018-05-21 2018-10-12 南通路桥工程有限公司 Case leads to segment and case leads to segment lifting method for turning

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108643064A (en) * 2018-05-21 2018-10-12 南通路桥工程有限公司 Case leads to segment and case leads to segment lifting method for turning

Similar Documents

Publication Publication Date Title
CN106088148B (en) Pipe gallery template and its application
CN207176738U (en) A kind of staggered joint erection comprehensive pipe gallery structure based on prestress system
CN105756088A (en) Combined prefabricated assembled multi-cabin comprehensive pipe rack
CN105756089A (en) Transverse laminated connection type single compartment precast multiple-compartment assembled comprehensive pipe gallery
CN105401593A (en) Assembly type square underground pipe gallery
CN105756087A (en) Assembling-type anchoring structure for adjacent plates of prefabricated comprehensive pipe rack
CN206538784U (en) Prefabrication and assembly construction box culvert
CN105672351A (en) Construction method of buckling connection type prefabricated ribbed bar concrete comprehensive pipe rack structure
CN103231993B (en) Indoor GIS transports positioning apparatus and using method
CN110863512A (en) Prefabricated cable utility tunnel
CN207672616U (en) A kind of outdoor cable penetration pipe is passed by one's way laying structure
CN206110120U (en) A rectangle concrete pile for making up piping lane lateral wall
CN107142957B (en) A kind of city integrated piping lane walking circulation construction system and its method
CN109322326A (en) A kind of pre-groove formula cable type pipe gallery
CN214994477U (en) Pipeline changes structure in foundation ditch
CN211922702U (en) Prefabricated cable utility tunnel
CN110635436A (en) Compound cable pit
CN204098066U (en) The square underground pipe gallery of assembling
CN209339184U (en) A kind of pre-groove formula cable type pipe gallery
CN102852063B (en) concrete block and construction method for road construction
CN205776353U (en) Brace type Pipe rack
CN205857009U (en) Gap bridge pipeline reservation device
CN203626305U (en) Concealed communication base station
CN204401594U (en) A kind of floating mat device for laying geotextile
CN203247497U (en) Bridge type hoisting reconstruction construction structure for communication optical cables

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171003