CN206530342U - 跨蠕滑断裂带隧道衬砌构造 - Google Patents
跨蠕滑断裂带隧道衬砌构造 Download PDFInfo
- Publication number
- CN206530342U CN206530342U CN201621489925.8U CN201621489925U CN206530342U CN 206530342 U CN206530342 U CN 206530342U CN 201621489925 U CN201621489925 U CN 201621489925U CN 206530342 U CN206530342 U CN 206530342U
- Authority
- CN
- China
- Prior art keywords
- lining cutting
- cutting section
- section
- fracture belt
- tunnel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
跨蠕滑断裂带隧道衬砌构造,以有效减小蠕动变形对隧道衬砌的影响,避免造成衬砌大面积破坏。该隧道衬砌包括左侧衬砌节段、右侧衬砌节段和中间衬砌节段,左侧衬砌节段、右侧衬砌节段分别位于蠕滑断裂带两侧,中间衬砌节段位于蠕滑断裂带内,左侧衬砌节段与中间衬砌节段之间设置左侧柔性连接节段,侧衬砌节段与中间衬砌节段之间设置右侧柔性连接节段。
Description
技术领域
本实用新型涉及隧道,特别涉及一种跨蠕滑断裂带隧道衬砌构造。
背景技术
青藏高原是由几个陆块相继合并而成的,川藏铁路将穿越三大缝合带地区,即金沙江缝合带、澜沧江缝合带、班公怒江蛇绿岩缝合带;近斜交穿越雅鲁藏布江蛇绿岩缝合带,线路伴随长度近400km。在板块缝合带进行隧道建设面临的主要工程难题之一是活动断裂。,活动断裂分为粘滑断裂和蠕滑断裂。活动断裂对工程的影响主要表现为错动破坏(抗错断问题)和地震破坏(抗震问题)。
活动断裂是威胁川藏铁路隧道工程的安全建设与运营的重要地质病害,是川藏铁路建设中必须面对且又函待解决的关键地质问题之一。对于建造在活动断裂带的隧道工程,开展跨蠕滑断裂带隧道抗错断措施显得尤为必要。
实用新型内容
本实用新型所要解决的技术问题是提供一种跨蠕滑断裂带隧道衬砌构造,以有效减小蠕动变形对隧道衬砌的影响,避免造成衬砌大面积破坏。
本实用新型解决其技术问题所采用的技术方案如下:
本实用新型的跨蠕滑断裂带隧道衬砌构造中的柔性连接段,其特征是:该隧道衬砌包括左侧衬砌节段、右侧衬砌节段和中间衬砌节段,左侧衬砌节段、右侧衬砌节段分别位于蠕滑断裂带两侧,中间衬砌节段位于蠕滑断裂带内,左侧衬砌节段与中间衬砌节段之间设置左侧柔性连接节段,侧衬砌节段与中间衬砌节段之间设置右侧柔性连接节段。
所述左侧柔性连接节段、右侧柔性连接节段由内而外由全环的初期支护、柔性垫层和二次衬砌构成。
本实用新型的有益效果是,通过尽量减小隧道节段的长度,使得衬砌节段在破碎带及其两侧保持相对独立,在衬砌节段之间设置柔性连接节段,减小衬砌节段的连接刚度,有利于适应破碎带的蠕动变形,不会导致衬砌大面积的破坏;柔性连接节段在隧道初支和二衬之间设置柔性垫层,可以吸收断层蠕动和地震的能量和位移,减小对隧道衬砌的影响。
附图说明
本说明书包括如下两幅附图:
图1是本实用新型跨蠕滑断裂带隧道衬砌构造的平面图;
图2是本实用新型跨蠕滑断裂带隧道衬砌构造中的柔性连接段的断面结构示意图;
图中示出构件和对应的标记:左侧衬砌节段11,右侧衬砌节段12,中间衬砌节段13,左侧柔性连接节段21,右侧柔性连接节段22,系统注浆锚杆23,初期支护24,柔性垫层25,二次衬砌26。
具体实施方式
下面结合附图和实施例对本实用新型进一步说明。
参照图1,本实用新型的跨蠕滑断裂带隧道衬砌构造中的柔性连接段,该隧道衬砌包括左侧衬砌节段11、右侧衬砌节段12和中间衬砌节段13,左侧衬砌节段11、右侧衬砌节段12分别位于蠕滑断裂带两侧,中间衬砌节段13位于蠕滑断裂带内,左侧衬砌节段11与中间衬砌节段13之间设置左侧柔性连接节段21,侧衬砌节段12与中间衬砌节段13之间设置右侧柔性连接节段22。通过尽量减小隧道节段的长度,使得衬砌节段在破碎带及其两侧保持相对独立,在衬砌节段之间设置柔性连接节段,减小衬砌节段的连接刚度,有利于适应破碎带的蠕动变形,不会导致衬砌大面积的破坏。
参照图2,所述左侧柔性连接节段21、右侧柔性连接节段22由内而外由全环的初期支护24、柔性垫层25和二次衬砌26构成。柔性垫层25可以吸收断层蠕动和地震的能量和位移,减小对隧道衬砌的影响。所述柔性垫层25为泡沫混凝土垫层或者橡胶垫层。
参照图2,所述初期支护24包括由覆盖隧道围岩的喷射钢纤维混凝土层和埋设于其内的钢拱架,还可以包括沿围岩周向间隔设置有系统注浆锚杆23。
以上所述只是用图解说明本实用新型跨蠕滑断裂带隧道衬砌构造的一些原理,并非是要将本实用新型局限在所示和所述的具体结构和适用范围内,故凡是所有可能被利用的相应修改以及等同物,均属于本实用新型所申请的专利范围。
Claims (5)
1.跨蠕滑断裂带隧道衬砌构造,其特征是:该隧道衬砌包括左侧衬砌节段(11)、右侧衬砌节段(12)和中间衬砌节段(13),左侧衬砌节段(11)、右侧衬砌节段(12)分别位于蠕滑断裂带两侧,中间衬砌节段(13)位于蠕滑断裂带内,左侧衬砌节段(11)与中间衬砌节段(13)之间设置左侧柔性连接节段(21),侧衬砌节段(12)与中间衬砌节段(13)之间设置右侧柔性连接节段(22)。
2.如权利要求1所述的跨蠕滑断裂带隧道衬砌构造,其特征是:所述左侧柔性连接节段(21)、右侧柔性连接节段(22)由内而外由全环的初期支护(24)、柔性垫层(25)和二次衬砌(26)构成。
3.如权利要求2所述的跨蠕滑断裂带隧道衬砌构造,其特征是:所述柔性垫层(25)为泡沫混凝土垫层或者橡胶垫层。
4.如权利要求2所述的跨蠕滑断裂带隧道衬砌构造,其特征是:所述初期支护(24)包括由覆盖隧道围岩的喷射钢纤维混凝土层和埋设于其内的钢拱架构成。
5.如权利要求4所述的跨蠕滑断裂带隧道衬砌构造,其特征是:所述初期支护(24)还包括沿围岩周向间隔设置有系统注浆锚杆(23)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621489925.8U CN206530342U (zh) | 2016-12-30 | 2016-12-30 | 跨蠕滑断裂带隧道衬砌构造 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621489925.8U CN206530342U (zh) | 2016-12-30 | 2016-12-30 | 跨蠕滑断裂带隧道衬砌构造 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206530342U true CN206530342U (zh) | 2017-09-29 |
Family
ID=59917536
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621489925.8U Active CN206530342U (zh) | 2016-12-30 | 2016-12-30 | 跨蠕滑断裂带隧道衬砌构造 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206530342U (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108252721A (zh) * | 2018-01-11 | 2018-07-06 | 北京工业大学 | 一种用于穿越活动断层区的抗断型铰接隧道及其应用 |
CN108691555A (zh) * | 2018-04-20 | 2018-10-23 | 北京工业大学 | 断层破碎带段抗震隧道管道连接件 |
CN109681231A (zh) * | 2019-01-24 | 2019-04-26 | 中铁第四勘察设计院集团有限公司 | 一种活动断层区段矿山法隧道位移自适应结构与安装方法 |
-
2016
- 2016-12-30 CN CN201621489925.8U patent/CN206530342U/zh active Active
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108252721A (zh) * | 2018-01-11 | 2018-07-06 | 北京工业大学 | 一种用于穿越活动断层区的抗断型铰接隧道及其应用 |
CN108252721B (zh) * | 2018-01-11 | 2019-12-03 | 北京工业大学 | 一种用于穿越活动断层区的抗断型铰接隧道及其应用 |
CN108691555A (zh) * | 2018-04-20 | 2018-10-23 | 北京工业大学 | 断层破碎带段抗震隧道管道连接件 |
CN109681231A (zh) * | 2019-01-24 | 2019-04-26 | 中铁第四勘察设计院集团有限公司 | 一种活动断层区段矿山法隧道位移自适应结构与安装方法 |
CN109681231B (zh) * | 2019-01-24 | 2024-01-19 | 中铁第四勘察设计院集团有限公司 | 一种活动断层区段矿山法隧道位移自适应结构与安装方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206530342U (zh) | 跨蠕滑断裂带隧道衬砌构造 | |
CN106050245A (zh) | 矩形隧道断面零距离下穿既有车站的支护结构及构建方法 | |
CN201747387U (zh) | 巷道支护支架 | |
US9045865B2 (en) | Polymer grouting method for uplifting ballastless track of high-speed rail | |
CN203515598U (zh) | 跨越活动断层的隧道支护结构 | |
CN109989768A (zh) | 一种适用于隧道穿越活断层的衬砌结构及其施工方法 | |
CN204238948U (zh) | 一种适用于傍山沿河隧道的棚洞结构 | |
CN108708740A (zh) | 一种可消除隧道底鼓病害的隧道底部构造 | |
CN103821542B (zh) | 一种具有波折纹型面的防冲支架 | |
Ma et al. | Analysis on ultimate water pressure and treatment measures of tunnels operating in water rich areas based on water hazard investigation | |
CN210977504U (zh) | 一种震后快速修复的隧道减震结构 | |
CN102979543B (zh) | 高应力区临河硬岩双线隧道脆性破坏段围岩的支护方法 | |
CN201321596Y (zh) | 既有桥梁防落石构造 | |
CN104879136B (zh) | 用于穿越溶洞的软弱破碎地层隧道支护体系及安装方法 | |
CN207297017U (zh) | 小间距下穿隧道结构及隧道交叉结构 | |
CN110645013A (zh) | 一种震后快速修复的隧道减震结构 | |
Li-ying et al. | Discussion and analysis of accident reasons of deep foundation pits | |
CN108798698A (zh) | 一种穿越水平位错活动断层的盾构隧道结构 | |
CN206111182U (zh) | 一种矩形隧道断面零距离下穿既有车站的支护结构 | |
CN108894799A (zh) | 大断面隧道轻高型组合钢架 | |
CN107725088A (zh) | 一种抗岩爆和大变形翼式劈裂型吸能锚杆及结构 | |
CN203783605U (zh) | 一种高强度巷道支护支架 | |
CN208870608U (zh) | 大断面隧道轻高型组合钢架 | |
CN102562098A (zh) | 隧道钢制快速拆装临时仰拱 | |
JP2013160029A (ja) | トンネル構造およびその施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |