CN206488292U - A kind of new boiler combustor being convenient to clean - Google Patents
A kind of new boiler combustor being convenient to clean Download PDFInfo
- Publication number
- CN206488292U CN206488292U CN201621412786.9U CN201621412786U CN206488292U CN 206488292 U CN206488292 U CN 206488292U CN 201621412786 U CN201621412786 U CN 201621412786U CN 206488292 U CN206488292 U CN 206488292U
- Authority
- CN
- China
- Prior art keywords
- level pipeline
- convenient
- combustion
- blower fan
- clean
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Solid-Fuel Combustion (AREA)
Abstract
The utility model provides a kind of new boiler combustor being convenient to clean, including boiler, blower fan, protection network, air inlet pipe, combustion-supporting tubular construction, ring flange, feed hopper, passage and thermal insulation board, and described feed hopper is arranged on the top of passage;Described ring flange is arranged on airway tube;Described thermal insulation board is arranged on the inside of boiler;Described combustion tube structure setting is connected in the inner side of thermal insulation board, and in bottom with blower fan;Described protection network is arranged on the lower left quarter of blower fan;Described air inlet pipe is arranged on the upper right quarter of blower fan.The utility model conveniently adjusts flexible one-level pipeline, the distance between secondary canalization and three-level pipeline, cleaning mixed and disorderly substances in pipe are convenient, it is adaptable to different size of boiler by one-level pipeline, secondary canalization, being equipped with for three-level pipeline.
Description
Technical field
The utility model belongs to combustor technical field, more particularly to a kind of new boiler combustor being convenient to clean.
Background technology
Steam boiler is the Industrial Boiler for heating the water to certain parameter and producing high-temperature steam, belongs to special equipment.Cause
Its fired heat duty is low, and combustion thermal efficiency is high, can effectively reduce exhaust gas temperature, energy-saving, using economy, therefore obtains
It is widely applied.
Chinese Patent Application No. is 201420666931.0, a kind of entitled steam boiler combustor of innovation and creation
Air distribution device, belongs to combustor technical field, including combustor body, and the combustor body bottom portion is provided with air intake passage, institute
State on flame retardant coating and cooling layer that the side wall of combustor body includes setting gradually from inside to outside, the side wall of the combustor body
It is located at institute on the feeding port connected provided with the crater connected with the steam boiler and with feed device, the flame retardant coating inwall
State to help provided with blower fan between crater and air intake passage and some aid distributing pipes are provided with oxygen mouthful, the flame retardant coating, per the air distribution
Pipe one end connects the blower fan and helps oxygen mouthful, and the other end connects the air intake passage.
Existing combustor, which is existed, is inconvenient to the length for adjusting combustion tube, is inconvenient to clear up inside combustion tube, it is impossible to suitable
The problem of for different types of boiler.
Therefore, invent a kind of new boiler combustor being convenient to clean and seem very necessary.
Utility model content
In order to solve the above-mentioned technical problem, the utility model provides a kind of new boiler combustor being convenient to clean, with
Solve to be inconvenient to clear up inside the length for being inconvenient to adjust combustion tube that existing combustor is present, combustion tube, it is impossible to be applied to
The problem of different types of boiler, a kind of new boiler combustor being convenient to clean, including boiler, blower fan, protection network, air inlet
Pipe, combustion-supporting tubular construction, ring flange, feed hopper, passage and thermal insulation board, described feed hopper are arranged on the top of passage;Institute
The ring flange stated is arranged on airway tube;Described thermal insulation board is arranged on the inside of boiler;Described combustion tube structure setting every
The inner side of hot plate, and be connected in bottom with blower fan;Described protection network is arranged on the lower left quarter of blower fan;Described air inlet pipe is set
In the upper right quarter of blower fan;Described combustion-supporting tubular construction includes one-level pipeline, and secondary canalization, three-level pipeline, fixing bolt is combustion-supporting
Mouthful, fixed disk and fixing hole, described combustion-supporting mouth are fixed on the right side of three-level pipeline by fixing bolt;Described fixed disk weldering
It is connected on the left side of one-level pipeline;Described secondary canalization is fixed on the middle part of one-level pipeline and three-level pipeline by fixing bolt;
Described fixing hole is opened in the upper and lower ends of fixed disk.
The utility model can also use following technical measures.
Described one-level pipeline, secondary canalization, the grafting successively of three-level pipeline, and fixed by fixing bolt, be conducive to stretching
Contracting is convenient, easy to disassemble, and cleaning mixed and disorderly substances in pipe is convenient, it is adaptable to different size of boiler.
Described thermal insulation board uses aluminum fiberboard, is conducive to preferably preventing from crossing influence work in combustion-supporting tubular construction, improves
Operating efficiency.
Described protection network uses PVC plastic protection network, is conducive to preventing the debris in air from entering in blower fan, uses
More facilitate.
Described combustion-supporting mouth uses section to be horn-like, is conducive to preferably expanding the combustion range of flame, convenient use.
Compared with prior art, the utility model has the advantages that:
The utility model has the advantages and positive effects of:The utility model passes through one-level pipeline, secondary canalization, three-level
Being equipped with for pipeline, it is convenient to adjust flexible one-level pipeline, the distance between secondary canalization and three-level pipeline, cleaning mixed and disorderly substances in pipe
It is convenient, it is adaptable to different size of boiler.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model.
Fig. 2 is the structural representation of combustion-supporting tubular construction of the present utility model.
In figure:
1- boilers;2- blower fans;3- protection networks;4- air inlet pipe;The combustion-supporting tubular constructions of 5-;51- one-level pipelines;52- secondary canalizations;
53- three-level pipelines;54- fixing bolts;The combustion-supporting mouths of 55-;56- fixed disks;57- fixing holes;6- ring flanges;7- feed hoppers;8- is led
Expects pipe;9- thermal insulation boards.
Embodiment
The utility model is described further below in conjunction with accompanying drawing:
Embodiment:
As depicted in figs. 1 and 2
The utility model is adopted the technical scheme that to solve technical problem present in known technology:One kind is new just
In the boiler combustor of cleaning, including boiler 1, blower fan 2, protection network 3, air inlet pipe 4, combustion-supporting tubular construction 5, ring flange 6, charging
Bucket 7, passage 8 and thermal insulation board 9, described feed hopper 7 are arranged on the top of passage 8;Described ring flange 6 is arranged on air guide
On pipe 8;Described thermal insulation board 9 is arranged on the inner side of boiler 1;Described combustion-supporting tubular construction 5 is arranged on the inner side of thermal insulation board 9, and
Bottom is connected with blower fan 2;Described protection network 3 is arranged on the lower left quarter of blower fan 2;Described air inlet pipe 4 is arranged on the right side of blower fan 2
Top;Described combustion-supporting tubular construction 5 includes one-level pipeline 51, secondary canalization 52, three-level pipeline 53, fixing bolt 54, combustion-supporting mouth
55, fixed disk 56 and fixing hole 57, described combustion-supporting mouth 55 are fixed on the right side of three-level pipeline 53 by fixing bolt 54;It is described
Fixed disk 56 be welded on the left side of one-level pipeline 51;Described secondary canalization 52 is fixed on one-level pipeline by fixing bolt 54
51 and the middle part of three-level pipeline 53;Described fixing hole 57 is opened in the upper and lower ends of fixed disk 56.
The utility model can also use following technical measures.
Described one-level pipeline 51, secondary canalization 52, the grafting successively of three-level pipeline 53, and fixed by fixing bolt 54,
It is flexible convenient to be conducive to, easy to disassemble, and cleaning mixed and disorderly substances in pipe is convenient, it is adaptable to different size of boiler 1.
Described thermal insulation board 9 uses aluminum fiberboard, is conducive to preferably preventing from crossing influence work in combustion-supporting tubular construction 5, carries
High workload efficiency.
Described protection network 3 uses PVC plastic protection network, is conducive to preventing the debris in air from entering in blower fan, makes
With more facilitate.
Described combustion-supporting mouth 55 uses section to be horn-like, is conducive to preferably expanding the combustion range of flame, conveniently makes
With.
Operation principle
The utility model in the course of the work, raw material is put into out of charging aperture 7, is transported to by passage 8 in boiler, is led to
Cross air inlet pipe 4 to come in and go out into combustion-supporting tubular construction 5 flammable gas, fuel gas is blowed to by blower fan 2 by point in combustion-supporting tubular construction 5
Combustion, the tightness of one-level pipeline 51, secondary canalization 52 and three-level pipeline 53 is adjusted by fixing bolt 54, elongated or
It is to shorten one-level pipeline 51, secondary canalization 52 and three-level pipeline 53, an one-level pipeline 51 and two grades is pulled down by fixing bolt 54
Pipeline 52 or three-level pipeline 53 are taken apart, carry out the debris inside cleaning one-level pipeline 51, secondary canalization 52 and three-level pipeline 53.
Using technical scheme described in the utility model, or those skilled in the art is in technical solutions of the utility model
Under inspiration, similar technical scheme is designed, and reaches above-mentioned technique effect, is to fall into protection model of the present utility model
Enclose.
Claims (5)
1. a kind of new boiler combustor being convenient to clean, it is characterised in that the new boiler combustor being convenient to clean,
Including boiler(1), blower fan(2), protection network(3), air inlet pipe(4), combustion-supporting tubular construction(5), ring flange(6), feed hopper(7), lead
Expects pipe(8)And thermal insulation board(9), described feed hopper(7)It is arranged on passage(8)Top;Described ring flange(6)It is arranged on
Passage(8)On;Described thermal insulation board(9)Installed in boiler(1)Inner side;Described combustion-supporting tubular construction(5)It is arranged on thermal insulation board
(9)Inner side, and in bottom and blower fan(2)Connection;Described protection network(3)It is arranged on blower fan(2)Lower left quarter;Described enters
Tracheae(4)It is arranged on blower fan(2)Upper right quarter;Described combustion-supporting tubular construction(5)Including one-level pipeline(51), secondary canalization
(52), three-level pipeline(53), fixing bolt(54), combustion-supporting mouth(55), fixed disk(56)And fixing hole(57), described combustion-supporting mouth
(55)Pass through fixing bolt(54)It is fixed on three-level pipeline(53)Right side;Described fixed disk(56)It is welded on one-level pipeline
(51)Left side;Described secondary canalization(52)Pass through fixing bolt(54)It is fixed on one-level pipeline(51)With three-level pipeline(53)
Middle part;Described fixing hole(57)It is opened in fixed disk(56)Upper and lower ends.
2. the new boiler combustor being convenient to clean as claimed in claim 1, it is characterised in that described one-level pipeline
(51), secondary canalization(52), three-level pipeline(53)Grafting successively.
3. the new boiler combustor being convenient to clean as claimed in claim 1, it is characterised in that described thermal insulation board(9)
Using aluminum fiberboard.
4. the new boiler combustor being convenient to clean as claimed in claim 1, it is characterised in that described protection network(3)
Using PVC plastic protection network.
5. the new boiler combustor being convenient to clean as claimed in claim 1, it is characterised in that described combustion-supporting mouth(55)
Section is used to be horn-like.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621412786.9U CN206488292U (en) | 2016-12-22 | 2016-12-22 | A kind of new boiler combustor being convenient to clean |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621412786.9U CN206488292U (en) | 2016-12-22 | 2016-12-22 | A kind of new boiler combustor being convenient to clean |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206488292U true CN206488292U (en) | 2017-09-12 |
Family
ID=59771324
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621412786.9U Expired - Fee Related CN206488292U (en) | 2016-12-22 | 2016-12-22 | A kind of new boiler combustor being convenient to clean |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206488292U (en) |
-
2016
- 2016-12-22 CN CN201621412786.9U patent/CN206488292U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206488292U (en) | A kind of new boiler combustor being convenient to clean | |
CN207163091U (en) | A kind of biomass fuel fruit and vegetable drying equipment | |
CN206386943U (en) | Supercritical water oxidation burner | |
CN106048183B (en) | A kind of biomass electricity Dual-energy source heat-treatment furnace | |
CN104164803A (en) | Gas direct-fired heating drying oven | |
CN206094890U (en) | Ultrahigh molecular weight polyethylene manages heating furnace | |
CN208547258U (en) | A kind of apparatus for reusing residual heat | |
CN207750272U (en) | A kind of air-to-air energy recovery silencing means | |
CN206648287U (en) | A kind of energy-saving, environmental protection boiler of Utilizing Energy Sources in Reason | |
CN206875539U (en) | A kind of abandoned mine low concentration gas utilizes simple waste gas residual-heat heating device | |
CN206803810U (en) | A kind of oil heater | |
CN205245751U (en) | Gardenia is drying system for extract product | |
CN209605397U (en) | A kind of high-efficient hot air furnace | |
CN207456135U (en) | A kind of Novel large-space dries room temperature flow-disturbing system | |
CN204042916U (en) | Drying equipment in a kind of domestic waste sorting pretreatment | |
CN212512533U (en) | Waste heat utilization device for drying kiln | |
CN212838191U (en) | Cold starting drive of wind power generation | |
CN212431686U (en) | Drying-machine heating system | |
CN207050211U (en) | Environment-friendly type natural gas fireplace | |
CN204000450U (en) | A kind of Gas Direct-fired heated oven | |
CN209431867U (en) | A kind of happy firing of heat preservation being rapidly heated | |
CN207040476U (en) | A kind of energy-efficient warming pig house using biogas | |
CN203980333U (en) | Heat exchanger | |
CN207514963U (en) | Recovery device for heat energy of fume of boiler | |
CN202675597U (en) | High-efficiency hot blast stove |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |