CN206485519U - Seabed operation supports the stern drum support structure of ship - Google Patents
Seabed operation supports the stern drum support structure of ship Download PDFInfo
- Publication number
- CN206485519U CN206485519U CN201720120176.XU CN201720120176U CN206485519U CN 206485519 U CN206485519 U CN 206485519U CN 201720120176 U CN201720120176 U CN 201720120176U CN 206485519 U CN206485519 U CN 206485519U
- Authority
- CN
- China
- Prior art keywords
- support
- plate
- ship
- stern
- internal partition
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Butt Welding And Welding Of Specific Article (AREA)
Abstract
The utility model discloses the stern drum support structure that a kind of seabed operation supports ship, including support outside plate(1), connection bracket(2), support swash plate(3), closing panel(4), main deck(5), stern transom plate(6), support baseboard(7), landing slab(9)And internal partition(11), the support outside plate(1), connection bracket(2), support swash plate(3), closing panel(4)And internal partition(11)Fit together and and main deck(5), stern transom plate(6), support baseboard(7), landing slab(9)Welding forms overall structure.The utility model drum support structure form is more succinct, connection and reasonable arrangement, attractive appearance, realize watertight separation function, meet equipment and use functional requirement, and constitute overall with Ship Structure, effectively transmission service load, the local overall strength of participation Ship Structure, improve the stability and service life of supporting construction.
Description
Technical field
The utility model is related to the stern drum support structure that a kind of seabed operation supports ship.
Background technology
Ship is supported in seabed operation(SSV)Building course in, stern roller is one of important equipment, and it is electric at sea
Cable is collected, leads in cable mooring and oceangoing voyage towing operation and play a significant role.During shipping work, because drum functions are negative
Lotus is big, stress is complicated, and it requires also at a relatively high to supporting construction, is ensureing that structural strength meets the situation of drum functions load
Under, optimize structure type and effectively be connected to form entirety with Ship Structure, be conducive to its load to be efficiently transferred to hull knot
Structure, it is to avoid drum functions load is destroyed to the fatigue strength of supporting construction, while according to ship hull plate molded line data, support is outer
With ship hull plate fairing transition after the processing of plate hyperboloid, the aesthetic property of stern structure is improved.
Utility model content
The purpose of this utility model is to provide a kind of more succinct, connection and reasonable arrangement, attractive appearance, realizes that watertight separates work(
Can, meet the stern drum support structure that equipment supports ship using the seabed operation of functional requirement.
The technical scheme that the utility model is used to achieve the above object is:One kind includes support outside plate(1), connection elbow
Plate(2), support swash plate(3), closing panel(4), main deck(5), stern transom plate(6), support baseboard(7), landing slab(9)And inside
Dividing plate(11), the support outside plate(1), connection bracket(2), support swash plate(3), closing panel(4)And internal partition(11)Group
It is fitted together and and main deck(5), stern transom plate(6), support baseboard(7), landing slab(9)Welding forms overall structure.
The support baseboard(7)On be connected with bottom plate reinforcing plate(8).
The internal partition(11)Provided with watertight manhole's lid(10)With internal partition lightening core(12).
A kind of seabed operation of the utility model supports the stern drum support structure of ship, is ensureing that structural strength meets roller
In the case of live load, design and optimize structure type and effectively be connected to form entirety with Ship Structure, be conducive to it to bear
Lotus is efficiently transferred to Ship Structure, it is to avoid drum functions load is destroyed to the fatigue strength of supporting construction, while according to hull
Outside plate molded line data, with ship hull plate fairing transition after support outside plate hyperboloid is processed, improve the aesthetic property of stern structure.
Brief description of the drawings
Fig. 1 is the side view one for the stern drum support structure that a kind of seabed operation of the utility model supports ship.
Fig. 2 is the side view two for the stern drum support structure that a kind of seabed operation of the utility model supports ship.
Fig. 3 is the front view for the stern drum support structure that a kind of seabed operation of the utility model supports ship.
Fig. 4 is the top view for the stern drum support structure that a kind of seabed operation of the utility model supports ship.
In figure:1st, outside plate is supported;2nd, bracket is connected;3rd, swash plate is supported;4th, closing panel;5th, main deck;6th, stern transom plate;7、
Support baseboard;8th, bottom plate reinforcing plate;9th, landing slab;10th, watertight manhole is covered;11st, internal partition;12nd, internal partition lightening core.
Embodiment
As shown in Figures 1 to 4, seabed operation supports the stern drum support structure of ship, including support outside plate 1, connection elbow
Plate 2, support swash plate 3, closing panel 4, main deck 5, stern transom plate 6, support baseboard 7, bottom plate reinforcing plate 8, landing slab 9 and it is internal every
Plate 11, support outside plate 1, connection bracket 2, support swash plate 3, closing panel 4 and internal partition 11 are fitted together and and main deck
5th, stern transom plate 6, support baseboard 7, landing slab 9, which are welded, forms overall structure, with stern after bottom plate reinforcing plate 8 and the assembling of support baseboard 7
Shrouding 6, landing slab 9 are welded, and internal partition 11 is provided with watertight manhole's lid 10 and internal partition lightening core 12, the utility model seabed
Operation supports the stern drum support structure of ship, bottom plate reinforcing plate 8 to be welded after being assembled with support baseboard 7 with stern transom plate 6, landing slab 9
Connect, according to the requirement of the outside dimension of roller and working clearance, calculate the size of support baseboard curved surface, set according to stressing conditions
Count out the thickness and reinforcement structure size of bottom plate, and consider its successive fashion with Ship Structure, so as to effectively will support by
Power is delivered to Ship Structure, is tyre surface assembling support swash plate 3 to support outside plate 1, connects bracket 2 and internal partition 11, and and stern
Shrouding 6, main deck 5, landing slab 9 and the welding of support baseboard 7 form structure entirety, according to the outside dimension and workplace of roller
The requirement of gap, calculates the size of support outside plate curved surface, according to the setting out data of ship hull plate molded line, will support outside plate hyperboloid
Fairing is transitioned into ship hull plate after processing, to improve the aesthetic property of stern structure, live load further according to roller and to support
The requirement of structure, designs the thickness of support outside plate and the size of supporting construction, due to the requirement of drum functions environment, whole branch
Support structure has watertight sexual function, on the premise of supporting construction intensity is ensured, structure arrangement, size and form are designed
Optimization, and the strength check of supporting construction is carried out, structure type reasonable in design is connected with Ship Structure, by supporting construction load
Ship Structure is efficiently transferred to, it is to avoid the fatigue rupture of branch binding structure, finally, to the stern structure of supporting construction region
Strength check is carried out, the related request of specification is met with the structure overall strength for ensureing the region, internally cut out on dividing plate 11
Watertight manhole's lid 10 and internal partition lightening core 12, for the ease of site operation, mitigate construction weight and facilitate the movement of persons, examine
Repair, it is as far as possible on dividing plate internally to be provided with perforate, Ran Houzai in the case where supporting construction intensity meets drum functions load more
It is secondary that supporting construction intensity is checked, to reach the purpose of optimization design, stern roller 14 is arranged in supporting construction 15,
The abrasionproof outside plate 13 at two ends is installed after debugging is errorless, according to the working characteristics of roller, the support outside plate at its two ends be possible to by
Larger abrasion, is conducive to improving supporting construction service life, the drum support structure form is more using special abrasionproof outside plate
Succinctly, connection and reasonable arrangement, attractive appearance, realize watertight separation function, meet equipment and use functional requirement, and constituted with Ship Structure
It is overall, effectively transmit service load, participate in the local overall strength of Ship Structure, improve the stability of supporting construction and use
Life-span.
Claims (3)
1. a kind of seabed operation supports the stern drum support structure of ship, it is characterised in that:Including support outside plate(1), connection elbow
Plate(2), support swash plate(3), closing panel(4), main deck(5), stern transom plate(6), support baseboard(7), landing slab(9)And inside
Dividing plate(11), the support outside plate(1), connection bracket(2), support swash plate(3), closing panel(4)And internal partition(11)Group
It is fitted together and and main deck(5), stern transom plate(6), support baseboard(7), landing slab(9)Welding forms overall structure.
2. a kind of seabed operation according to claim 1 supports the stern drum support structure of ship, it is characterised in that:It is described
Support baseboard(7)On be connected with bottom plate reinforcing plate(8).
3. a kind of seabed operation according to claim 1 supports the stern drum support structure of ship, it is characterised in that:It is described
Internal partition(11)Provided with watertight manhole's lid(10)With internal partition lightening core(12).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720120176.XU CN206485519U (en) | 2017-02-09 | 2017-02-09 | Seabed operation supports the stern drum support structure of ship |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720120176.XU CN206485519U (en) | 2017-02-09 | 2017-02-09 | Seabed operation supports the stern drum support structure of ship |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206485519U true CN206485519U (en) | 2017-09-12 |
Family
ID=59764832
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720120176.XU Expired - Fee Related CN206485519U (en) | 2017-02-09 | 2017-02-09 | Seabed operation supports the stern drum support structure of ship |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206485519U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109747772A (en) * | 2018-12-14 | 2019-05-14 | 大连中远海运重工有限公司 | The side ejector sleeve support construction and installation method of ocean engineering ship bow part Side Thrusters |
CN109747780A (en) * | 2018-12-14 | 2019-05-14 | 大连中远海运重工有限公司 | The urea cabinet and its manufacture craft of pulp carrier |
CN110287501A (en) * | 2018-03-19 | 2019-09-27 | 江苏现代造船技术有限公司 | A kind of setting out method of ship hull plate label part |
CN112664553A (en) * | 2020-12-09 | 2021-04-16 | 大连中远海运重工有限公司 | Novel stern roller base for ship |
-
2017
- 2017-02-09 CN CN201720120176.XU patent/CN206485519U/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110287501A (en) * | 2018-03-19 | 2019-09-27 | 江苏现代造船技术有限公司 | A kind of setting out method of ship hull plate label part |
CN110287501B (en) * | 2018-03-19 | 2023-06-20 | 江苏现代造船技术有限公司 | Lofting method for ship hull plate marking part |
CN109747772A (en) * | 2018-12-14 | 2019-05-14 | 大连中远海运重工有限公司 | The side ejector sleeve support construction and installation method of ocean engineering ship bow part Side Thrusters |
CN109747780A (en) * | 2018-12-14 | 2019-05-14 | 大连中远海运重工有限公司 | The urea cabinet and its manufacture craft of pulp carrier |
CN112664553A (en) * | 2020-12-09 | 2021-04-16 | 大连中远海运重工有限公司 | Novel stern roller base for ship |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206485519U (en) | Seabed operation supports the stern drum support structure of ship | |
CN109747772A (en) | The side ejector sleeve support construction and installation method of ocean engineering ship bow part Side Thrusters | |
CN101429928A (en) | Integral hoisting method for wind generator set on the sea | |
CN105417403A (en) | Method for installing ultrahigh ultra-large type floating crane in dock | |
CN206278229U (en) | A kind of draw off gear of marine anchor chain | |
CN103061521B (en) | Coliseum Steel Cantilever Truss torque type mounting method | |
CN203902799U (en) | Double-curved-surface-shaped floating oil production and storage platform | |
CN204435199U (en) | A kind of casing jointing | |
CN207049435U (en) | Siphon piping water intake transporting and hoisting is with regard to bit platform | |
CN203998583U (en) | Spacecraft is light-duty suspender attaching parts for lifting | |
CN103274021B (en) | Integrated machine base module of shipborne anchor machine and mounting method of integrated machine base module | |
CN205557514U (en) | Waters spiral anchor construction equipment | |
CN201745721U (en) | Special installation vessel for marine intertidal wind power generating set | |
CN207360518U (en) | Sealing device for the interim floating of ship | |
CN101761691A (en) | Bound floating pipeline towing pipe method process | |
CN201834176U (en) | Tooling for underwater anchor chock modification work | |
CN204979158U (en) | Latent floating carrying platform device | |
CN202842118U (en) | Working and accommodation platform for aquaculture at sea | |
CN204056256U (en) | A kind of boats and ships and ocean engineering structure close up uses scaffold | |
KR20130063330A (en) | The aid buoyancy device of the sea jacket structure | |
CN206265262U (en) | Movable dock | |
CN202697476U (en) | Marine raft device | |
CN206243398U (en) | A kind of integral type toilet peculiar to vessel | |
CN204265212U (en) | A kind of floating drum for installing super-heavy component under water | |
CN204659964U (en) | Chain cable fairlead bracing or strutting arrangement |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |