CN206480996U - A kind of emergency cable bypass - Google Patents

A kind of emergency cable bypass Download PDF

Info

Publication number
CN206480996U
CN206480996U CN201720051285.0U CN201720051285U CN206480996U CN 206480996 U CN206480996 U CN 206480996U CN 201720051285 U CN201720051285 U CN 201720051285U CN 206480996 U CN206480996 U CN 206480996U
Authority
CN
China
Prior art keywords
cable
emergency
emergency cable
mandrel
bypass
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720051285.0U
Other languages
Chinese (zh)
Inventor
周添文
陈永敏
杨植雄
许方庭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Eagle Energy Technology Co Ltd
Original Assignee
Guangdong Eagle Energy Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Eagle Energy Technology Co Ltd filed Critical Guangdong Eagle Energy Technology Co Ltd
Priority to CN201720051285.0U priority Critical patent/CN206480996U/en
Application granted granted Critical
Publication of CN206480996U publication Critical patent/CN206480996U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of bypass of emergency cable, including emergency cable and for loading the cable fixation structure of emergency cable, the emergency cable is provided at both ends with the fast-wiring head being connected with failure cable field joint end, the cable fixation structure includes cable trough, crossbeam and mandrel, the crossbeam is rotatably set up on the cable trough, mandrel is fixedly connected with the middle part of the crossbeam, emergency cable is wound on the mandrel, emergency cable mandrel adjoint rotation during folding and unfolding on mandrel, the distribution outlet cable that can solve prior art using the utility model needs very long reparation after breaking down, test and telegram in reply time, production equipment to enterprise causes huge destruction and brings the technical problem of quite serious economic loss.

Description

A kind of emergency cable bypass
Technical field
The utility model is related to field of cables, more particularly to a kind of bypass of emergency cable.
Background technology
For ease of constructing and saving resource, the distribution outlet cable of major part enterprise all uses buried mode, earth's surface at present Landfill laying is carried out using cement.The service life of cable is limited, adds the severe use environment influence in some areas, and cable is even Failure occurs in you, when cable breaks down, it is necessary to survey trouble point is first sought with cable detector device, then carries out road surface and opens Dig, after finding out that all trouble points confirmations are errorless, then carry out cable reparation, test, telegram in reply, repair time is very long, entirely Electric power is transmitted without normal direction enterprise, it is impossible to meet the active demand of enterprise's fast power restoration, particularly go out in night in engineering time section Existing cable fault, the response for rushing to repair resource is just more delayed.If urgency call generator carries out emergency service, the time is at least Also need 2-3 hours.Enterprise can only bear considerable damage and the serious economic loss that fault outage is caused to production equipment.
Therefore, prior art has yet to be improved and developed.
The content of the invention
The purpose of this utility model is to provide a kind of emergency cable bypass, to solve the distribution outlet cable of prior art Very long reparation, test and telegram in reply time are needed after breaking down, the production equipment to enterprise causes huge destruction and band Carry out quite serious economic loss.
The technical solution of the utility model is as follows:
A kind of emergency cable bypass, wherein, including emergency cable and the cable fixation structure for loading emergency cable, institute State the fast-wiring head being connected with failure cable field joint end that is provided at both ends with of emergency cable, the cable fixation structure bag Cable trough, crossbeam and mandrel are included, the crossbeam is rotatably set up on the cable trough, be fixedly connected with the middle part of the crossbeam Mandrel, emergency cable is wound on the mandrel, emergency cable mandrel adjoint rotation during folding and unfolding on mandrel.
Described emergency cable bypass, wherein, the fast-wiring head includes DL type joints and TP type joints, DL type joints The cable connection end of emergency cable and other cables is arranged at, TP type joints are arranged at the connection end of emergency cable and copper bar.
Described emergency cable bypass, wherein, the emergency cable two ends are also crimped with fast binding clip, and fast binding clip should Urgent telegram cable and failure cable field joint end are fixed together.
Described emergency cable bypass, wherein, the mandrel two ends are each provided with a dividing plate, emergency cable be wound in two every On mandrel regions between plate.
Described emergency cable bypass, wherein, the length of the emergency cable of each mandrel winding is 20m, and emergency cable is set It is set to diameter 240mm copper flexible cable.
Described emergency cable bypass, wherein, the emergency cable is 0.4kV emergency cables, and each of emergency cable connects Progress insulation protection at 10kV shrinkage rubber sheaths, 10kV shrinkage rubber sheath butted lines is provided with line.
Described emergency cable bypass, wherein, emergency cable bypass surrounding, which is provided with the safety for preventing pedestrian close and enclosed, covers Structure, is additionally provided with warning sign.
The beneficial effects of the utility model:The utility model is bypassed by providing a kind of emergency cable, in the outlet of enterprise When cable breaks down, the cable for temporarily replacing breaking down and needing to repair is bypassed with 0.4kV emergency cables, it is quick to set up power supply Bypass, ensures that business electrical is not influenceed by construction duration and response goods and materials, allow enterprise can Power resumption in a short time, will The influence to production of having a power failure is preferably minimized, solve prior art distribution outlet cable break down after need very long repair Multiple, test and telegram in reply time, the production equipment to enterprise cause huge destruction and bring quite serious economic loss Technical problem.
Brief description of the drawings
Fig. 1 is the structural representation of enterprise's distribution outlet cable of prior art.
Fig. 2 is equipped with the structural representation of enterprise's distribution outlet cable of the present utility model.
Fig. 3 is the structural representation of cable fixation structure in the utility model.
Fig. 4 is the structural representation of wire clamp in the utility model.
Embodiment
To make the purpose of this utility model, technical scheme and advantage clearer, clear and definite, develop simultaneously implementation referring to the drawings The utility model is further described example.
Refering to Fig. 1, enterprise's distribution outlet cable structure of prior art is as shown in figure 1, between power distribution station and electricity consumption enterprise The transmission of electric power is carried out by being embedded in the cable of underground.When the cable in somewhere breaks down, it is necessary to first use cable detector device Survey trouble point is sought, pavement excavation is then carried out, after finding out that all trouble points confirmations are errorless, then carry out cable reparation, test, answer Electricity, repair time is very long, is in off-position in whole engineering time section, it is impossible to transmit electric power to enterprise.
In order to solve the above problems, refering to Fig. 2 to Fig. 4, the utility model provides a kind of emergency cable bypass, wherein, bag Include emergency cable 1 and the cable fixation structure 2 for loading emergency cable 1, the emergency cable 1 is provided at both ends with and failure The fast-wiring first 10 of cable field joint end connection, cable fixation structure 2 includes cable trough 20, crossbeam 21 and mandrel 22, institute State crossbeam 21 to be rotatably set up on the cable trough 20, the middle part of crossbeam 21 is fixedly connected with mandrel 22, and emergency cable 1 is wound In on the mandrel 22, the length for the emergency cable 1 that each mandrel 22 is wound is 20m, and emergency cable 1 is set to diameter 240mm Copper flexible cable, emergency cable 1 is wound on mandrel 22 and is stored and transported, when needing to use emergency cable 1, pull Emergency cable 1 makes it from folding and unfolding on mandrel 22, the adjoint rotation of mandrel 22 during folding and unfolding on mandrel 22 of emergency cable 1.
Further, fast-wiring first 10 includes DL type joints and TP type joints, and DL type joints are arranged at the He of emergency cable 1 The cable connection end of other cables, TP type joints are arranged at the connection end of emergency cable 1 and copper bar(That is the company of power distribution station or enterprise Connect end).
Emergency cable and on-site cable are firmly fixed for greater safety, and the two ends of emergency cable 1 are also crimped with speed and connect Wire clamp 11(As shown in Figure 4), emergency cable 1 and failure cable field joint end be fixed together by fast binding clip 11.
Because emergency cable 1 is wound on mandrel 22, jolting in transportation and vibrate easily make winding answer urgent telegram Axial movement occurs for cable 1, therefore, in the present embodiment, and the two ends of mandrel 22, which are each provided with one, is used for what emergency cable 1 was positioned Dividing plate 23, emergency cable 1 is wound on the region of mandrel 22 between two dividing plates 23.
In the present embodiment, for enterprise's 0.4kV outlet cables used in everyday, emergency cable 1 is set to 0.4kV and met an urgent need Cable, causes to be provided with electric shock accidents, each wiring of emergency cable 1 to prevent pedestrian from touching at cable connection 10kV shrinkage rubber sheaths(Do not indicated in figure), insulation protection is carried out at 10kV shrinkage rubber sheath butted lines, this reality is improved With the new security used.
Further, emergency cable bypass surrounding is provided with the safety for preventing pedestrian close and encloses shield structure(Do not marked in figure Show), the warning sign of " halting, Keep Clear-High Voltage " is also provided with some conspicuous positions.
It is use flow of the present utility model below:
When failure cable loop length be less than 40m when, directly release the end switch of fault loop two end, with meet an urgent need The cable that cable 1 need to be repaired instead of failure, two end switch are connected by fast-wiring first 10 and wire clamp 11, quick to set up interim supply Electricity bypass, emergency cable 1 is bypassed and carries out insulation protection at each wiring with 10kV shrinkages rubber sheath, and whole cable is bypassed Carry out safe enclose to cover and hang " halting, Keep Clear-High Voltage " warning sign in some conspicuous positions, scene sets full-time guardian and pacified Full monitoring, while repairing former faulty cable, tests cable after reparation, then sends a telegram in reply, and removes emergency cable 1.
When the switch distance at Method of Cable Trouble Point and any one of loop two ends is less than 20m, then faulty section cable is blocked, so Choosing is released afterwards and connects the switch terminals failure cable head for installing that one end of the bypass of emergency cable 1, and failure is got around with 0.4kV emergency cables 1 The cable that need to be repaired, docking switch terminals and cut cable, quickly set up temporary power bypass, while former faulty cable is repaired, Cable is tested after reparation, then sent a telegram in reply, emergency cable 1 is removed.
When the switch distance at Method of Cable Trouble Point and any one of loop two ends is more than 20m, then cut from the two ends at failure Disconnected faulty section cable, the cable formation that getting around failure with 0.4kV emergency cables 1 need to repair is bypassed, will by fast-wiring first 10 Emergency cable 1 docks the trouble-free cut cable in two, quickly sets up temporary power bypass, while former faulty cable is repaired, Cable is tested after reparation, then sent a telegram in reply, emergency cable 1 is removed.
The utility model is bypassed by providing a kind of emergency cable, when the outlet cable of enterprise breaks down, uses 0.4kV Emergency cable bypass temporarily replaces the cable for needing to repair that breaks down, quick to set up power supply bypass, ensure business electrical not by Construct the influences of duration and response goods and materials, allow enterprise can Power resumption in a short time, the influence having a power failure to production is dropped to It is minimum, solve prior art distribution outlet cable break down after need very long reparation, test and telegram in reply time, to enterprise The production equipment of industry causes huge destruction and brings the technical problem of quite serious economic loss.
It should be appreciated that application of the present utility model is not limited to above-mentioned citing, those of ordinary skill in the art are come Say, can according to the above description be improved or converted, all these modifications and variations should all belong to the appended power of the utility model The protection domain that profit is required.

Claims (7)

1. a kind of bypass of emergency cable, it is characterised in that including emergency cable and for loading the cable fixed knot of emergency cable Structure, the emergency cable is provided at both ends with the fast-wiring head being connected with failure cable field joint end, and the cable fixes Structure includes cable trough, crossbeam and mandrel, and the crossbeam is rotatably set up on the cable trough, fixed in the middle part of the crossbeam Mandrel is connected with, emergency cable is wound on the mandrel, emergency cable mandrel adjoint rotation during folding and unfolding on mandrel.
2. emergency cable according to claim 1 bypass, it is characterised in that the fast-wiring head include DL type joints and TP type joints, DL type joints are arranged at the cable connection end of emergency cable and other cables, and TP type joints are arranged at emergency cable With the connection end of copper bar.
3. emergency cable bypass according to claim 2, it is characterised in that the emergency cable two ends are also crimped with speed and connect Emergency cable and failure cable field joint end are fixed together by wire clamp, fast binding clip.
4. emergency cable bypass according to claim 1, it is characterised in that the mandrel two ends are each provided with a dividing plate, Emergency cable is wound on the mandrel regions between two dividing plates.
5. emergency cable bypass according to claim 1, it is characterised in that the length of the emergency cable of each mandrel winding For 20m, emergency cable is set to diameter 240mm copper flexible cable.
6. the emergency cable bypass according to any one of claim 1 to 5, it is characterised in that the emergency cable is 0.4kV 10kV shrinkage rubber sheaths, 10kV shrinkage rubber sheath butted lines are provided with emergency cable, each wiring of emergency cable Place carries out insulation protection.
7. emergency cable bypass according to claim 1, it is characterised in that emergency cable bypass surrounding, which is provided with, prevents row The close safety of people encloses shield structure, is additionally provided with warning sign.
CN201720051285.0U 2017-01-17 2017-01-17 A kind of emergency cable bypass Active CN206480996U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720051285.0U CN206480996U (en) 2017-01-17 2017-01-17 A kind of emergency cable bypass

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720051285.0U CN206480996U (en) 2017-01-17 2017-01-17 A kind of emergency cable bypass

Publications (1)

Publication Number Publication Date
CN206480996U true CN206480996U (en) 2017-09-08

Family

ID=59754537

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720051285.0U Active CN206480996U (en) 2017-01-17 2017-01-17 A kind of emergency cable bypass

Country Status (1)

Country Link
CN (1) CN206480996U (en)

Similar Documents

Publication Publication Date Title
EP1724892B1 (en) Live conductor stringing and splicing methods
US8076923B2 (en) Dead-line phase identification system and method thereof
US20110217014A1 (en) Adaptor for mounting cable connectors
KR100926445B1 (en) Uninterruptible bypassing method for underground power line using extension elbow
KR101122499B1 (en) Non-power-failure power distribution method using wire-changing device and bypasscable
GB2545730A (en) A mechanical fuse for use with overhead telecommunications cable
CN206480996U (en) A kind of emergency cable bypass
CN105527683A (en) Outdoor optical cable jumper wire and laying method
JP4839812B2 (en) Ground resistance management method
Koch et al. Second generation gas-insulated line
CN210271854U (en) Intelligent early warning cable
JP2009531826A (en) Power cable that can be searched for faults
US10578822B2 (en) Controlled shear point fiber optic cable adapter
CN113446060A (en) Subway assembled station and section seepage-proofing disaster-prevention monitoring and alarming system
KR0138717B1 (en) Cable establishment method
JP2005191727A (en) Opgw system
CN113725781B (en) Method for overlapping and crossing two adjacent same-tower double-circuit power lines by using temporary cable
Li et al. Live-line operation and maintenance of power distribution networks
EP3128630B1 (en) Method for electrical separation of the metallic sheath a hvdc mi cable
CN211206613U (en) Grounding protection equipment for shallow sea submarine optical cable maintenance
CN220551802U (en) Crude oil pipeline crossing leakage monitoring alarm system
Schiff Ready or Not...
CN108282183A (en) It is a kind of to realize the system and method for taking electricity and data transmission using multicore cable
CN103217760B (en) Reflective film optical cable
KR20100035010A (en) Monitoring system for underground power lines and equipments

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant