CN206476604U CN201720115189.8U CN201720115189U CN206476604U CN 206476604 U CN206476604 U CN 206476604U CN 201720115189 U CN201720115189 U CN 201720115189U CN 206476604 U CN206476604 U CN 206476604U
Authority
CN
China
Prior art keywords
platform
insulation material
axle
retracting device
material quickly
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720115189.8U
Other languages
Chinese (zh)
Inventor
刘武超
王森荣
干海勇
熊亮
乔介平
杨晓鹏
邱银宝
张海龙
张帅
赵晓文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 5 Co Ltd
Original Assignee
Sinohydro Bureau 5 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 5 Co Ltd filed Critical Sinohydro Bureau 5 Co Ltd
Priority to CN201720115189.8U priority Critical patent/CN206476604U/en
Application granted granted Critical
Publication of CN206476604U publication Critical patent/CN206476604U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model discloses a kind of broad place insulation material quickly retracting device, belong to road earth material constructing device, horizontally disposed first platform being connected including the dozer with hydraulic crawler excavator, the second platform is connected with the left of first platform, right side is connected with the 3rd platform, and the first platform, the second platform and the 3rd platform constitute telescopic combined platform;Hydraulic motor is installed, axle is connected to hydraulic motor by shaft coupling and is horizontal on the second platform, the two ends of axle are supported by the bracing strut on the second platform and the 3rd platform, and axle is provided with arc pressuring plate.The device is additionally provided with the guider for removing the soil being bonded on geotechnological film surface and stone and the location-plate for keeping neatly crimping during folding and unfolding insulation material.The utility model improves the folding and unfolding speed of extremely frigid zones winter earth material insulation material, it is to avoid earth material is endured cold;It fast quick-recovery can be constructed after positive temperature, it is ensured that the progress and construction quality of winter earth material construction, save the positive temperature of limited earth material and construct the period.

Description

A kind of broad place insulation material quickly retracting device
Technical field
The utility model is related to a kind of road earth material constructing device, and in particular to quick to a kind of broad place insulation material Draw off gear.
Background technology
According to《Rolling earth-rock dam job specfication》(DL/T5129-2013) and relevant regulations, should when temperature is less than 0 DEG C Stopping earth material, which is constructed and taken, slows down the earth material filled in storehouse face to prevent there is frozen soil phenomenon after covering and heat insulating measure, insulation, therefore The subzero temperature period will directly affect clay core wall of earth dam and fill the duration.Conventional earth material Winter protection measure is that covering insulation material is carried out Protection, this method can effectively alleviate the construction quality influence that earth material is endured cold brought.The river mouth Hydropower Project of Yalongjiang River two is located in East Side of Qinghai-Xizang Plateau edge zone, category west Sichuan plateau climatic province, many average temperatures of the whole year are 10.9 DEG C, and extreme maximum temperature is 35.9 DEG C, Annual lowest climate temperature is -15.9 DEG C, and March annual November to next year is the winter of this area.Winter temperature is relatively low, lowest temperature Degree is concentrated mainly on December~January next year then, January 1.8 DEG C of samming, no permafrost, daily 23:00 to next day 11:00 is The subzero temperature period.The engineering winter construction period is up to 5 wheat harvesting periods, and Annual lowest climate temperature is relatively low, therefore carrying out covering and heat insulating measure is It is highly important.Winter day and night temperature is larger, and the low temperature period part soil body can endure cold and containing ice crystal, ice crystal is heated after noon heating It can typically melt, the soil body is then subjected to frozen-thaw process.Two river mouths power station be the straight core wall rockfill dam of gravelly soil, height of dam 295m, wherein The clay core wall of earth dam gravelly soil design amount of filling 441.14 ten thousand m3, contact clay 17.96 ten thousand m3, it is 1.56 ten thousand that average every layer, which is filled area, ㎡, peak period reaches 2 Wan Duo ㎡, and the winter construction side of filling amount reaches 1,280,000 m3, account for the 28% of core wall filling building earth material.At present should Engineering is carried out using the geomembrane of " film of three cloth two " depending on earth material insulation covering protection, temperature of the construction period with scene, temperature Recover construction during higher than 0 DEG C, stop construction during less than 0 DEG C.The current ㎡ of core wall filling building area about 8000, is matched somebody with somebody using conventional forklift Close artificial progress and receive anti-geomembrane, geotechnological film quality is about 1kg or so per square meter, due to the artificial folding and unfolding geotechnique using routine Film, so every piece of geomembrane is cut into size for 20m × 6m.25 people and 1 forklift is needed to coordinate when receiving geomembrane, it is 2 small When complete receive geomembrane work.30 people and 1 forklift are needed when putting geomembrane, putting the time of geomembrane needs 3 hours.But have daily The earth material engineering time of limit is 10 hours or so, therefore in order to the maximized engineering time using the lower earth material of positive temperature, scene Postponed in the presence of receipts geomembrane time advance and covering geomembrane time, cause outside air temperature when less than 0 DEG C, earth material is not covered, Earth material insulation is not affected by guarantee.Coordinate the destruction carried to geomembrane larger using forklift, cause recycling rate of waterused relatively low, and Every piece of geomembrane size is smaller, and overall heat insulation effect is relatively low, it is necessary to consume a large amount of artificial, labor intensity is big, time length, expense Height, easily wastes the positive temperature construction period limited daily, it is impossible to meet quick continuous productive process requirement.Current China's planning is with building High earth and rockfill dam is more, is largely located in High aititude, extremely frigid zones, such as double Jiangkou, the Milin projects in Tibet, core wall filling building side's amount Greatly, the problem of there is winter construction, can in 1 year if winter stopping construction, it is considered to fill influence of the rainy season on precordial distress Less using the period of constructing, construction phase of project will be very long, it is considered to financial cost, and engineering efficiency will be severely impacted.
Utility model content
The technical problems to be solved in the utility model is to provide a kind of broad place insulation material quickly retracting device, solves Man-hour requirement, which is applied, in the insulation material covering of earth material consumes a large amount of artificial, and labor intensity is big, the defect of time length, improves earth material Insulation material folding and unfolding rapidity, it is ensured that winter earth material construction progress and construction quality the problem of.
In order to solve the above technical problems, the technical scheme that is used of the utility model for:
A kind of broad place insulation material quickly retracting device, including set with the level that the dozer of hydraulic crawler excavator is connected It is connected with the second platform on the left of the first platform put, the first platform, right side is connected with the 3rd platform, it is the first platform, second flat Platform and the 3rd platform constitute telescopic combined platform;Hydraulic motor, axle are provided with by hydraulic motor support on second platform Hydraulic motor is connected to by shaft coupling and is horizontal, the two ends of axle are by being arranged on the second platform and the 3rd platform Bracing strut is supported, and axle is provided with arc pressuring plate.
According to such scheme, the opposite guider that is open is additionally provided with second platform and the 3rd platform, it is described to lead Include a disk and two cylinders to device, one end of two cylinders is fixed on disk, has gap between two cylinders And parallel axes is set.
According to such scheme, the two ends of the axle are additionally provided with vertical location-plate.
According to such scheme, first platform is provided with chute along its length, and the second platform and the 3rd platform pass through spiral shell Tether and be connected in chute.
According to such scheme, the oil pipe of the former dozer of the hydraulic crawler excavator is connected to the tubing interface of hydraulic motor.
According to such scheme, second platform and the 3rd one end of platform away from the first platform are provided with slip limited block.
According to such scheme, reinforcing plate is transversely provided with below first platform.
According to such scheme, the axle is mainly made up of three parts, and left and right ends are solid shaft portion, and centre is hollow shaft Part.
According to such scheme, the bracing strut is including vertical fixed part and uses hinge and bolted movable part Point.
Compared with prior art, the beneficial effects of the utility model are:Improve extremely frigid zones winter earth material insulation material Folding and unfolding speed, it is to avoid earth material is endured cold;Insulation material quickly is packed up after positive temperature, can quickly recover construction, it is ensured that winter soil Expect the progress and construction quality of construction, save the limited earth material positive temperature construction period, also provide experience for similar engineering.
Brief description of the drawings
The specific embodiment party of broad place insulation material quickly retracting device a kind of to the utility model below in conjunction with the accompanying drawings Formula is described further, wherein:
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the positive schematic diagram that the utility model is arranged on hydraulic crawler excavator dozer;
Fig. 3 is the side schematic view that the utility model is arranged on hydraulic crawler excavator dozer.
Each label is interpreted as in figure:1- hydraulic motors, 101- tubing interfaces, 2- shaft couplings, 3- location-plates, 4- arc pressures Plate, 5- axles, 6- hydraulic motor supports, 7- bracing struts, the platforms of 8- second, 9- guiders, the platforms of 10- first, 11- the 3rd is flat Platform.
Embodiment
The utility model is mainly the Collapsible structure body being made up of fixed part, rotating part and targeting part, main The engineering that the placement grinding that being used for the construction time has the outdoor earth material of large area of subzero temperature phenomenon appearance is constructed.It can be used for 3m~6m The folding and unfolding construction of the insulation material of width, after platform shrinks completely, will not influence the normal work of hydraulic crawler excavator.
Wherein fixed part is main flat by hydraulic motor support 6, bracing strut 7, the first platform 10, the second platform 8 and the 3rd Platform 11 is constituted.The dozer of hydraulic crawler excavator is reequiped in the case where not influenceing bucket hydraulic excavator normal work. First platform 10, the second platform 8 and the 3rd platform 11 constitute the combined platform of retractable, and combined platform level, which is welded on, to be pushed away On mamoty.Operate the dozer of hydraulic crawler excavator away from ground 300mm position, be fixed, then by the first platform 10 are welded on fixed dozer, and the oil pipe of dozer is disassembled are connected on hydraulic motor 1.First platform 10, It is attached between second platform 8 and the 3rd platform 11 using M30 bolts, combined platform up to 7.24m, width is 1m, the Two platforms 8 and the 3rd platform 11 positioned at the left side and right side of the first platform 10 and can slide to the scope of the first platform 10 respectively Interior, the overall length of combined platform is 4.04m after contraction, and width is 1m.All platforms are made using channel-section steel combination, wherein The length of second platform 8 and the 3rd platform 11 is 2m, and width is 1m.The length direction of second platform 8 and the 3rd platform 11 Channel-section steel lower surface is welded with the steel plate that length, width and height are followed successively by 2000mm × 140mm × 20mm, and the second platform 8 and the 3rd platform 11 exist Close to one end of the first platform 10 provided with 6 M30 bolts hole, the steel plate conduct that two pieces of thickness are 20mm is welded in the end of the other end Slip limiting plate.One piece of length, width and height is welded on the second platform 8 and the 3rd platform 11 and is followed successively by 140mm × 140mm × 10mm's 4 M20 bolt is set on steel plate, steel plate, for connecting guider 9.The length of first platform 10 is 4m, width 2m, in length The chute that length and width are respectively 3800mm × 3.8mm is cut out on the channel-section steel for spending direction, it is wide to be laterally also welded with 7 block lengths thereunder Height is followed successively by 140mm × 100mm × 20mm steel plate as reinforcing plate.When second platform 8 and the 3rd platform 11 need to slide, only The nut of M30 bolts need to be unclamped, you can realize the second platform 8 and the 3rd platform 11 on the first platform 10 slip, realize receive Contracting function.Hydraulic motor support 6 and bracing strut 7 are additionally provided with the second platform 8, bracing strut 7 is provided with the 3rd platform 11.Axle 7 points of support is vertical fixed part and uses hinge and the bolted movable parts of M20, and the through-hole diameter of movable part is 91mm, a diameter of 90mm of the position axle 5, movable part can facilitate dismounting axle 5 at any time.
Rotating part is mainly made up of hydraulic motor 1, shaft coupling 2 and axle 5.Using the oil pipe of hydraulic crawler excavator dozer, The tubing interface 101 on hydraulic motor 1 is connected to, in the handle for driving the former dozer of in-house operation of hydraulic crawler excavator, you can control The rotary speed of hydraulic motor 1 processed, a mark is done by installation site of two oil pipes on hydraulic motor 1 respectively, it is ensured that every time During operation, the direction of rotation of hydraulic motor 1 is consistent.The model selection of hydraulic motor 1 is rotation according to the weight of geomembrane When the torque capacity that needs and optimum speed determine that the connection between hydraulic motor 1 and axle 5 need to customize shaft coupling 2 as requested. A diameter of 100mm of axle 5, the two ends of axle 5 are solid shafting.Some a diameter of 90mm in the middle of solid shafting, its length is 50mm, This is partially disposed in the movable part of bracing strut 7, for preventing the transverse shifting of axle 5.Left end solid shafting be and customization shaft coupling 2 The part of connection, and bore a diameter of 20mm pin-and-hole.The center section of axle 5 is hollow shaft, and hollow shaft portion and left end are long The 300mm long 200mm of solid shaft portion, right-hand member solid shaft portion is connected using welding manner.4 arcs are set on 5 axles Pressing plate 4, the length of arc pressuring plate 4 is 500mm, and width is 20mm, and each arc pressuring plate 4 bores 3 M10 bolts hole, and in pair of axle 5 Position is answered to bore M10 bolt hole, for fixing geomembrane on axle 5.A width of 6m × the 120m of geomembrane length that the engineering is intended that, Maximum gauge about 500mm is rolled, therefore the center of axle 5 of the utility model is 650mm from the height of the first platform 10.
Targeting part is mainly made up of location-plate 3 and guider 9.Also set close to the position of bracing strut 7 at the two ends of axle 5 There is the vertical circular location-plate 3 being bolted to by M10 on axle 5, for keeping neatly crimping during folding and unfolding insulation material, prevent Only there are inclination conditions during geomembrane folding and unfolding.The opposite guiding that is open is additionally provided with the second platform 8 and the 3rd platform 11 Device 9, it is 25mm steel pipe cylinders that the guider 9, which includes a disk and two internal diameters, and one end of two cylinders is fixed to On disk, between two cylinders there is gap and parallel axes 5 to set, geotechnological film thickness is about 5mm, that is, control two cylinders Spacing is 6mm.Disk is fixed on the second platform 8 and the 3rd platform 11 by disc holder.The main purpose of guider 9 is The soil and stone being bonded on geotechnological film surface are removed, can stretch the geomembrane of fold, and play geomembrane folding and unfolding direction Impulse.One end of geomembrane is cut by the spacing of arc pressuring plate 4, it is ensured that geomembrane can be fixed by arc pressuring plate 4, And geomembrane has to pass through guider 9.
The device is when in use, it is necessary to slides to each platform and is fixed after determining precision afterwards in place, then carries out axle 5 Install, axle 5 need to ensure its concentricity when installing.After each retracting is discharged into, suspender belt is used cooperatively using excavator bucket The geomembrane completed will be wound or axle 5 hangs, then changed a roll of geomembrane or an axle 5 proceeds folding and unfolding work, hanging Dress process, notes protection axle 5 to prevent mechanically damaged.After the completion of folding and unfolding work, fixed after platform to be contracted to 4m, not shadow Ring the normal work on dam facing of excavator.

Claims (9)

1. a kind of broad place insulation material quickly retracting device, it is characterised in that:Including connecting with the dozer of hydraulic crawler excavator The second platform (8) is connected with the left of horizontally disposed first platform (10) connect, the first platform (10), right side is connected with the 3rd Platform (11), the first platform (10), the second platform (8) and the 3rd platform (11) constitute telescopic combined platform;Second platform (8) hydraulic motor (1) is provided with by hydraulic motor support (6) on, axle (5) is connected to hydraulic motor (1) by shaft coupling (2) And be horizontal, the two ends of axle (5) are supported by the bracing strut (7) being arranged on the second platform (8) and the 3rd platform (11), Axle (5) is provided with arc pressuring plate (4).
2. a kind of broad place insulation material quickly retracting device according to claim 1, it is characterised in that:Described second The opposite guider (9) that is open is additionally provided with platform (8) and the 3rd platform (11), the guider (9) includes a circle Disk and two cylinders, one end of two cylinders are fixed on disk, have gap between two cylinders and parallel axes (5) is set Put.
3. a kind of broad place insulation material quickly retracting device according to claim 1, it is characterised in that:The axle (5) two ends are additionally provided with vertical location-plate (3).
4. a kind of broad place insulation material quickly retracting device according to claim 1, it is characterised in that:Described first Platform (10) is provided with chute along its length, and the second platform (8) and the 3rd platform (11) are bolt-connected in chute.
5. a kind of broad place insulation material quickly retracting device according to claim 1, it is characterised in that:The hydraulic pressure The oil pipe of excavator original dozer is connected to the tubing interface (101) of hydraulic motor (1).
6. a kind of broad place insulation material quickly retracting device according to claim 1, it is characterised in that:Described second The one end of platform (8) and the 3rd platform (11) away from the first platform (10) is provided with slip limited block.
7. a kind of broad place insulation material quickly retracting device according to claim 1, it is characterised in that:Described first Reinforcing plate is transversely provided with below platform (10).
8. a kind of broad place insulation material quickly retracting device according to claim 1, it is characterised in that:The axle (5) mainly it is made up of three parts, left and right ends are solid shaft portion, centre is hollow shaft portion.
9. a kind of broad place insulation material quickly retracting device according to claim 1, it is characterised in that:The axle branch Frame (7) is including vertical fixed part and uses hinge and bolted movable part.
CN201720115189.8U 2017-02-08 2017-02-08 A kind of broad place insulation material quickly retracting device Active CN206476604U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720115189.8U CN206476604U (en) 2017-02-08 2017-02-08 A kind of broad place insulation material quickly retracting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720115189.8U CN206476604U (en) 2017-02-08 2017-02-08 A kind of broad place insulation material quickly retracting device

Publications (1)

Publication Number Publication Date
CN206476604U true CN206476604U (en) 2017-09-08

Family

ID=59748858

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720115189.8U Active CN206476604U (en) 2017-02-08 2017-02-08 A kind of broad place insulation material quickly retracting device

Country Status (1)

Country Link
CN (1) CN206476604U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106744079A (en) * 2017-02-08 2017-05-31 中国水利水电第五工程局有限公司 A kind of broad place insulation material quickly retracting device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106744079A (en) * 2017-02-08 2017-05-31 中国水利水电第五工程局有限公司 A kind of broad place insulation material quickly retracting device

Similar Documents

Publication Publication Date Title
CN106744079A (en) A kind of broad place insulation material quickly retracting device
CN108166486B (en) Deep buried pipe type prefabricated energy pipe pile and construction process thereof
CN207597376U (en) Tidal Flat Reclamation blowing-filling sludge burning into sand layer foundation reinforcing structure
CN104089089A (en) Pressure backfill type elastic buried pipe construction method
CN206646386U (en) A kind of pitch-rood
CN102041800A (en) Method for constructing PVC (polyvinyl chloride) composite geomembrane watertight core of earth-rockfill dam
CN111441227B (en) Induced joint cutting device and method for preventing frost heaving, thawing and sinking of existing frozen soil roadbed and highway
CN206476604U (en) A kind of broad place insulation material quickly retracting device
CN107035388A (en) A kind of tunnel double-lining compounded rubber lifting locking plug template and its application method
CN107482538A (en) A kind of cable direct-burried servicing unit
CN207672397U (en) A kind of milling-planing device for asphalt paving
CN103741708B (en) Prefabricated concrete rod sleeve basis
CN207434770U (en) A kind of air pressure balanced-type broadness fluctuating place keeps the temperature rainproof material quickly retracting machine
CN207144867U (en) A kind of detachable liquid storage tank
CN208251678U (en) Holes filling bracket and heritage buildings underground opening interstitital texture
CN206956754U (en) A kind of easy device for foundation ditch local dewatering
CN101660418B (en) Box culvert jack-in replacement rectangular pipe support method used for tunnel construction
CN107386085A (en) A kind of lightweight floor crushing device suitable for urban pavement
CN212404750U (en) Induced seam cutting device
CN113931171A (en) Protection device for preventing tubular pile from being frozen and expanded and damaged
CN203684258U (en) Prefabricated concrete rod sleeve foundation
CN210238319U (en) Urban bridge pastes carbon cloth reinforcing apparatus
CN109763682B (en) Underground refrigeration house structure and construction method thereof
CN209669696U (en) A kind of anti-fall ice production apparatus of intelligence suitable for overpass discharge outlet
CN206268602U (en) A kind of earth source heat pump horizontal tube crosses line protection device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant