CN206448544U - A kind of protection network of construction - Google Patents

A kind of protection network of construction Download PDF

Info

Publication number
CN206448544U
CN206448544U CN201720095272.3U CN201720095272U CN206448544U CN 206448544 U CN206448544 U CN 206448544U CN 201720095272 U CN201720095272 U CN 201720095272U CN 206448544 U CN206448544 U CN 206448544U
Authority
CN
China
Prior art keywords
protection
protection network
stratum reticulare
connecting rope
network layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720095272.3U
Other languages
Chinese (zh)
Inventor
张贺翔
王璐鹏
王若谷
欧玉玲
杨裕智
何昕蓓
罗燕文
欧庆鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Pfizer Construction Engineering Co Ltd
Original Assignee
Guangxi Pfizer Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Pfizer Construction Engineering Co Ltd filed Critical Guangxi Pfizer Construction Engineering Co Ltd
Priority to CN201720095272.3U priority Critical patent/CN206448544U/en
Application granted granted Critical
Publication of CN206448544U publication Critical patent/CN206448544U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of protection network of construction, including the first protection stratum reticulare, the second protection stratum reticulare, the 3rd protection network layer and flexible wire ropes, the second protection stratum reticulare is connected to the inner side of the 3rd protection network layer, and second protection stratum reticulare be located at the 3rd protection network layer upside, the first protection stratum reticulare is located at the upside of the second protection stratum reticulare, the nylon connecting rope is connected to the bottom of the 3rd protection network, described to link up with the two ends for being fixedly mounted on nylon connecting rope, the flexible wire ropes are embedded in the inner chamber of nylon connecting rope.The protection network of the construction is provided with the protection stratum reticulare that elastic string is constituted; buffer protection is carried out to workman; impact of the workman to protection network can be reduced simultaneously; nylon connecting rope inside the 3rd protection network with being equipped with flexible wire ropes; the overall intensity of protection network can be increased; provided with multilayer proofing stratum reticulare, protection effect is good, prevents from influenceing the life security of workman when protection network is damaged.

Description

A kind of protection network of construction
Technical field
The utility model is related to technical field of building construction, specially a kind of protection network of construction.
Background technology
At present, in construction, protection network generally is built in architecture enclosing, on the one hand strengthens construction safety, it is to avoid Building material slides and injures workmen, is on the other hand also prevented from dust diffusion, and influence health pollutes environment.At present The protection network of use largely connects nylon wire on square steelframe.
In traditional construction protection network, simple in construction, low intensity, when high level has heavy objects crash net, The intensity of nylon wire is difficult to keep out gravitational thrusts, and cracky causes object to expose from protection network, abnormally dangerous, when workman is not small The heart effectively can not carry out buffer protection when dropping to workman, easily come to harm.
Utility model content
The purpose of this utility model is to provide a kind of protection network of construction, to solve to carry in above-mentioned background technology The traditional construction protecting screen structure gone out is simple, low intensity, when high level has heavy objects crash net, nylon wire Intensity is difficult to keep out gravitational thrusts, and cracky effectively can not carry out buffer protection to workman when workman's imprudence drops, hold Vulnerable problem.
To achieve the above object, the utility model provides following technical scheme:A kind of protection network of construction, including First protection stratum reticulare, the second protection stratum reticulare, the 3rd protection network layer, nylon connecting rope, junction button, hook and flexible wire ropes, institute The inner side that the second protection stratum reticulare is connected to the 3rd protection network layer is stated, and the second protection stratum reticulare is located at the upside of the 3rd protection network layer, The first protection stratum reticulare is connected to the inner side of the 3rd protection network layer, and the first protection stratum reticulare is located at the upper of the second protection stratum reticulare Side, the nylon connecting rope is connected between the bottom of the 3rd protection network, and nylon connecting rope and the 3rd protection network by connection Button is connected, described to link up with the two ends for being fixedly mounted on nylon connecting rope, and the flexible wire ropes are embedded in nylon connecting rope Inner chamber.
It is preferred that, the first protection stratum reticulare is made up of elastic string, and the first protection stratum reticulare is well shape structure.
It is preferred that, the second protection stratum reticulare is made of nylon wire, and the second protection stratum reticulare is network structure.
It is preferred that, the 3rd protection network layer is circular ring, and the inside of the 3rd protection network layer is provided with flexible steel wire Rope.
Compared with prior art, the beneficial effects of the utility model are:The protection network of the construction is provided with elastic string The protection stratum reticulare of composition, with good elasticity, when workman drops, can carry out buffer protection, while work can be reduced to workman Impact of the people to protection network, nylon connecting rope can increase protection network overall with being equipped with flexible wire ropes inside the 3rd protection network Intensity, service life is long, and provided with multilayer proofing stratum reticulare, protection effect is good, when preventing that protection network is damaged, influences the life of workman Safety.
Brief description of the drawings
Fig. 1 is the utility model structural representation;
Fig. 2 is that the utility model first protects net-layer structure schematic diagram;
Fig. 3 is that the utility model second protects net-layer structure schematic diagram;
Fig. 4 is the protection network Rotating fields schematic diagram of the utility model the 3rd;
Fig. 5 is the utility model nylon connecting rope internal structure schematic diagram.
In figure:1st, the first protection stratum reticulare, the 2, second protection stratum reticulare, the 3, the 3rd protection network layer, 4, nylon connecting rope, 5, connection Button, 6, hook, 7, flexible wire ropes.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the utility model embodiment is carried out Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of the utility model, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment obtained, belongs to the scope of the utility model protection.
Fig. 1-5 are referred to, the utility model provides a kind of technical scheme:A kind of protection network of construction, including the The one protection protection of stratum reticulare 1, second stratum reticulare 2, the 3rd protection network layer 3, nylon connecting rope 4, junction button 5, hook 6 and flexible wire ropes 7, the second protection stratum reticulare 2 is connected to the inner side of the 3rd protection network layer 3, and the second protection stratum reticulare 2 is located at the upper of the 3rd protection network layer 3 Side, the first protection stratum reticulare 1 is connected to the inner side of the 3rd protection network layer 3, and the first protection stratum reticulare 1 is located at the second protection stratum reticulare 2 Upside, nylon connecting rope 4 is connected between the bottom of the 3rd protection network 3, and the protection network 3 of nylon connecting rope 4 and the 3rd by even Connect button 5 to be connected, hook 6 is fixedly mounted on the two ends of nylon connecting rope 4, flexible wire ropes 7 are embedded in the interior of nylon connecting rope 4 Chamber, hook 6 is provided with elastic buckles, prevents hook 6 from coming off.
In above-described embodiment, specifically, the first protection stratum reticulare 1 is made up of elastic string, and the first protection stratum reticulare 1 is well shape Structure, with good elasticity, when workman drops, can carry out buffer protection, while workman can be reduced to protection network to workman Impact.
In above-described embodiment, specifically, the second protection stratum reticulare 2 is made of nylon wire, and the second protection stratum reticulare 2 is netted Structure, can strengthen the protective effect to workman, when preventing that protection network is damaged, influence the life security of workman.
In above-described embodiment, specifically, the 3rd protection network layer 3 is circular ring, and the inside of the 3rd protection network layer 3 is set Flexible steel wire rope 7, can increase the overall intensity of protection network.
Operation principle:In the protection network using the construction, need first to the working protection network of whole building There is the understanding in a structure, can more easily be used, by hook of the protection network by the two ends of nylon connecting rope 4 6 are connected to the lower end of operation platform, due to the first protection stratum reticulare 1 constituted provided with elastic string, with good elasticity, work as workman When dropping, buffer protection can be carried out to workman, while impact of the workman to protection network, nylon connecting rope 4 and three proofings can be reduced Flexible wire ropes 7 are equipped with inside protecting wire net 3, the overall intensity of protection network can be increased, prevent from causing Buddhist nun during heavy impact protection network The fracture of imperial connecting rope 4, so that the life security of workman is influenceed, while provided with multigroup protection stratum reticulare, making with good protection With being effectively protected the safety of construction worker.
In summary, general principle of the present utility model, principal character and advantage has been shown and described above.The industry Technical staff it should be appreciated that the utility model is not restricted to the described embodiments, described in above-described embodiment and specification only It is to illustrate principle of the present utility model, on the premise of the utility model spirit and scope are not departed from, the utility model also has Various changes and modifications, these changes and improvements are both fallen within the range of claimed the utility model.The utility model requirement Protection domain is defined by appended claims and its effect thing.

Claims (4)

1. a kind of protection network of construction, including the first protection stratum reticulare (1), the second protection stratum reticulare (2), the 3rd protection network layer (3), nylon connecting rope (4), junction button (5), hook (6) and flexible wire ropes (7), it is characterised in that:Second protection network Layer (2) is connected to the inner side of the 3rd protection network layer (3), and the second protection stratum reticulare (2) is located at the upside of the 3rd protection network layer (3), The first protection stratum reticulare (1) is connected to the inner side of the 3rd protection network layer (3), and the first protection stratum reticulare (1) is located at the second protection The upside of stratum reticulare (2), the nylon connecting rope (4) be connected to the 3rd protection network layer (3) bottom, and nylon connecting rope (4) with It is connected between 3rd protection network layer (3) by junction button (5), the hook (6) is fixedly mounted on the two of nylon connecting rope (4) End, the flexible wire ropes (7) are embedded in the inner chamber of nylon connecting rope (4).
2. a kind of protection network of construction according to claim 1, it is characterised in that:The first protection stratum reticulare (1) it is made up of elastic string, and the first protection stratum reticulare (1) is well shape structure.
3. a kind of protection network of construction according to claim 1, it is characterised in that:The second protection stratum reticulare (2) it is made of nylon wire, and the second protection stratum reticulare (2) is network structure.
4. a kind of protection network of construction according to claim 1, it is characterised in that:The 3rd protection network layer (3) it is circular ring, and the inside of the 3rd protection network layer (3) is provided with flexible wire ropes (7).
CN201720095272.3U 2017-01-19 2017-01-19 A kind of protection network of construction Expired - Fee Related CN206448544U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720095272.3U CN206448544U (en) 2017-01-19 2017-01-19 A kind of protection network of construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720095272.3U CN206448544U (en) 2017-01-19 2017-01-19 A kind of protection network of construction

Publications (1)

Publication Number Publication Date
CN206448544U true CN206448544U (en) 2017-08-29

Family

ID=59667802

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720095272.3U Expired - Fee Related CN206448544U (en) 2017-01-19 2017-01-19 A kind of protection network of construction

Country Status (1)

Country Link
CN (1) CN206448544U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109736194A (en) * 2019-03-07 2019-05-10 湖南科技大学 A kind of anti-fall ice production apparatus of intelligence suitable for overpass discharge outlet
CN110130631A (en) * 2019-05-15 2019-08-16 深汕特别合作区磐汩新材料有限公司 A kind of safety guard net
CN114412213A (en) * 2021-12-23 2022-04-29 中国华冶科工集团有限公司 Protection device and method for steel structure roof installation
CN114607160A (en) * 2022-03-16 2022-06-10 中交第四公路工程局有限公司 Novel building safety net
CN114607160B (en) * 2022-03-16 2024-05-10 中交第四公路工程局有限公司 Novel building safety net

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109736194A (en) * 2019-03-07 2019-05-10 湖南科技大学 A kind of anti-fall ice production apparatus of intelligence suitable for overpass discharge outlet
CN110130631A (en) * 2019-05-15 2019-08-16 深汕特别合作区磐汩新材料有限公司 A kind of safety guard net
CN114412213A (en) * 2021-12-23 2022-04-29 中国华冶科工集团有限公司 Protection device and method for steel structure roof installation
CN114412213B (en) * 2021-12-23 2023-09-08 中国华冶科工集团有限公司 Protective device and method for steel structure roof installation
CN114607160A (en) * 2022-03-16 2022-06-10 中交第四公路工程局有限公司 Novel building safety net
CN114607160B (en) * 2022-03-16 2024-05-10 中交第四公路工程局有限公司 Novel building safety net

Similar Documents

Publication Publication Date Title
CN206448544U (en) A kind of protection network of construction
CN205421984U (en) Net is weighed down in high air defence with cushioning effect
CN206873949U (en) Construction regularization floor steel platform for material unloading
CN209835427U (en) Tower crane hook body with protector for construction
CN207079898U (en) Outer hanging basket structure
CN207845065U (en) A kind of manned crane hanging basket
CN206634949U (en) A kind of building tower crane cat ladder and safeguard
CN202154960U (en) Safety belt for high-altitude working
CN208591477U (en) A kind of high altitude operation safe fall-proof rope
CN201794282U (en) Platform device for high-altitude operation
CN209052275U (en) Land petroleum works equipment lifting collision prevention device
CN214402848U (en) Safe plain net convenient to it is fixed
CN206383118U (en) A kind of electric power tool case with shatter-resistant performance
CN207493072U (en) A kind of work about electric power catching device with safety protection function
CN205460569U (en) Safety rope with buffering area
CN205224632U (en) Safety protecting mesh
CN209429565U (en) A kind of building safety protective net of installation easy to disassemble
CN210032700U (en) Lightweight stake hole protector
CN204319555U (en) 3 back belt type safety belts
CN219241413U (en) Novel high-strength dense-mesh type safe vertical net
CN209670874U (en) A kind of novel building security protection ladder
CN211569853U (en) Lifting device for hoisting plate girder
CN210331471U (en) Anti-falling protective tool for aerial work
CN204252568U (en) A kind of security protection insurance card device
CN207934477U (en) A kind of novel anti-falling safety net structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170829

Termination date: 20220119

CF01 Termination of patent right due to non-payment of annual fee