CN206429797U - The band prefabricated direct-buried heat insulation elbow of the seamless polyethylene of straight length - Google Patents

The band prefabricated direct-buried heat insulation elbow of the seamless polyethylene of straight length Download PDF

Info

Publication number
CN206429797U
CN206429797U CN201720096982.8U CN201720096982U CN206429797U CN 206429797 U CN206429797 U CN 206429797U CN 201720096982 U CN201720096982 U CN 201720096982U CN 206429797 U CN206429797 U CN 206429797U
Authority
CN
China
Prior art keywords
straight length
elbow
heat insulation
protection tube
tube section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720096982.8U
Other languages
Chinese (zh)
Inventor
吴月兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Huidong Pipeline Ltd By Share Ltd
Original Assignee
Hebei Huidong Pipeline Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Huidong Pipeline Ltd By Share Ltd filed Critical Hebei Huidong Pipeline Ltd By Share Ltd
Priority to CN201720096982.8U priority Critical patent/CN206429797U/en
Application granted granted Critical
Publication of CN206429797U publication Critical patent/CN206429797U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Thermal Insulation (AREA)

Abstract

The utility model discloses a kind of band prefabricated direct-buried heat insulation elbow of the seamless polyethylene of straight length, it includes outer protection tube, heat-insulation layer and elbow, the outer protection tube is the integral structure of thermoforming, it is sleeved on elbow, cavity is formed between outer protection tube inwall and elbow outer wall, the heat-insulation layer is filled in cavity, the elbow includes curved tube section and straight length, the straight length is connected to curved tube section two ends, the outer protection tube includes outer shield curved tube section and outer shield straight length, the outer shield straight length is connected to outer shield curved tube section two ends, when the utility model is connected at the scene, outer protection tube is the integral structure of thermoforming, not only without weld seam, outer protection tube integral rigidity is ensured, and with good airproof performance, bear the advantages of pressure is big, outer protection tube and elbow two ends are provided with straight length simultaneously, when connecting at the scene, straight length docks tighter with insulation straight tube, make welding very firm, finally increase the service life, ensure that pipe network being capable of long-term safety operation simultaneously.

Description

The band prefabricated direct-buried heat insulation elbow of the seamless polyethylene of straight length
Technical field
The utility model is related to a kind of direct-burried heat supply heat insulation elbow, and in particular to a kind of band seamless polyethylene of straight length is prefabricated Direct-burried heat insulation elbow.
Background technology
The making of prefabricated direct-buried heat insulation elbow has two ways both at home and abroad at present, and one is that heat insulation elbow polyethylene outer protective pipe is Pass through sweat soldering by being cut into given shape;Two be that heat insulation elbow polyethylene outer protective pipe is formed in one, but outer protection tube With elbow two ends without straight length, i.e., prefabricated direct-buried heat insulation elbow is by steel elbow and the outer protection tube elbow of welding fabrication(Or Integrally formed outer protection tube)And polyurethane foaming thermal insulation material composition.
If polyethylene outer protective pipe is formed by being cut into given shape by sweat soldering, due to outer protection tube welding Into in outer protection tube surface formation multiple-pass weld, at present without detection device, often through its quality condition is visually observed, weld seam is strong Degree causes the pressure that can bear to reduce, is also easy to produce cracking, sealing is poor, influence heat insulation effect, make well below strength of parent The shortcomings of using the lost of life, the weak link as conduit running;And the integrally formed outer protection tube elbow without straight length, During joint connection in site, it is unreal interface easily occur, causes imprecision, produces gap, the problem of final not prison welding is solid, it is possible to give Pipe network operation brings hidden danger.
Therefore, inventor concentrates on studies, and invents a kind of band prefabricated direct-buried heat insulation elbow of the seamless polyethylene of straight length, uses The utility model, outer protection tube is the integral structure of thermoforming, not only without weld seam, has ensured outer protection tube integral rigidity, and With good airproof performance, pressure is born greatly, the advantages of service life is long, while outer protection tube and elbow two ends are provided with straight length, existing During connection, straight length docks tighter with insulation straight tube, makes welding very firm, finally increases the service life, simultaneously guarantor Hindering pipe network being capable of long-term safety operation.
Utility model content
The technical problems to be solved in the utility model is:
A kind of band prefabricated direct-buried heat insulation elbow of the seamless polyethylene of straight length is provided, its outer protection tube is the integral type knot of thermoforming Structure, solves current outer protection tube and is formed by being cut into given shape by sweat soldering, the weld seam caused is easy to crack, and sealing is poor, Bear the low shortcoming of pressure, and outer protection tube is formed in one, but itself and elbow two ends do not have caused by straight length with insulation When straight tube is docked, it is unreal interface easily occur, causes imprecision, produces gap, the problem of final not prison welding is solid.
In order to solve the above-mentioned technical problem, the utility model discloses a kind of prefabricated direct-buried guarantor of the band seamless polyethylene of straight length Warm elbow, it includes outer protection tube, heat-insulation layer and elbow, and the outer protection tube is the integral structure of thermoforming, and it is sleeved on elbow On, cavity is formed between outer protection tube inwall and elbow outer wall, the heat-insulation layer is filled in cavity, the elbow include curved tube section and Straight length, the radius of curvature of the curved tube section is R, and the external diameter of curved tube section is D, and the length range of the radius of curvature R is R < 5D, the straight length is connected to curved tube section two ends, and the outer protection tube includes outer shield curved tube section and outer shield straight length, described outer The radius of curvature for protecting curved tube section is equal with the radius of curvature of curved tube section, and the outer shield straight length is connected to outer shield curved tube section two End.
Further, the outer protection tube is polyethylene material.
Further, the kernel of section of the outer protection tube and elbow is overlapped.
Further, the outer shield flow development length is 200mm.
Further, the heat-insulation layer is polyurethane foam.
Further, the elbow is metal material.
Further, the elbow is compressing.
Further, the flow development length is not less than 400mm.
Further, the straight length and curved tube section integrated formed structure.
Further, the outer shield straight length and outer shield curved tube section integrated formed structure.
When the utility model is connected at the scene, outer protection tube is the integral structure of thermoforming, not only without weld seam, is ensured Outer protection tube integral rigidity, and with good airproof performance, bear pressure greatly, the advantages of service life is long, while outer protection tube and elbow Two ends are provided with straight length, when connecting at the scene, and straight length docks tighter with being incubated straight tube, makes welding very firm, finally Increase the service life, while ensureing that pipe network being capable of long-term safety operation.
Brief description of the drawings
Fig. 1 is the utility model structural representation;
Legend:1. outer protection tube, 11. outer shield curved tube sections, 12. outer shield straight lengths, 2. heat-insulation layers, 3. elbows, 31. curved tubes section, 32. straight length.
Embodiment
The utility model is described further with reference to embodiment, but is not limited to the content on specification.
The utility model discloses a kind of band prefabricated direct-buried heat insulation elbow of the seamless polyethylene of straight length, it include outer protection tube 1, Heat-insulation layer 2 and elbow 3, the outer protection tube 1 are the integral structure of polyethylene thermoforming, described to be thermoformed into fire bending system or hot pressing System, not only without weld seam, has ensured outer protection tube integral rigidity, and with good airproof performance, bear the advantages of pressure is big, outer protection tube 1 is sleeved on elbow 3 and is overlapped with the kernel of section of elbow 3, and cavity, the guarantor are formed between the inwall of outer protection tube 1 and the outer wall of elbow 3 Warm layer 2 is filled in cavity, and heat-insulation layer 2 is polyurethane foam, and full polyurethane foam is filled in cavity, same thickness is formed Heat-insulation layer 2, makes insulation uniform, and the elbow 3 is that metal material is integrally compressing, and it includes curved tube section 31 and straight length 32, The radius of curvature of the curved tube section 31 is R, and the external diameter of curved tube section 31 is D, and the length range of the radius of curvature R is R < 5D, institute State straight length 32 and be connected to 31 two ends of curved tube section, its length establishing criteria GB/T29047 is determined, will for meet welding 400mm should be not less than by asking, and the outer protection tube 1 includes outer shield curved tube section 11 and outer shield straight length 12, the outer shield curved tube section 11 Radius of curvature is equal with the radius of curvature of curved tube section 31, and the outer shield straight length 12 is connected to 11 two ends of outer shield curved tube section, When connecting at the scene, outer shield straight length 12 docks tighter with insulation straight tube, makes welding very firm, increases the service life, The outer shield length establishing criteria GB/T29047 of straight length 12 determines that its length is 200mm.
Elbow 3 with straight length is prior art, makes and produces according to the standard of country, its radius of curvature is less than outside it 5 times of footpath.
Polyurethane foam is by isocyanates(Monomer)It is polymerized with hydroxy compounds, with good heat insulating, heat conduction system Number bottom, easy to use quick, ageing-resistant, the advantages of service life is long, is most preferable heat-insulating material using in utilidor.
When being connected at the scene using the utility model, outer protection tube is the integral structure of thermoforming, not only without weld seam, is protected Hindered outer protection tube integral rigidity, and with good airproof performance, it is big to bear pressure, the advantages of service life is long, at the same outer protection tube and Elbow is provided at both ends with straight length, when connecting at the scene, and straight length docks very tight with insulation straight tube, makes welding more firm Gu, finally increase the service life, while ensureing that pipe network being capable of long-term safety operation.
Obviously, above-mentioned embodiment of the present utility model is only intended to clearly illustrate the utility model example, And it is not the restriction to embodiment of the present utility model.For affiliated one of ordinary skill in the art, above-mentioned It can also be made other changes in different forms on the basis of explanation.Here all embodiments can not be given thoroughly Lift.It is every to belong to obvious changes or variations that the technical solution of the utility model extends out still in the utility model Protection domain row.

Claims (10)

1. a kind of band prefabricated direct-buried heat insulation elbow of the seamless polyethylene of straight length, it is characterised in that:It includes outer protection tube(1), insulation Layer(2)And elbow(3), the outer protection tube(1)For the integral structure of thermoforming, it is sleeved on elbow(3)On, outer protection tube(1) Inwall and elbow(3)Cavity, the heat-insulation layer are formed between outer wall(2)It is filled in cavity, the elbow(3)Including curved tube section (31)And straight length(32), the curved tube section(31)Radius of curvature be R, curved tube section(31)External diameter be D, the radius of curvature R length range is R < 5D, the straight length(32)It is connected to curved tube section(31)Two ends, the outer protection tube(1)Including outer Protect curved tube section(11)With outer shield straight length(12), the outer shield curved tube section(11)Radius of curvature and curved tube section(31)Curvature half Footpath is equal, the outer shield straight length(12)It is connected to outer shield curved tube section(11)Two ends.
2. the prefabricated direct-buried heat insulation elbow of the seamless polyethylene of band straight length according to claim 1, it is characterised in that:It is described outer Pillar(1)For polyethylene material.
3. the prefabricated direct-buried heat insulation elbow of the seamless polyethylene of band straight length according to claim 1 or 2, it is characterised in that:Institute State outer protection tube(1)And elbow(3)Kernel of section overlap.
4. the prefabricated direct-buried heat insulation elbow of the seamless polyethylene of band straight length according to claim 1, it is characterised in that:It is described outer Protect straight length(12)Length is 200mm.
5. the prefabricated direct-buried heat insulation elbow of the seamless polyethylene of band straight length according to claim 1, it is characterised in that:It is described to protect Warm layer(2)For polyurethane foam.
6. the prefabricated direct-buried heat insulation elbow of the seamless polyethylene of band straight length according to claim 1, it is characterised in that:It is described curved Head(3)For metal material.
7. the prefabricated direct-buried heat insulation elbow of the seamless polyethylene of band straight length according to claim 1 or 6, it is characterised in that:Institute State elbow(3)To be compressing.
8. the prefabricated direct-buried heat insulation elbow of the seamless polyethylene of band straight length according to claim 1, it is characterised in that:It is described straight Pipeline section(32)Length is not less than 400mm.
9. the prefabricated direct-buried heat insulation elbow of the seamless polyethylene of band straight length according to claim 1 or 8, it is characterised in that:Institute State straight length(32)With curved tube section(31)Be formed in one structure.
10. the prefabricated direct-buried heat insulation elbow of the seamless polyethylene of band straight length according to claim 1 or 4, it is characterised in that:Institute State outer shield straight length(12)With outer shield curved tube section(11)Be formed in one structure.
CN201720096982.8U 2017-01-25 2017-01-25 The band prefabricated direct-buried heat insulation elbow of the seamless polyethylene of straight length Active CN206429797U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720096982.8U CN206429797U (en) 2017-01-25 2017-01-25 The band prefabricated direct-buried heat insulation elbow of the seamless polyethylene of straight length

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720096982.8U CN206429797U (en) 2017-01-25 2017-01-25 The band prefabricated direct-buried heat insulation elbow of the seamless polyethylene of straight length

Publications (1)

Publication Number Publication Date
CN206429797U true CN206429797U (en) 2017-08-22

Family

ID=59590504

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720096982.8U Active CN206429797U (en) 2017-01-25 2017-01-25 The band prefabricated direct-buried heat insulation elbow of the seamless polyethylene of straight length

Country Status (1)

Country Link
CN (1) CN206429797U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113883352A (en) * 2018-08-23 2022-01-04 山西理工红日节能服务有限公司 Prefabricated heat preservation double-deck return bend

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113883352A (en) * 2018-08-23 2022-01-04 山西理工红日节能服务有限公司 Prefabricated heat preservation double-deck return bend
CN113883352B (en) * 2018-08-23 2023-11-21 山西理工红日节能服务有限公司 Prefabricated heat-insulating double-layer bent pipe

Similar Documents

Publication Publication Date Title
CN206429797U (en) The band prefabricated direct-buried heat insulation elbow of the seamless polyethylene of straight length
CN206429798U (en) The band prefabricated direct-buried heat-preserving bent pipe of the seamless polyethylene of straight length
CN204554102U (en) HDPE-PP composite winding reinforced pipe
CN208281646U (en) A kind of outer protective polyethylene layer polyurethane foam heat-insulation pipe road
CN206469002U (en) Valve with attemperator
CN210661840U (en) Winding-free, seam-free, waterproof and sun-proof glass fiber prefabricated overhead directly-buried heat-insulation tee joint
CN211875335U (en) 180-degree flanging connecting device for steel lining ultra-high molecular weight polyethylene pipe
CN204213553U (en) Heat preservation pipe prefabricated and pipeline tracing system
CN107131364B (en) Enhanced cushion rubber electric smelting double containment polyethylene composite pipe
CN203880326U (en) Heat preservation pipeline
CN206943664U (en) A kind of Double-metal composite elbow pipe fitting
CN205489409U (en) Modified chlorination polyvinyl chloride cable protection double -ply bellows
CN201159350Y (en) Bi-metal pipe fitting for steel skeleton plastic composite pipe
CN210219019U (en) Prefabricated type heat preservation elbow
CN213576146U (en) Plastic sleeve seamless elbow with good protection effect
CN217177898U (en) Plate-type hot-melt welding joint plugging plug cap for prefabricated direct-buried heat-insulation pipeline system
CN219082593U (en) Steel sleeve of inner and outer steel sleeve heating rings
CN216715873U (en) Jacketed pipe structure capable of preventing thermal stress deformation
CN216307105U (en) Anticorrosive type insulating tube with spiral sheath
CN210600688U (en) PIR composite telescopic cold insulation pipe shell
CN219035922U (en) Novel combined connection device for PSP steel-plastic composite pressure pipe
CN202580423U (en) End metallurgical mechanical double-metal composite T-shaped pipe fitting
CN214699627U (en) Repaired mouth constriction device suitable for prefabricated direct-burried insulating tube
CN216843641U (en) Prefabricated direct-burried electric tracing insulating tube
CN215862364U (en) Double-layer heat-preservation underwater equipment pipeline

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant