CN206428833U - A kind of reinforced concrete member post-cast strip - Google Patents
A kind of reinforced concrete member post-cast strip Download PDFInfo
- Publication number
- CN206428833U CN206428833U CN201621466015.8U CN201621466015U CN206428833U CN 206428833 U CN206428833 U CN 206428833U CN 201621466015 U CN201621466015 U CN 201621466015U CN 206428833 U CN206428833 U CN 206428833U
- Authority
- CN
- China
- Prior art keywords
- post
- reinforced concrete
- cast strip
- concrete member
- protruding bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model provides a kind of reinforced concrete member post-cast strip, belongs to technical field of building construction, for solving the problem of existing post-cast strip bar connecting workload is big.The post-cast strip is located at the temporary construction seam that reinforced concrete member is reserved, the overlap joint connection in opposite directions along its length of the protruding bar at temporary construction seam, and pours ultra-high performance concrete formation post-cast strip.Protruding bar in post-cast strip only needs overlap joint to connect, the protruding bar lap of splice can effectively be shortened, simultaneously, protruding bar transverse lap spacing is also without particular/special requirement, and protruding bar need not be accurately positioned, it is only necessary to mutually be avoided, it is easy to reinforced concrete member pre-formed, so as to significantly save protruding bar connection workload, construction speed is accelerated, difficulty of construction is reduced.
Description
Technical field
The utility model is related to technical field of building construction, more particularly to a kind of reinforced concrete member post-cast strip.
Background technology
After being used as at the temporary construction seam of conventional reinforced concrete member using concrete (non-ultra-high performance concrete)
Pour the connecting material of band.Typically connected in order that obtaining reinforcing bar and giving full play between intensity, armored concrete protruding bar using colligation
Connect (lapped length of steel bar >=25~50d, d is bar diameter, similarly hereinafter), be welded to connect (single-sided welding >=10d, two-sided welding >=
5d) or mechanically connect.If connected using colligation, lapped length of steel bar is longer, causes post-cast strip wider, is unfavorable for reinforcing bar and mixes
Solidifying soil component arrangement, and amount of reinforcement is more;If using being welded to connect or mechanically connecting, connection workload is larger, and such as
When protruding bar arrangement is closeer, possibly effectively it can not be welded to connect or be mechanically connected between the protruding bar of part, be reduced
Bonding strength.
Therefore, how a kind of saving bar connecting workload, accelerating construction progress are provided, and can ensure that armored concrete structure
The reinforced concrete member post-cast strip of part total quality, is the technical problem of those skilled in the art's urgent need to resolve.
Utility model content
Workload is big for protruding bar connection present in the connection of current reinforced concrete member post-cast strip, speed slowly very
In the case of can not carrying out effectively connection to part reinforced concrete member protruding bar, the present invention provide it is a kind of it is convenient, fast,
Reliable connection method, significantly to save bar connecting workload, accelerating construction progress, while also ensuring that reinforced concrete member
Between connection it is safe and reliable.
The utility model solves the technical scheme that its technical problem used:
A kind of reinforced concrete member post-cast strip, the reinforced concrete member is poured into a mould by normal concrete and protruding bar
Protruding bar in shaping, and reserved temporary construction seam, reinforced concrete member at the temporary construction seam along its length
Opposite overlap joint connection, mutually two protruding bars of overlap joint connection are staggered settings along perpendicular to length direction, and the post-cast strip is wrapped
Include the protruding bar and ultra-high performance concrete and the integrative-structure to be formed, the post-cast strip are poured at the temporary construction seam
The reinforced concrete member is linked to be overall structure.
Further, the lap of splice of the protruding bar in the reinforced concrete member each other is 6d~12d, d
For bar diameter.
Further, the ultra-high performance concrete is ultra high performance cementitious, its compressive strength standard value
≥120mpa。
Further, the connection between the post-cast strip self-strength and the post-cast strip and reinforced concrete member is strong
Degree is not less than the intensity of reinforced concrete member.
Further, the profile of the protruding bar is linear pattern, linear belt hook type or annular.
Compared with prior art, the beneficial effects of the utility model are:
Reinforced concrete member post-cast strip of the present utility model is located at the temporary construction seam that reinforced concrete member is reserved,
Protruding bar overlap joint connection in opposite directions along its length at temporary construction seam, two protruding bars overlapped in opposite directions need not
Colligation, welding are mechanically connected, and pouring ultra-high performance concrete at temporary construction seam in subsequent handling forms post-cast strip.
Because the protruding bar in post-cast strip only needs overlap joint to connect, without colligation, welding or mechanical connection, ultra-high performance concrete
Stronger bond stress is formed between protruding bar to transmit protruding bar stress, can effectively shorten protruding bar overlap joint length
Degree, meanwhile, protruding bar transverse lap spacing is also without particular/special requirement, and protruding bar need not be accurately positioned, it is only necessary to mutually be kept away
Open, be easy to reinforced concrete member pre-formed, so as to significantly save protruding bar connection workload, accelerate construction
Progress, reduces difficulty of construction.Moreover, the concrete for pouring post-cast strip is ultra-high performance concrete so that post-cast strip is certainly
Bonding strength between body intensity and post-cast strip and reinforced concrete member is not less than the intensity of armored concrete, post-cast strip knot
Structure bearing capacity, rigidity, cracking resistance and anti-fatigue performance are preferable, it is ensured that the overall quality of reinforced concrete member.
Brief description of the drawings
Fig. 1 is the elevation of the reinforced concrete member post-cast strip of the embodiment of the utility model one;
Fig. 2 is the plan of the reinforced concrete member post-cast strip of the embodiment of the utility model one.
In figure:11- reinforced concrete members;12- normal concretes;13- protruding bars;21- ultra-high performance concretes.
Embodiment
Below in conjunction with the drawings and specific embodiments to the utility model proposes a kind of reinforced concrete member post-cast strip work
It is further described.According to following explanation, advantages and features of the present utility model will become apparent from.Below will by it is cited it
Embodiment combination accompanying drawing, describes technology contents of the present utility model and feature in detail.It need to illustrate in addition, accompanying drawing is using non-
Often simplified form and use non-accurately ratio, only to it is convenient, lucidly aid in illustrating the utility model embodiment
Purpose.For sake of convenience, described below " on ", " under " the upper and lower direction with accompanying drawing is consistent, but this can not turn into this reality
With the limitation of new technique scheme.
Describe the structure composition of reinforced concrete member post-cast strip of the present utility model in detail with reference to Fig. 1 and Fig. 2.
As depicted in figs. 1 and 2, reinforced concrete member 11 is by normal concrete 12 and the moulding by casting of protruding bar 13, and
Reserved temporary construction seam (not shown), post-cast strip is arranged at temporary construction seam, the protruding bar in reinforced concrete member 11
The 13 overlap joint connections in opposite directions along its length at temporary construction seam, mutually two protruding bars 13 of overlap joint connection are along perpendicular to length
Stagger setting in degree direction.That is, two protruding bars 13 that the overlap joint connection of both sides is stitched positioned at temporary construction are applied temporarily
Stagger setting along perpendicular to length direction at work seam, the two is not contacted directly.Post-cast strip includes protruding bar 13 and superelevation
Energy concrete 21 pours the integrative-structure to be formed at temporary construction seam, and reinforced concrete member 11 is linked to be overall knot by post-cast strip
Structure.
Specifically, reinforced concrete member post-cast strip of the present utility model is positioned at facing that reinforced concrete member 11 is reserved
When construction joint at, the opposite overlap joint connection, and the length of overlap joint along its length of protruding bar 13 at temporary construction seam
Shorter, two protruding bars 13 overlapped in opposite directions do not need colligation, welding or mechanically connected, in temporary construction in subsequent handling
Ultra-high performance concrete 21 is poured at seam and forms post-cast strip.Because the protruding bar 13 in post-cast strip only needs overlap joint to connect, and
Without colligation, welding or mechanical connection, stronger bond stress is formed between ultra-high performance concrete 21 and protruding bar 13
The stress of protruding bar 13 is transmitted, can effectively shorten the lap of splice of protruding bar 13, meanwhile, the transverse lap spacing of protruding bar 13
Also without particular/special requirement, protruding bar 13 need not be accurately positioned, it is only necessary to mutually be avoided, and be easy to reinforced concrete member 11
It is pre-formed, so as to significantly save the connection workload of protruding bar 13, construction speed is accelerated, difficulty of construction is reduced.And
And, the concrete for pouring post-cast strip is ultra-high performance concrete 21 so that post-cast strip self-strength and post-cast strip and steel
Bonding strength between reinforced concrete component 11 is not less than the intensity of armored concrete 11, late poured band structure bearing capacity, rigidity, anti-
Fragility energy and anti-fatigue performance are preferable, it is ensured that the overall quality of reinforced concrete member 11.
It is preferred that the lap of splice of protruding bar 13 each other in reinforced concrete member 11 is 6d~12d, (d is
Bar diameter, similarly hereinafter).It is connected, lapped length of steel bar >=25~50d and is welded to connect with conventional colligation, single-sided welding >=
10d, two-sided welding >=5d is compared, and saves a large amount of reinforcing bars.Moreover, saving the connection workload of protruding bar 13.
Certainly, the ultra-high performance concrete for pouring post-cast strip is ultra high performance cementitious, with high-strength
The characteristics such as degree, high tenacity, high-durability, its compressive strength standard value >=120mpa, hold so as to meet the intensity of post-cast strip, structure
Carry the requirement of power, rigidity, cracking resistance and anti-fatigue performance.
It is preferred that due to pouring post-cast strip using ultra-high performance concrete 21, so that post-cast strip self-strength and described
Bonding strength between post-cast strip and reinforced concrete member is not less than the intensity of reinforced concrete member so that post-cast strip has
Standby preferable structural bearing capacity, rigidity, cracking resistance and anti-fatigue performance, it can be ensured that the quality of post-cast strip meets specification will
Ask.
It is preferred that the profile of protruding bar 13 is not limited, the profile of the protruding bar 13 can be linear pattern, linear belt crotch
Type or annular.So as to reduce further the workload of the connection of protruding bar 13, difficulty of construction is reduced.
Please continue to refer to Fig. 1 and Fig. 2, the present embodiment is poured after also disclosing a kind of reinforced concrete member of the present utility model
The construction method of band, comprises the following steps:
Step one:By normal concrete 12 and the moulding by casting of protruding bar 13, reinforced concrete member 11 is formed, and reserve
Temporary construction is stitched so that the protruding bar 13 of reinforced concrete member 11 overlaps a fixed length along its length at temporary construction seam
Degree, because the concrete for being used to pour post-cast strip in subsequent construction process is at ultra-high performance concrete 21, temporary construction seam
The certain length that protruding bar 13 is overlapped is 6d~12d, and d is bar diameter.
Step 2:Reinforced concrete member 11 in installation steps one, is stitched in the temporary construction of reinforced concrete member 11
Place sets pouring template ultra-high performance concrete 21 to form reinforced concrete member post-cast strip, and causes post-cast strip and post-cast strip
Bonding strength between reinforced concrete member 11 is not less than the intensity of reinforced concrete member.
In summary, reinforced concrete member post-cast strip of the present utility model is positioned at facing that reinforced concrete member 11 is reserved
When construction joint at, the opposite overlap joint connection, two overlapped in opposite directions along its length of protruding bar 13 at temporary construction seam
Protruding bar 13 does not need colligation, welding or mechanically connected, and pours very-high performance in subsequent handling at temporary construction seam and mixes
Solidifying soil 21 forms post-cast strip.Because the protruding bar 13 in post-cast strip only needs overlap joint to connect, without colligation, welding or machine
Tool is connected, and forms stronger bond stress between ultra-high performance concrete 21 and protruding bar 13 to transmit the stress of protruding bar 13,
The lap of splice of protruding bar 13 can effectively be shortened, meanwhile, the transverse lap spacing of protruding bar 13 is also without particular/special requirement, overhanging steel
Muscle 13 need not be accurately positioned, it is only necessary to mutually be avoided, and be easy to reinforced concrete member 11 pre-formed, so as to significantly save
The connection workload of protruding bar 13 has been saved, construction speed has been accelerated, reduces difficulty of construction.Moreover, for pouring post-cast strip
Concrete is ultra-high performance concrete 21 so that between post-cast strip self-strength and post-cast strip and reinforced concrete member 11
Bonding strength is not less than the intensity of armored concrete 11, late poured band structure bearing capacity, rigidity, cracking resistance and anti-fatigue performance
Preferably, it is ensured that the overall quality of reinforced concrete member 11.Reinforced concrete member post empiricism side of the present utility model
Method, pours to form reinforced concrete member using normal concrete 12 and protruding bar 13 first, while reserved temporary construction seam,
The laterally opposite overlap joint connection of protruding bar 13 at temporary construction seam;Then ultra-high performance concrete is poured at temporary construction seam
21 form post-cast strip, and reinforced concrete member 11 is linked to be overall structure by the post-cast strip.The construction method is simple to operate, construction effect
Rate is high, the quality of post-cast strip is ensure that, with preferably promotional value.
Foregoing description is only the description to the utility model preferred embodiment, not to any limit of the utility model scope
Calmly, the those of ordinary skill in the utility model field does according to the disclosure above content any change, modification, belonging to right will
Seek the protection domain of book.
Claims (5)
1. a kind of reinforced concrete member post-cast strip, the reinforced concrete member is poured into by normal concrete and protruding bar
Type, and reserved temporary construction seam, it is characterised in that protruding bar in the reinforced concrete member edge at the temporary construction seam
Length direction overlaps connection in opposite directions, and two protruding bars of mutually overlap joint connection stagger setting along perpendicular to length direction, described
Post-cast strip includes the protruding bar and ultra-high performance concrete pours the integrative-structure to be formed, institute at the temporary construction seam
State post-cast strip and the reinforced concrete member is linked to be overall structure.
2. reinforced concrete member post-cast strip according to claim 1, it is characterised in that in the reinforced concrete member
The protruding bar lap of splice each other be 6d~12d, d is bar diameter.
3. reinforced concrete member post-cast strip according to claim 1, it is characterised in that the ultra-high performance concrete is
Ultra high performance cementitious, its compressive strength standard value >=120mpa.
4. reinforced concrete member post-cast strip according to claim 1, it is characterised in that the post-cast strip self-strength with
And the bonding strength between the post-cast strip and reinforced concrete member is not less than the intensity of reinforced concrete member.
5. reinforced concrete member post-cast strip according to claim 1, it is characterised in that the profile of the protruding bar is
Linear pattern, linear belt hook type or annular.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621466015.8U CN206428833U (en) | 2016-12-29 | 2016-12-29 | A kind of reinforced concrete member post-cast strip |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621466015.8U CN206428833U (en) | 2016-12-29 | 2016-12-29 | A kind of reinforced concrete member post-cast strip |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206428833U true CN206428833U (en) | 2017-08-22 |
Family
ID=59585826
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621466015.8U Active CN206428833U (en) | 2016-12-29 | 2016-12-29 | A kind of reinforced concrete member post-cast strip |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206428833U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106639003A (en) * | 2016-12-29 | 2017-05-10 | 上海市政工程设计研究总院(集团)有限公司 | Reinforced concrete member post-cast strip and construction method of same |
CN108374523A (en) * | 2018-02-05 | 2018-08-07 | 范砥 | A kind of Bar Anchorage structure and Bar Anchorage method |
-
2016
- 2016-12-29 CN CN201621466015.8U patent/CN206428833U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106639003A (en) * | 2016-12-29 | 2017-05-10 | 上海市政工程设计研究总院(集团)有限公司 | Reinforced concrete member post-cast strip and construction method of same |
CN108374523A (en) * | 2018-02-05 | 2018-08-07 | 范砥 | A kind of Bar Anchorage structure and Bar Anchorage method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204112604U (en) | The slip casting rebar connector of band cone tail | |
CN105569224B (en) | Concrete filled steel tube edge constraint overlaps monoblock type shear wall and preparation and installation method | |
CN203113627U (en) | Nodular cast iron grout sleeve for connecting longitudinal steel bars | |
CN108035439A (en) | A kind of rapid coagulation soil assembling type node and its construction method | |
CN206428833U (en) | A kind of reinforced concrete member post-cast strip | |
CN108130856B (en) | Using the bridge superstructure seam of the single layer steel bar arrangement of UHPC grouting material | |
CN108166652A (en) | The two-sided overlapped shear wall and its construction method of band connection lacing wire | |
CN106760054A (en) | Precast reinforced concrete shear wall | |
CN102926504A (en) | Connecting steel construction member for steel and concrete overlapped beam combined part and construction method thereof | |
CN108999076A (en) | A kind of the class socket joint connection structure and its construction method of column and adjacent members | |
CN108316466A (en) | A kind of prefabricated window member that floats, assembled float window joint structure and its construction method | |
CN203729498U (en) | Vertical reinforcement-steel sleeve but joint connection structure of assembled wall | |
CN109339281A (en) | A kind of prefabricated assembling type reinforced concrete shear wall vertically splices node structure and its construction method | |
CN106639003A (en) | Reinforced concrete member post-cast strip and construction method of same | |
CN106121085B (en) | Assembled integral concrete shear force wall splicing structure and its assembling method | |
CN205444169U (en) | Variable cross section reinforced concrete precast pile of X -shaped cross -section and square cross -section combination | |
CN209040349U (en) | A kind of ring muscle fastening shear wall structure being easily installed | |
CN106930436A (en) | A kind of reinforced concrete shear wall of built-in prestress steel diagonal brace | |
CN108748648B (en) | A kind of elongated prestressed pore passage positioning device in the prefabricated longitudinal direction of short line casting box girder segment and construction method | |
CN206554247U (en) | Precast floor slab and prefabricated panel attachment structure and building | |
CN103541443B (en) | Post-cast strip structure and construction method thereof | |
CN209703838U (en) | Steel bar connecting structure between reinforcing bar connector and precast concrete | |
CN204456670U (en) | Fabricated construction straight screw sleeve connection joint | |
CN207228355U (en) | A kind of assembling steel plate Combined concrete wall and steel bar truss floor support plate connecting structure | |
CN206418775U (en) | A kind of arm support and concrete spraying machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |