CN206376372U - The horizontal paving docking node apparatus of industrial premises composite plate - Google Patents
The horizontal paving docking node apparatus of industrial premises composite plate Download PDFInfo
- Publication number
- CN206376372U CN206376372U CN201621352643.3U CN201621352643U CN206376372U CN 206376372 U CN206376372 U CN 206376372U CN 201621352643 U CN201621352643 U CN 201621352643U CN 206376372 U CN206376372 U CN 206376372U
- Authority
- CN
- China
- Prior art keywords
- waterproof
- received
- wall board
- combined wall
- receipts
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Finishing Walls (AREA)
Abstract
The utility model is related to the horizontal paving docking facilities of the steel building Side fascia of environmental protection, more particularly to the horizontal paving docking node apparatus of industrial premises composite plate and installation method, and current node, which is primarily present problem, to be had:Water proofing property is bad, is unfavorable for wall protection against the tide, anti-corrosion;Side accessory not up to standardization is received, the loss and waste of material is caused;Primary fastener is exposed, easily gets rusty or is corroded;Node is unsightly etc..The utility model is received side by combined wall board, wall beam and waterproof and constituted, inner waterproofing is welded on wall beam and receives side, outside is installed by the combined wall board of docking point, leave receipts side groove in centre, when receipts are installed outer waterproof in groove and received, outer waterproof is received to be fixed on wall beam in the middle part of side, and both sides are fixed on combined wall board with pulling rivet, sealing clay is scribbled between combined wall board and outer waterproof receive side, the lid when outer waterproof is received and there are waterproof receipts in the middle part of.The utility model technology is compared with prior art:Node service life is long, accessory standardization, loss is reduced, with good economic and practical.
Description
Technical field:
The present invention relates to the horizontal paving docking facilities of the steel building Side fascia of environmental protection, more particularly to industrial premises are multiple
The horizontal paving docking node apparatus of plywood.
Background technology:
Coloured silk steel transverse bed board is applied than wide, structural steel industrial building wall surface composite board in Modern Steel Structure factory building at present
During horizontal paving there is following unreasonable defect in joint node.
1st, node unsightly, causes metope integral smoothness effect not comply with one's wishes.
2nd, under outdoor conditions, difference variation is big, and the easy aging of fluid sealant, rainwater penetrates into wall along the receipts side at abutment joint
Body, is unfavorable for wall protection against the tide, anti-corrosion.
3rd, side accessory not up to standardization is received, the loss and waste of material is caused.
4th, the main part that tightly returns is exposed, easily gets rusty or is corroded, cause metope to come off, maintenance cost is high.
The content of the invention:
In order to solve the above technical problems, it is an object of the invention to provide a kind of horizontal paving docking node of industrial premises composite plate
Device, makes the horizontal paving of composite plate metope of industrial premises reach waterproof, safety, economy, service-strong requirement to taking over control.
In order to solve the above technical problems, the technical scheme that the present invention is provided is, the horizontal paving docking node of industrial premises composite plate
Device, receives side by combined wall board, wall beam and waterproof and constitutes, it is characterised in that side is received in welding or mode connects for screw inner waterproofing on wall beam,
The combined wall board of docking point is installed in outside, is separately fixed at using the tapping screw with water proof ring on wall beam, and receipts side is left in centre
Groove, when receiving the waterproof receipts outer with tapping screw installation in groove, outer waterproof is received to be fixed on wall beam in the middle part of side, and both sides covered solid
Determine the tapping screw of combined wall board, and be fixed on pulling rivet on combined wall board, applied between combined wall board and outer waterproof receive side
There is sealing clay, the lid when outer waterproof is received and there are waterproof receipts in the middle part of.The technology of the present invention is compared with prior art:By original wall
Improved in face of receiving side, while reducing the length on monolithic receipts side, also cover all fasteners, make node service life
It is long, it can also accomplish that accessory is standardized to greatest extent, reduce the loss of material, it is to avoid waste, with good economy in fact
The property used.
Inner waterproofing receives side and is characterised by that there is a folding surface both sides, and bending angle a is that 140 ° -160 ° middle parts have a U-shaped convex
Rise.Bending and and projection all make its flexible, fitted with composite wall closer.
Outer waterproof receives side and is characterised by that middle part, which has on a U-shaped groove, U-shaped groove two side, curved arc, and afterbody two ends are each
It is curved once.U-shaped groove makes that outer waterproof receives side and the mounting distance of wall beam shortens, and increase its it is elastic while formed and install
The benefit of the cavity back bending of lid is the bond area of waterproof and increase waterproof clay.Curved arc is used for and the curved arc shape on lid
Into gripping mechanism.
Installation method has the following steps:
A. inner waterproofing receipts side is welded on wall beam, forms inner waterproofing;
B., combined wall board is installed, the docking point of two pieces of combined wall boards is separately mounted to using the tapping screw with water proof ring
On wall beam, centre, which is reserved, installs the position that outer waterproof receives side;
C. uniform smearing waterproof clay in the back bending on side is received in outer waterproof, good position is determined, to cover installation combined wall board
Tapping screw, then self tapping spiral shell in centre, which is beaten, is fixed on wall beam, and both sides are fixed on compound temple plate with pulling rivet;
D. buckle waterproof and receive side lid, complete to install.
Install simple, firmly, water resistance is good, and metope integral smoothness is attractive in appearance.
Brief description of the drawings:
Fig. 1 is the horizontal paving docking node apparatus scheme of installation of industrial premises composite plate of the present invention;
Fig. 2 is that the horizontal outer waterproof of paving docking node apparatus of industrial premises composite plate of the present invention receives side enlarged section;
Fig. 3 is that the horizontal paving docking node apparatus waterproof of industrial premises composite plate of the present invention receives side lid enlarged section;
Fig. 4 is that side enlarged section is received in the horizontal paving docking node apparatus inner waterproofing of industrial premises composite plate of the present invention.
Embodiment
Referring to the drawings 1 --- accompanying drawing 4 is visible, the horizontal paving docking node apparatus of industrial premises composite plate, by combined wall board 1, wall
Beam 2 and waterproof receive welding or mode connects for screw inner waterproofing on side composition, wall beam 2 and receive side 3, and the combined wall board 1 of docking point is installed in outside,
It is separately fixed at using the tapping screw 4 with water proof ring on wall beam 2, receipts side groove is left in centre, and tapping screw 4 is used in the groove of side receiving
Outer waterproof is installed and receives side 5, outer waterproof is received the middle part of side 5 and is fixed on wall beam 2, and both sides covered the self tapping spiral shell of fixed combined wall board 1
Nail 4, and be fixed on pulling rivet 12 on combined wall board 1, sealing clay 6 is scribbled between combined wall board 1 and outer waterproof receive side 5,
The lid 7 when 5 middle parts there are waterproof receipts is received in outer waterproof.The technology of the present invention is compared with prior art:By original metope to receiving
Side is improved, and while reducing monolithic and receive the length on side, is also covered all fasteners, is made node service life long, can be with
Accomplish that accessory is standardized to greatest extent, reduce the loss of material, it is to avoid waste, with good economic and practical.
Side 3 is received in inner waterproofing folding surface 8, and bending angle a is that 140 ° -160 ° middle parts have a U-shaped projection 9.Bending and with it is convex
Rising all makes its flexible, is fitted with combined wall board 1 closer.
The middle part on outer waterproof receipts side 5, which has on a U-shaped groove 10, the two side of U-shaped groove 10, curved arc 11, and afterbody two ends respectively have
One back bending 13.U-shaped groove 10 makes that outer waterproof receives side 5 and the mounting distance of wall beam 2 shortens, and increase its it is elastic while formed
The benefit for installing the cavity back bending 13 of lid is the bond area of waterproof and increase waterproof clay.Curved arc 11 is used for receiving with waterproof
While the formation gripping mechanism of curved arc 11 covered.
Installation method is characterised by:Have the following steps:
A. inner waterproofing receipts side 3 is welded on wall beam 2, forms inner waterproofing;
B., combined wall board 1 is installed, pacified the docking point of two pieces of combined wall boards 1 respectively using the tapping screw 4 with water proof ring
On wall beam 2, centre, which is reserved, installs the position that outer waterproof receives side 5;
C. uniform smearing sealing clay 6 in the back bending 13 on side 5 is received in outer waterproof, good position is determined, to cover installation compound
The tapping screw 4 of wallboard 1, then centre tapping screw 4 be fixed on wall beam 2, both sides pulling rivet 12 is fixed on composite wall
On plate 1;
D. buckle waterproof and receive side lid 7, complete to install.
Install simple, firmly, water resistance is good, and metope integral smoothness is attractive in appearance.
Claims (3)
1. a kind of horizontal paving docking node apparatus of industrial premises composite plate, receives side by combined wall board, wall beam and waterproof and constitutes, its feature
It is, side is received in welding or mode connects for screw inner waterproofing on wall beam, and the combined wall board of docking point is installed in outside, and receipts side groove is left in centre,
When receiving the waterproof receipts outer with tapping screw installation in groove, outer waterproof is received to be fixed on wall beam in the middle part of side, and both sides covered fixed
The tapping screw of combined wall board, and be fixed on pulling rivet on combined wall board, scribbled between combined wall board and outer waterproof receive side
Sealing clay, the lid when outer waterproof is received and has waterproof receipts in the middle part of.
2. a kind of horizontal paving docking node apparatus of industrial premises composite plate according to claim 1, it is characterised in that inner waterproofing
Receiving side both sides has a folding surface, and bending angle a is that 140 ° -160 ° middle parts have a U-shaped raised.
3. a kind of horizontal paving docking node apparatus of industrial premises composite plate according to claim 1, it is characterised in that outer waterproof
Receive to have in the middle part of side and have curved arc on a U-shaped groove, U-shaped groove two side, afterbody two ends are each curved once.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621352643.3U CN206376372U (en) | 2016-12-12 | 2016-12-12 | The horizontal paving docking node apparatus of industrial premises composite plate |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621352643.3U CN206376372U (en) | 2016-12-12 | 2016-12-12 | The horizontal paving docking node apparatus of industrial premises composite plate |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206376372U true CN206376372U (en) | 2017-08-04 |
Family
ID=59405410
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621352643.3U Expired - Fee Related CN206376372U (en) | 2016-12-12 | 2016-12-12 | The horizontal paving docking node apparatus of industrial premises composite plate |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206376372U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106759931A (en) * | 2016-12-12 | 2017-05-31 | 湖南金海钢结构股份有限公司 | Industrial premises composite plate horizontal paving docking node apparatus and installation method |
-
2016
- 2016-12-12 CN CN201621352643.3U patent/CN206376372U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106759931A (en) * | 2016-12-12 | 2017-05-31 | 湖南金海钢结构股份有限公司 | Industrial premises composite plate horizontal paving docking node apparatus and installation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106930413B (en) | Buckling structure of aluminum alloy wallboard, roof panel and corner connecting material | |
CN106759931A (en) | Industrial premises composite plate horizontal paving docking node apparatus and installation method | |
CN206376372U (en) | The horizontal paving docking node apparatus of industrial premises composite plate | |
CN204827148U (en) | Steel construction colored steel is bordured | |
CN207092302U (en) | A kind of water-proof metal curtain wall | |
CN212129699U (en) | Waterproof construction of various steel house roofing and parapet | |
CN205063202U (en) | Be located eave decorative board on outer wall | |
CN103422625A (en) | Unit extensible type assembled metal gutter and manufacturing and installing method thereof | |
CN102220792B (en) | Metal curtain wall assembling device | |
CN104594569A (en) | Device for increasing wind-resistant performance of metal roof and mounting method thereof | |
CN202090526U (en) | Rigid waterproof assembling unit for top of parapet wall | |
CN202073241U (en) | Connecting piece of metallic roofing daylighting board | |
CN210564051U (en) | Anti-leakage device for closing profile of system door and window | |
CN213143444U (en) | Deformation joint construction structure for indoor and outdoor walls | |
CN205077748U (en) | There is parapet post gable node construction system | |
CN204531194U (en) | A kind of device improving metal Roof wind resistance | |
CN209958530U (en) | Vertical receipts limit seam waterproof node of horizontal board of steel construction | |
CN102587570A (en) | Wall space contour plate and connecting member thereof | |
CN209163078U (en) | The connection structure of aluminium veneer curtain wall and exterior wall | |
CN208456276U (en) | Steel can have enough to meet the need enclosure wall | |
JP5319202B2 (en) | Mounting structure | |
CN219586935U (en) | Connection structure of integral bathroom roof and wallboard | |
CN217268414U (en) | Roof and ventilator link up and use waterproof end cap | |
CN204551915U (en) | A kind of metal roofing board fastening structure | |
CN213897824U (en) | Photovoltaic is with general waterproof baffle of various steel tile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address |
Address after: 411100 Jinhai Road, Jiuhua demonstration area, Xiangtan, Hunan 1 Patentee after: HUNAN JINHAI STEEL STRUCTURE CO.,LTD. Address before: 410000 Jinhai Road, Jiuhua demonstration area, Yuhu District, Xiangtan, Hunan, 1 Patentee before: HUNAN JINHAI STEEL STRUCTURE Co.,Ltd. |
|
CP03 | Change of name, title or address | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170804 Termination date: 20211212 |
|
CF01 | Termination of patent right due to non-payment of annual fee |