CN206359928U - Concave herbaceous field structure applied to road machine non-isolated band - Google Patents

Concave herbaceous field structure applied to road machine non-isolated band Download PDF

Info

Publication number
CN206359928U
CN206359928U CN201621473599.1U CN201621473599U CN206359928U CN 206359928 U CN206359928 U CN 206359928U CN 201621473599 U CN201621473599 U CN 201621473599U CN 206359928 U CN206359928 U CN 206359928U
Authority
CN
China
Prior art keywords
section
machine non
concave
field structure
herbaceous field
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621473599.1U
Other languages
Chinese (zh)
Inventor
黄剑
梁捷
韩忠
张鹏
翟袁桢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Rhyme Water Engineering Design Co Ltd
SHANGHAI HONGBO PROJECT MANAGEMENT Co Ltd
Original Assignee
Shanghai Rhyme Water Engineering Design Co Ltd
SHANGHAI HONGBO PROJECT MANAGEMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Rhyme Water Engineering Design Co Ltd, SHANGHAI HONGBO PROJECT MANAGEMENT Co Ltd filed Critical Shanghai Rhyme Water Engineering Design Co Ltd
Priority to CN201621473599.1U priority Critical patent/CN206359928U/en
Application granted granted Critical
Publication of CN206359928U publication Critical patent/CN206359928U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model is related to a kind of concave herbaceous field structure applied to road machine non-isolated band;The linkage section that dirty section, middle lower concave segment and connection cut dirty section and lower concave segment is cut including both sides;Described section of dirty section is provided close to machine non-isolated band curb side, in a concave shape, from the bottom to top provided with infiltration coefficient≤1 × 10‑6M/s fill stratum and resistant vegetable layer, during rainfall, silt that its groove structure having can carry pavement runoff, impurity retention, so as to cut down pollution of area source;Cutting the intensive plantation shrub of linkage section of dirty section and lower concave segment, rubbish and the suspension of floating that closely knit limb can be in effectively catching road runoff.The high Initial Runoff of concave herbaceous field effectively catching pollutional load that the utility model is related to, enhances retaining power of the machine non-isolated with greenery patches;It can further purify simultaneously, infiltrate the relatively low rainfall runoff of pollution concentration, so as to alleviate Urban Rainwater Runoff Pollution, mitigating the load of Storm Sewer Network, meet the theory of sponge urban construction.

Description

Concave herbaceous field structure applied to road machine non-isolated band
Technical field
The utility model is related to field of environment engineering, more particularly to a kind of up concave type applied to road machine non-isolated band is green Ground structure.
Background technology
Traditional city development pattern causes the black smelly outstanding problem of urban water-body.During rainfall, it is a large amount of that Initial Runoff is carried Pavement garbage is unprocessed and quickly flows into city river.And curb gets up greenery patches corral in machine non-isolated band so that Road runoff can not be flowed into wherein, it is impossible to the reduction polluted using greenery patches in machine non-isolated band to Initial Runoff, to runoff volume The effect such as control.
With the implementation of sponge urban construction pattern theory, the application of open type curb is more and more wider, in machine non-isolated band Cut down Initial Runoff pollution, the function of control runoff volume and be fully utilized in greenery patches.But due to domestic city appearance of the city environmental sanitation environment It is not good enough, cause rainfall first flush effects substantially, the road runoff pollutional load at rainfall initial stage is larger, and carried in Initial Runoff Substantial amounts of rubbish.If Initial Runoff is without intercepting, the greenery patches of machine non-isolated band is entered by curb opening, it is non-by machine is directly affected The growth of isolation strip implants, brings poor city appearance environment, and increase the difficulty and cost of greening maintenance.
Utility model content
The purpose of the present utility model is that overcoming the shortcomings of that above-mentioned prior art exists to have there is provided one kind alleviates city City's early-stage rainwater runoff pollution and the concave herbaceous field structure applied to road machine non-isolated band for cutting dirty purification function.This practicality New combination curb opening, by the concave herbaceous field structure of special shape, by the footpath at initial stage of pollution concentration height, carrying silt Stream progress is dammed storage, and the suspension floated in Initial Runoff and rubbish are dammed, it is to avoid pollution concentration high initial stage Runoff enters in machine non-isolated band and influences city appearance environment, increases the difficulty and cost of greening maintenance.
To achieve these goals, the technical solution of the utility model is as follows:
The utility model is related to a kind of concave herbaceous field structure applied to road machine non-isolated band, the concave herbaceous field Structure includes the linkage section that dirty section, middle lower concave segment and connection cut dirty section and lower concave segment that cuts of both sides;Described section of dirty section is set In close to machine non-isolated band curb side, described section of dirty section is in a concave shape.
It is preferred that, described section of dirty section is 5cm~10cm relative to the recessed depth of road plane;One side is cut dirty section width and accounted for Machine non-isolated with bandwidth 15%~20%.
It is preferred that, described section of dirty section is provided with fill stratum and resistant vegetable layer from the bottom to top;The infiltration coefficient of the fill stratum ≤1×10-6m/s.Cut dirty section and be supplied to the certain hydraulic detention time of rainwater so that suspended particulate substance is able to be settled down to and cut in water Dirty section bottom, and retained by filler surface.
It is preferred that, described section of dirty section and the inwall of curb 2 are closely coupled.
It is preferred that, the peak of described section of dirty section is flushed with the lower end of curb opening.The curb is open type road Along stone.
It is preferred that, the curb is open type curb, and opening lowest point absolute altitude cuts dirty section peak higher than described Absolute altitude.
It is preferred that, the concave herbaceous field structure setting is in the both sides of the road with certain design grade.
It is preferred that, the lower concave segment width accounts for 60%~70% of machine non-isolated with bandwidth;The lower concave segment minimum point is low In a section dirty section minimum point.
It is preferred that, relative to road plane, the recessed depth of the lower concave segment is 150mm~250mm.
It is preferred that, the lower concave segment is from the bottom to top provided with gravel layer, layer of sand, plantation soil layer and coating.
It is preferred that, one stormwater overflow mouthful is set every 10~15m on the lower concave segment center line, the stormwater overflow mouthful with Subsurface stormwater pipeline is connected.
It is preferred that, intensive kind is implanted with single file hedgerow on the linkage section, and plant height is higher than 30cm.
Compared with prior art, the utility model has the advantages that:
Recessed greenery patches structure of the present utility model is using the sand setting effect for cutting dirty section, for the mud carried in Initial Runoff Husky, impurity is retained;Simultaneously by the single file shrub zone closely planted in connect band, intercept the rubbish floated in runoff and hang Float;The plant for the recessed greenery patches main part that adequately protects, has ensured the Runoff for entering recessed machine non-isolated band;Cut Impurity, the pollutant stayed is easily cleared up, under the theory for meeting sponge urban construction, it is ensured that city appearance environment is unaffected.
Brief description of the drawings
By reading the detailed description made with reference to the following drawings to non-limiting example, other spies of the present utility model Levy, objects and advantages will become more apparent upon:
Fig. 1 is the floor plan of the recessed greenery patches structure of the utility model;
Fig. 2 is the structural representation in the recessed greenery patches of the utility model;
Wherein, 1 is cuts dirty section, and 2 be curb, and 3 be shrub, and 4 be stormwater overflow mouthful, and 5 be plantation soil layer, and 6 be coating, 7 be gravel layer, and 8 be layer of sand, and 9 be curb osculum, and 10 be road, and 11 be pavement, and 12 be linkage section, and 13 be lower concave segment.
Embodiment
The utility model is described in detail with reference to embodiment.Following examples will be helpful to the technology of this area Personnel further understand the utility model, but do not limit the utility model in any form.It should be pointed out that to this area For those of ordinary skill, without departing from the concept of the premise utility, it can also make certain adjustments and improvements.These Belong to protection domain of the present utility model.
Embodiment
The present embodiment is related to a kind of concave herbaceous field structure applied to both sides of the road machine non-isolated band.As shown in figure 1, flat Face figure is from top to bottom followed successively by car lane, machine non-isolated band and bicycle lane.As shown in Fig. 2 concave herbaceous field structure is set On machine non-isolated band between road 10 and pavement 11, include section dirty section 1, a lower concave segment 13 and the company of the two of both sides Connect section 12.Wherein cut dirty section 1 and be disposed in proximity to the side of curb 2, and it is closely coupled with the inwall of curb 2;Cut under dirty section 1 is in Concavity, recessed depth is 5cm~10cm with respect to the plane of road 10;Dirty section 1 is cut by poor (infiltration coefficient≤1 × 10 of water permeable ability-6m/ S) backfill is tamped, and whole segment length is unilateral wide to ensure that the runoff into machine non-isolated band is cutting the minimum of the dirty seepage flow of section 1 Degree accounts for 15%~20% of integrated machine non-isolated with bandwidth;Cut the strong vegetation of durability against pollution such as dirty a kind of plant greens grass of section;Cut dirty section The lower end that 1 peak should be open with curb 2 is flushed, and the pollution concentration that effectively can be flowed into curb osculum 9 is high, carry The Initial Runoff of silt carries out precipitation of damming.
The intensive kind of linkage section 12 of described section of dirty section 1 and lower concave segment 13 is implanted with single file hedgerow, based on shrub 3.In runoff The larger solid pollutant of volume (rubbish and suspension of floating) can effectively be intercepted by the distinctive tight structure of hedgerow limb.It is logical Cross and cut dirty section 1 and the R. concomitans of hedgerow, the silt, the rubbish of floating and suspension during rainfall entrained by Initial Runoff are cut Stay, it is ensured that enter the basic water quality of the lower runoff of concave segment 13, and ensured the normal growth of the lower vegetation of concave segment 13, it is to avoid rubbish enters Enter the lower concave segment 13 of machine non-isolated band and influence city appearance environment, increase the difficulty and cost of greening maintenance.
Lower concave segment 13 be located at recessed machine non-isolated band centre position, width account for machine non-isolated with bandwidth 60%~ 70%, it is the main part of concave herbaceous field structure, is that rainfall runoff enters to blend the main place of purification.The recessed depth of lower concave segment 13 The relative plane of road 10 of degree is 150mm~250mm;Green land spreading structure is divided into four layers in lower concave segment 13, is respectively from top to bottom: Coating 6, plantation soil layer 5, layer of sand 8, gravel layer 7, can further purify, infiltrate the relatively low rainfall runoff of pollution concentration.It is recessed 13 minimum points of section, less than the dirty minimum point of section 1 is cut, are that rainfall runoff remittance speed exceedes entering for concave herbaceous field when rainfall intensity is larger Ability is oozed, to avoid region ponding excessive, one stormwater overflow mouthful 4, the rain are set every 10~15m on the lower center line of concave segment 13 Water overfall 4 is connected with subsurface stormwater pipeline;Stormwater overflow mouthful 4 absolute altitudes are flush to the plane of road 10, i.e. the inner product of concave segment 13 instantly When water depth exceedes 10 plane of road, stormwater overflow mouthful 4 collects excessive runoff, and is discharged by municipal storm sewer.
As to the preferred of above-mentioned technical proposal, using having opening, or the curb 2 with water permeable ability, and Opening lowest point absolute altitude cuts the dirty peak absolute altitude of section 1 higher than the recessed greenery patches.
Specific embodiment of the utility model is described above.It is to be appreciated that the utility model not office It is limited to above-mentioned particular implementation, those skilled in the art can make various deformations or amendments within the scope of the claims, This has no effect on substantive content of the present utility model.

Claims (10)

1. a kind of concave herbaceous field structure applied to road machine non-isolated band, it is characterised in that the concave herbaceous field structure The linkage section that dirty section, middle lower concave segment and connection cut dirty section and lower concave segment is cut including both sides;Described section of dirty section is located at and leaned on Nearly machine non-isolated band curb side, described section of dirty section is in a concave shape.
2. the concave herbaceous field structure according to claim 1 applied to road machine non-isolated band, it is characterised in that described It is 5cm~10cm that dirty section, which is cut, relative to the recessed depth of road plane;One side cuts dirty section width and accounts for machine non-isolated with bandwidth 15%~20%.
3. the concave herbaceous field structure according to claim 1 applied to road machine non-isolated band, it is characterised in that described Cut dirty section and be provided with fill stratum and resistant vegetable layer from the bottom to top;Infiltration coefficient≤1 × 10 of the fill stratum-6m/s。
4. the concave herbaceous field structure according to claim 1 applied to road machine non-isolated band, it is characterised in that described The peak for cutting dirty section is flushed with the lower end of curb opening.
5. the concave herbaceous field structure according to claim 1 applied to road machine non-isolated band, it is characterised in that described Curb is open type curb, and opening lowest point absolute altitude cuts dirty section peak absolute altitude higher than described.
6. the concave herbaceous field structure according to claim 1 applied to road machine non-isolated band, it is characterised in that described Lower concave segment width accounts for 60%~70% of machine non-isolated with bandwidth;The lower concave segment minimum point is less than a section dirty section minimum point.
7. the concave herbaceous field structure according to claim 6 applied to road machine non-isolated band, it is characterised in that relative In road plane, the recessed depth of the lower concave segment is 150mm~250mm.
8. the concave herbaceous field structure according to claim 1 applied to road machine non-isolated band, it is characterised in that described Lower concave segment is from the bottom to top provided with gravel layer, layer of sand, plantation soil layer and coating.
9. the concave herbaceous field structure according to claim 1 applied to road machine non-isolated band, it is characterised in that described One stormwater overflow mouthful is set every 10~15m on lower concave segment center line, the stormwater overflow mouthful is connected with subsurface stormwater pipeline.
10. the concave herbaceous field structure according to claim 1 applied to road machine non-isolated band, it is characterised in that institute State to plant on linkage section and be implanted with single file hedgerow, plant height is higher than 30cm.
CN201621473599.1U 2016-12-29 2016-12-29 Concave herbaceous field structure applied to road machine non-isolated band Expired - Fee Related CN206359928U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621473599.1U CN206359928U (en) 2016-12-29 2016-12-29 Concave herbaceous field structure applied to road machine non-isolated band

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621473599.1U CN206359928U (en) 2016-12-29 2016-12-29 Concave herbaceous field structure applied to road machine non-isolated band

Publications (1)

Publication Number Publication Date
CN206359928U true CN206359928U (en) 2017-07-28

Family

ID=59377870

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621473599.1U Expired - Fee Related CN206359928U (en) 2016-12-29 2016-12-29 Concave herbaceous field structure applied to road machine non-isolated band

Country Status (1)

Country Link
CN (1) CN206359928U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109098256A (en) * 2018-10-10 2018-12-28 丁文铃 A kind of sunk type greenery patches structure in sponge city
CN111501956A (en) * 2020-03-31 2020-08-07 中国建筑第八工程局有限公司 Sponge type grass planting ditch based on limited space transformation and transformation method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109098256A (en) * 2018-10-10 2018-12-28 丁文铃 A kind of sunk type greenery patches structure in sponge city
CN111501956A (en) * 2020-03-31 2020-08-07 中国建筑第八工程局有限公司 Sponge type grass planting ditch based on limited space transformation and transformation method thereof

Similar Documents

Publication Publication Date Title
CN104005316B (en) A kind of road kerb that there is draining and cut dirty function
CN103643612B (en) Shallow grass ditch and the manufacture method of shallow grass ditch
CN103603320B (en) A kind of LID type storm-collector and design and calculation method thereof
CN203613515U (en) LID (Low Impact Development)-type rainwater ditch
CN203080678U (en) Environment-friendly community shock-resistant rainwater ecological utilizing system
CN204875417U (en) Ecological way engineering system
CN205398233U (en) Enhanced nitrogen removal rainwater garden who is fit for high ground water level of high cohesive soil earth
CN113818534B (en) Biological detention facility for sponge urban road
CN207062672U (en) A kind of permeable pavement structure
CN106320494B (en) The construction method of sponge engineering system based on existing urban road and drainage condition
CN203782519U (en) Shallow grass ditch
CN206359928U (en) Concave herbaceous field structure applied to road machine non-isolated band
CN207419183U (en) A kind of grass planting ditch for sponge city
CN207700330U (en) A kind of concave herbaceous field grass-planting ecological ditch
CN214362619U (en) Sponge urban road structure
CN104264773A (en) Flow storage wetland system for treating parking lot rainwater and adjusting microclimate
CN208501715U (en) A kind of Rain Garden
CN111535098A (en) Rainwater drainage system for green belts and sidewalks of town roads and construction method
CN102487695A (en) Green belt for roads
CN214530989U (en) Grass planting ditch and sponge city pavement road surface linking structure
CN104631279A (en) Space utilization road surface unit
CN204112465U (en) A kind of for the treatment of parking lot rainwater and regulate microclimate store stream wet land system
CN207685966U (en) A kind of grass planting ditch structure
CN211340255U (en) Rainwater drainage system for green belts and sidewalks of urban roads
CN212582325U (en) Town road with water function is received to face formula

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Huang Jian

Inventor after: Liang Jie

Inventor after: Han Zhong

Inventor after: Zhang Peng

Inventor after: Zhai Yuanzhen

Inventor after: Xie Sheng

Inventor before: Huang Jian

Inventor before: Liang Jie

Inventor before: Han Zhong

Inventor before: Zhang Peng

Inventor before: Zhai Yuanzhen

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170728