CN206356749U - High-pressure gas double-wall pipe weld monitoring system - Google Patents

High-pressure gas double-wall pipe weld monitoring system Download PDF

Info

Publication number
CN206356749U
CN206356749U CN201720006245.4U CN201720006245U CN206356749U CN 206356749 U CN206356749 U CN 206356749U CN 201720006245 U CN201720006245 U CN 201720006245U CN 206356749 U CN206356749 U CN 206356749U
Authority
CN
China
Prior art keywords
pressure gas
wall pipe
gas double
camera lens
monitoring system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720006245.4U
Other languages
Chinese (zh)
Inventor
陈云飞
陈乐�
刘汉军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangnan Shipyard Group Co Ltd
Original Assignee
Jiangnan Shipyard Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangnan Shipyard Group Co Ltd filed Critical Jiangnan Shipyard Group Co Ltd
Priority to CN201720006245.4U priority Critical patent/CN206356749U/en
Application granted granted Critical
Publication of CN206356749U publication Critical patent/CN206356749U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Investigating Materials By The Use Of Optical Means Adapted For Particular Applications (AREA)
  • Examining Or Testing Airtightness (AREA)

Abstract

The utility model provides a kind of high-pressure gas double-wall pipe weld monitoring system, and the high-pressure gas double-wall pipe includes outer tube, the inner tube set with the outer coaxial tube heart, the look cock being arranged on outer tube wall;The weld monitoring system includes camera lens, mirror body pipeline, conduit, video information process system and televimonitor, and the conduit passes through the look cock, and the mirror body pipeline is through the conduit and stretches into outer tube and inner tube;The video information process system and televimonitor are outside the high-pressure gas double-wall pipe;The camera lens is located at the end of mirror body pipeline, and the camera lens is sent to the commissure of inner tube or outer tube, and the cable of the camera lens is connected through mirror body pipeline with video information process system, and video information process system is connected with televimonitor.The utility model is simple in construction, application method is simple, inspection is rapid, with low cost, reliability is high.

Description

High-pressure gas double-wall pipe weld monitoring system
Technical field
The utility model is related to a kind of weld monitoring system, and more particularly to one kind applies to engine of boat and ship gaseous fuel Supply the high-pressure gas double-wall pipe weld monitoring system of piping.
Background technology
High-pressure gas double-wall pipe is the feed tube of ship machine gas engine fuel, to prevent letting out for high-pressure gas Leakage, the air-tightness and intensive properties of high-pressure gas double-wall pipe must assure that, so whole high-pressure gas double-wall pipe pipe joint should use up Amount is few, and system is in high pressure conditions, avoids connecting using flange as far as possible, use complete penetraction and fusion in welding butt welding form more.
In the welding production of common pipe, often only focus on the result of detection of non-destructive monitoring personnel, the ground of inconvenience observation Square welder thinks little of, and treats to carry out pinpointing the problems when seamless detection or flaw detection together after later stage all pipeline weldings are complete, Now this root pipe must be scrapped.Monitoring to the presentation quality of weld seam can not cause enough attention, so as to frequently result in weldering Seam outward appearance is unqualified and does over again, and reduces labor productivity.
High-pressure gas double-wall pipe is expensive, and pipe safety requires higher, so welding quality requires stricter, separately The outer whole pipe joint of high-pressure gas double-wall pipe is less, and presentation quality monitoring is difficult, so that the high-pressure gas double-walled of prior art Pipe weld monitoring system is often complicated, and method is cumbersome, checks slow, monitoring cost is high, poor reliability.
The content of the invention
The shortcoming of prior art in view of the above, the technical problems to be solved in the utility model is to provide a kind of structure Simply, method is simple, check the high high-pressure gas double-wall pipe weld monitoring system of rapid, with low cost, reliability, existing to overcome There is the drawbacks described above of technology.
In order to solve the above-mentioned technical problem, the utility model provides a kind of high-pressure gas double-wall pipe weld monitoring system, institute State the inner tube that high-pressure gas double-wall pipe is set including outer tube, with the outer coaxial tube heart, the look cock being arranged on outer tube wall;Institute Stating weld monitoring system includes camera lens, mirror body pipeline, conduit, video information process system and televimonitor, and the conduit is worn The look cock is crossed, the mirror body pipeline is through the conduit and stretches into outer tube and inner tube;The video information process System and televimonitor are outside the high-pressure gas double-wall pipe;
The camera lens is located at the end of mirror body pipeline, and the camera lens is sent to the commissure of inner tube or outer tube, the mirror The cable of head is connected through mirror body pipeline with video information process system, and video information process system is connected with televimonitor Connect.
Preferably, the camera lens includes illuminating lamp and miniature image sensor.
Preferably, the illuminating lamp be high-brightness LED lamp, the function with 360 ° of comprehensive scannings, and with focusing and Optical zoom function.
Preferably, the conduit is copper pipe.
Preferably, the maximum length of the mirror body pipeline is 1000 meters.
Preferably, the look cock is multiple, is respectively arranged near outer tube elbow, or the weld seam of inner tube, outer tube.
As described above, high-pressure gas double-wall pipe weld monitoring system of the present utility model, has the advantages that:
First, simple in construction, method is simple, check that rapid, with low cost, reliability is high;
2nd, can the welding of real-time monitoring tubular road when appearance of weld quality, can and after face of weld is cleaned out Presentation quality inspection is carried out to the surface of weld seam and its heat affected area immediately, can be detected in real time with the presence or absence of such as surface gas The surface defects such as hole, undercut, overlap, crackle, incomplete fusion, incomplete root penetration, root protrusion;So that weld defect can be timely It was found that, eliminate early, so as to improve the success rate of strength test and leak test, save construction cost, save the time.
Brief description of the drawings
Fig. 1 is shown as the structural representation of high-pressure gas double-wall pipe weld monitoring system of the present utility model.
Component label instructions
1 outer tube
2 inner tubes
3 look cocks
4 camera lenses
5 mirror body pipelines
6 conduits
7 video information process systems
8 televimonitors
Ab weld seams
Embodiment
Embodiment of the present utility model is illustrated by particular specific embodiment below, those skilled in the art can be by this Content disclosed by specification understands other advantages of the present utility model and effect easily.
Refer to Fig. 1.It should be clear that structure, ratio, size depicted in this specification institute accompanying drawings etc., only to coordinate Content disclosed in specification, so that those skilled in the art is understood with reading, being not limited to the utility model can be real The qualifications applied, therefore do not have technical essential meaning, the tune of the modification of any structure, the change of proportionate relationship or size It is whole, in the case where not influenceing the utility model effect that can be generated and the purpose that can reach, all should still it fall in the utility model institute The technology contents of announcement are obtained in the range of covering.Meanwhile, in this specification it is cited as " on ", " under ", "left", "right", The term of " centre " and " one " etc., is merely convenient to understanding for narration, and is not used to limit the enforceable scope of the utility model, Its relativeness is altered or modified, under without essence change technology contents, when being also considered as the enforceable category of the utility model.
As shown in figure 1, the utility model provides a kind of high-pressure gas double-wall pipe weld monitoring system, the high-pressure gas is double Wall pipe includes outer tube 1, the inner tube 2 set with the outer coaxial tube heart, the look cock 3 being arranged on outer tube wall.The weld seam prison Examining system includes camera lens 4, mirror body pipeline 5, conduit 6, video information process system 7 and televimonitor 8, and the conduit 6 is passed through The look cock 3, the mirror body pipeline 5 is through the conduit 6 and stretches into outer tube 1 and inner tube 2;At the video information Reason system 7 and televimonitor 8 are outside the high-pressure gas double-wall pipe.
The camera lens 4 is located at the end of mirror body pipeline 5, and the camera lens 4 is sent to the weld seam ab of inner tube 2 or outer tube 1 Place, the cable of the camera lens 4 is connected through mirror body pipeline 5 with video information process system 7, video information process system 7 and Televimonitor 8 is connected.
The camera lens 4 receives the light that commissure reflection comes, and this light is converted into electric signal, then will by mirror body pipeline 5 Electric signal is transported to the video information process system 7 outside the high-pressure gas double-wall pipe, and video information process system 7 will The electric signal received is stored and handled, then is transferred to the televimonitor 8 outside the high-pressure gas double-wall pipe, most The coloured image of weld seam monitored is shown by televimonitor 8 eventually, weld seam ab is observed and monitored.
The camera lens 4 includes illuminating lamp and miniature image sensor, and due to the hot environment of welding, camera lens 4 needs anti-height The ability of temperature, therefore, the camera lens 4 are high temperature resistant camera lens.The minimum of the camera lens 4 is identified as 0.5mm crack defect;For Some high-end borescopes, minimum identification is up to 0.04mm crackles.
The miniature image sensor is the core devices of high-pressure gas double-wall pipe weld monitoring system of the present utility model, It converts light signals into electric signal in the way of Charged Couple, and is sent to video information process system 7 to complete image Transmission and regeneration.The illuminating lamp is high-brightness LED lamp, and the function with 360 ° of comprehensive scannings can carry out 360 ° of full sides The scanning of position, and with focusing and optical zoom function.
The video information process system 7 uses high power clear colored CCD (English full name:Charge-couple- Device, Chinese full name:Charge coupled cell), using exclusive professional software processing system, freezed, amplified, analyzed, Measurement, is greatly improved the accuracy for judging inner-walls of duct flaw detection position.
The length of the mirror body pipeline 5 differs, according to actual needs choosing value, and its maximum length is 1000 meters.
The conduit 6 be mainly used in assisting the free bend of mirror body pipeline 5, rotation (diameter of conduit 6 it is small can with flexion torsion, Mirror body pipeline 5 is assisted to advance, retreat, rotating), consequently facilitating camera lens 3 is sent into specified commissure.Need to bend because of conduit 6, turn round Turn, therefore conduit 6 is preferably by the easy copper pipe for occurring plastic deformation.
Electric signal is conveyed to video information process system 7, video information process system by the camera lens 4 by mirror body pipeline 5 The electric signal received is stored and handled by system 7, then is transferred to the television monitoring outside the high-pressure gas double-wall pipe Device 8, so as to carry out the monitoring of visual field target, record, storage and graphical analysis, ensures well to diagnose and handling to provide.
The look cock 3 is multiple, is respectively arranged near outer tube elbow, or inner tube 2, the weld seam of outer tube 1.Because of height Compression ignition gas double-wall pipe pipe joint is less, sets multiple look cocks to be easy to outward appearance monitoring on the inside of weld seam.
The operating procedure of high-pressure gas double-wall pipe weld monitoring system of the present utility model is as follows:
First, before being monitored to double-wall pipe weld seam, operating personnel should contrast in endoscopic and be carried out in test block in kind Experiment, kilter is in each element for confirming high-pressure gas double-wall pipe weld monitoring system of the present utility model;
2nd, the internal structure feature of high-pressure gas double-wall pipe, the form at Butt Joint and position are understood, by program exhibition Open peer link instrument element, monitoring power supply, whether reliable, each instrument element position safety and steady of ground connection;
3rd, eyes should be made to adapt to monitoring of environmental and light before monitoring, should be noted that when working long hours and avoid eye fatigue, with Exempt from occur leakage prison;
4th, suitable camera lens 4 is selected, helps camera lens 4 to pass through look cock 3 with auxiliary mould conduit 6, smoothly reaches inner tube Or the specified commissure in outer tube;When camera lens 4 such as runs into obvious resistance in progradation, it should halt immediately, camera lens 4 Should be slow when exiting, it can not such as be pulled at by card master, in order to avoid damage outer tube 1, inner tube 2 and camera lens 4;
5th, before the insertion of camera lens 4 outer tube 1, should remove obstacle, burr in pipeline etc. may hinder, damage the thing of camera lens 4 Body;
6th, it can not understand for some inside or baroque pipeline, the advanced row observation of observation camera lens can be used, afterwards It is monitored again, makes camera lens just to monitored area as far as possible in monitoring;
When the 7th, being monitored inside the insertion of camera lens 4 monitoring object, the temperature of internal area to be monitored must be in tolerance zone It is interior, to avoid the damage of CCD lens assemblies;During monitoring, its radiation source intensity is also adjustable, in favor of the operation of endoscopic The observation of personnel and shooting defect image;
8th, the best fit of LED, adjustment LED and CCD camera lenses is opened, it is ensured that the picture on televimonitor is clear;
9th, generally, the mobile monitoring speed of camera lens 4 is no more than 10mm/s, should make image balance, beneficial to observation; Large area should use rectilinear scan pattern when sweeping survey, and survey width is swept every time and is no more than 20mm, the observation model of camera lens 4 is also must not exceed Enclose;
Tenth, weld monitoring personnel should prevent camera lens 4 from occurring to bear energy more than it between extraneous hard thing in the case of accident The violent shock of power;
11, the butt weld that need to carry out high-pressure gas double-wall pipe weld monitoring system monitoring according to design technology requirement is entered Line flag;
12, Treatment Analysis is carried out using the image of 8 pairs of collections of televimonitor, after weld monitoring is finished, prison should be provided Observe and predict announcement;
13, high-pressure gas double-wall pipe Butt welded seam performs inspection according to relevant criterion, is deposited not in the root of weld In crackle, incomplete penetration defect;The excessive defect that weld seam is present, operating personnel should record the image of the defect in time, and be subject to Numbering, after need to confirming to poor weld through relevant departments, can carry out soldering;After Weld Seam Repairation, 4 pairs of camera lens should be also used The weld seam re-starts endoscopic, final check and accept and record again;
14, after monitoring terminates every time, it is necessary to clean camera lens 4 using 70% spirit solvent, and arrange instrument, scene.
In summary, high-pressure gas double-wall pipe weld monitoring system of the present utility model, simple in construction, method is simple, inspection Look into rapid, with low cost, reliability high.Can the welding of real-time monitoring tubular road when appearance of weld quality, and in face of weld After cleaning out, presentation quality inspection can be carried out to the surface of weld seam and its heat affected area immediately, can detect in real time is It is no to there is such as surface pores, undercut, overlap, crackle, incomplete fusion, incomplete root penetration, root protrusion surface defect;So that weldering Seam defect can be found in time, be eliminated early, so as to improve the success rate of strength test and leak test, saving is constructed into This, saves the time.So, the utility model effectively overcomes various shortcoming of the prior art and has high industrial exploitation value Value.
Above-described embodiment only illustrative principle of the present utility model and its effect are new not for this practicality is limited Type.Any person skilled in the art can all be carried out without prejudice under spirit and scope of the present utility model to above-described embodiment Modifications and changes.Therefore, such as those of ordinary skill in the art without departing from the essence disclosed in the utility model God and all equivalent modifications completed under technological thought or change, should be covered by claim of the present utility model.

Claims (6)

1. a kind of high-pressure gas double-wall pipe weld monitoring system, the high-pressure gas double-wall pipe includes outer tube (1) and outer coaxial tube The inner tube (2) of heart setting, the look cock (3) being arranged on outer tube wall;Characterized in that,
The weld monitoring system includes camera lens (4), mirror body pipeline (5), conduit (6), video information process system (7) and TV Monitor (8), the conduit (6) passes through the look cock (3), and the mirror body pipeline (5) is through the conduit (6) and stretches into Between outer tube and inner tube;The video information process system (7) and televimonitor (8) are outside the high-pressure gas double-wall pipe Portion;
The camera lens (4) is located at the end of mirror body pipeline (5), and the camera lens (4) is sent to the commissure of inner tube or outer tube, institute The cable for stating camera lens (4) is connected through mirror body pipeline (5) with video information process system (7), video information process system (7) It is connected with televimonitor (8).
2. high-pressure gas double-wall pipe weld monitoring system according to claim 1, it is characterised in that:Camera lens (4) bag Include illuminating lamp and miniature image sensor.
3. high-pressure gas double-wall pipe weld monitoring system according to claim 2, it is characterised in that:The illuminating lamp is height Brightness LED, the function with 360 ° of comprehensive scannings, and with focusing and optical zoom function.
4. according to any described high-pressure gas double-wall pipe weld monitoring system of claims 1 to 3, it is characterised in that:It is described to lead Manage as copper pipe.
5. according to any described high-pressure gas double-wall pipe weld monitoring system of claims 1 to 3, it is characterised in that:The mirror The maximum length of body pipeline (5) is 1000 meters.
6. according to any described high-pressure gas double-wall pipe weld monitoring system of claims 1 to 3, it is characterised in that:It is described to see It is multiple to examine cock (3), is respectively arranged near outer tube elbow, or inner tube (2), the weld seam of outer tube (1).
CN201720006245.4U 2017-01-04 2017-01-04 High-pressure gas double-wall pipe weld monitoring system Active CN206356749U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720006245.4U CN206356749U (en) 2017-01-04 2017-01-04 High-pressure gas double-wall pipe weld monitoring system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720006245.4U CN206356749U (en) 2017-01-04 2017-01-04 High-pressure gas double-wall pipe weld monitoring system

Publications (1)

Publication Number Publication Date
CN206356749U true CN206356749U (en) 2017-07-28

Family

ID=59379449

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720006245.4U Active CN206356749U (en) 2017-01-04 2017-01-04 High-pressure gas double-wall pipe weld monitoring system

Country Status (1)

Country Link
CN (1) CN206356749U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107590324A (en) * 2017-08-29 2018-01-16 江南造船(集团)有限责任公司 High-pressure gas double-wall pipe stress and elastic support thermal expansion curve assay method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107590324A (en) * 2017-08-29 2018-01-16 江南造船(集团)有限责任公司 High-pressure gas double-wall pipe stress and elastic support thermal expansion curve assay method
CN107590324B (en) * 2017-08-29 2020-09-25 江南造船(集团)有限责任公司 Analysis and evaluation method for stress of high-pressure gas double-wall pipe and thermal expansion displacement of elastic support

Similar Documents

Publication Publication Date Title
CN105241375B (en) Contactless inspection of butt welds
CN107490589B (en) A kind of construction metallic conduit welded seam detection transillumination positioning device
CN101769728B (en) Method for detecting weld areas of hot-melting polythene pipe joints
CN107941828A (en) A kind of power cable and connector nondestructive detection system and method based on X-ray Real Time Imaging Technology
US6856662B2 (en) Remote examination of reactor nozzle J-groove welds
CN207850998U (en) A kind of emplacement type Nozzle weld ultrasonic phased array imaging detection simulating test pieces
CN206356749U (en) High-pressure gas double-wall pipe weld monitoring system
CN105758889A (en) Oil and gas pipeline infrared thermal wave imaging detection system and method
CN109521088B (en) Multichannel pulse vortex detection device and method for detecting pipeline defects
CN211235585U (en) Endoscope scanning device for inner surface of gas cylinder
CN208507205U (en) A kind of heavy water reactor main pipeline branch pipe connection connection structure for alleviating stress corrosion cracking
JP2011069616A (en) Device and method for inspection inner surface of pipe material
CN210269661U (en) Reducing pipeline crack detection equipment
JP2010169669A (en) Method and apparatus for inspecting cylindrical object
CN103217476A (en) Ultrasonic surface wave detection method for surface defects of butt weld of rows of tubes of boiler header
CN107389706B (en) Visual thick wall metal pipeline welded joint gamma source central transillumination positioning device
CN107703163B (en) Bispin formula high-pressure line welding seam positioner that detects a flaw
CN101915643A (en) Welding line air pressure leakage check technology
CN219104765U (en) In-car pipe detection probe
CN208060465U (en) A kind of pipeline inspection holder
CN207675673U (en) A kind of power cable and connector nondestructive detection system based on X-ray Real Time Imaging Technology
CN206398250U (en) A kind of metal corrugated pipe expansion joint for being easy to check internal injury
KR20220057330A (en) Inspection device of heat recovery steam generator fin tube
CN206459977U (en) Vortex endoscope
CN107389707B (en) Visual multipurpose process pipeline welding seam flaw detection device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant