CN206309374U - A kind of pitching pressure break and closing well diffusion tubing string step by step - Google Patents

A kind of pitching pressure break and closing well diffusion tubing string step by step Download PDF

Info

Publication number
CN206309374U
CN206309374U CN201621313580.0U CN201621313580U CN206309374U CN 206309374 U CN206309374 U CN 206309374U CN 201621313580 U CN201621313580 U CN 201621313580U CN 206309374 U CN206309374 U CN 206309374U
Authority
CN
China
Prior art keywords
tubing string
sliding sleeve
compression packer
pressure break
packer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621313580.0U
Other languages
Chinese (zh)
Inventor
刘忠能
蒙鑫
何华
任勇
冯长青
赵粉霞
李旭梅
刘汉斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum and Natural Gas Co Ltd
Original Assignee
China Petroleum and Natural Gas Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petroleum and Natural Gas Co Ltd filed Critical China Petroleum and Natural Gas Co Ltd
Priority to CN201621313580.0U priority Critical patent/CN206309374U/en
Application granted granted Critical
Publication of CN206309374U publication Critical patent/CN206309374U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model belongs to oilfield horizontal well oil pipe plus sand staged fracturing renovation technique field, specifically related to a kind of pitching pressure break and closing well diffusion tubing string step by step, including oil pipe, oil pipe lower end is sequentially connected safety joint, upper compression packer, sand blower of sliding sleeve and lower compression packer, it is 2~6 grades that described sand blower of sliding sleeve is equipped with series, interior latus rectum stepped change, pitching diameter is from small to large, compared with conventional fracturing string, on the tubing string, under use compression packer, fixed tubular column, cannot unseal, closing well diffusion after pressure break can be realized, supplement the purpose of reservoir energy;Meanwhile, sand blower of sliding sleeve configuration series is 2 ~ 6 grades, and diameter ball from small to large is put into successively, enables new sand blower of sliding sleeve, sets Y341 packers, can realize that multistage is constructed by dragging tubing string;The tubing string can realize the purpose of horizontal well refracturing, diffusion, and efficiency of construction can be improved again.

Description

A kind of pitching pressure break and closing well diffusion tubing string step by step
Technical field
The utility model belongs to oilfield horizontal well oil pipe plus sand staged fracturing renovation technique field, and in particular to one kind is step by step Pitching pressure break and closing well diffusion tubing string.
Background technology
At present, because low permeability oil and gas field injection-production relation is difficult to clearly set up, pressure keeps level relatively low.It is right In the low net horizontal section of portion of energy, in order to supplement reservoir energy, fracturing effect is improved, it is necessary to closing well pair after refracturing Fracturing section carries out diffusion, supplements stratum energy.
In conventional oil pipe sand fracturing tubing string, mostly just consider that card envelope is required, it is ensured that pressure break success, do not consider pressure Rear pressurize problem is split, pressurize 24h is even more required for a long time after conventional inflatable packer cannot meet pressure break, causes work Skill purpose is difficult to, and shows as:One, conventional inflatable packer construction is easy certainly by the interference of bottom hole pressure surge after terminating Dynamic deblocking, it is impossible to pressurize;Two, the interference that transformation section is vulnerable to upper and lower other transformation sections is repeated, cause pressurize difficult;Three, construction Efficiency is low.
Utility model content
The purpose of this utility model be overcome conventional oil pipe sand fracturing tubing string cannot meet pressure break after pressurize 24h even The requirement of longer time, the problem for causing technique purpose to be difficult to.
Therefore, the utility model provides a kind of pitching pressure break and closing well diffusion tubing string step by step, including oil pipe, described oil Pipe lower end is sequentially connected safety joint, upper compression packer, sand blower of sliding sleeve and lower compression packer, described sliding sleeve It is 2~6 grades that sanding machine is equipped with series, interior latus rectum stepped change, and pitching diameter is from small to large.
Between described safety joint and upper compression packer, between upper compression packer and sand blower of sliding sleeve and Connected by tubing nipple between sand blower of sliding sleeve and lower compression packer.
Described upper compression packer and lower compression packer is hydraulic setting, above proposes the compression packing of deblocking Device.
Described upper compression packer is Y341 type packers, and described lower compression packer is Y211 types machinery anchor Determine packer.
This pressure break of pitching step by step and the beneficial effect of closing well diffusion tubing string that the utility model is provided:
First, upper and lower packer above carries deblocking packer using mechanical anchor, as long as fixed tubular column, packer will not Deblocking, it can be ensured that fracturing section pressurize effect.
Second, upper packer is built the pressure and is set by pitching, circulation, and simple to operate, efficiency of construction is high.
3rd, can realize horizontal well multistage pressure break, closing well diffusion by dragging tubing string.
Brief description of the drawings
The utility model is described in further details below with reference to accompanying drawing.
Fig. 1 is structural representation of the present utility model.
Description of reference numerals:1st, oil pipe;2nd, safety joint;3rd, tubing nipple;4th, upper compression packer;5th, sliding sleeve sandblasting Device;6th, lower compression packer.
Specific embodiment
The purpose of this utility model is to provide a kind of pitching pressure break and closing well diffusion tubing string step by step, optimizes upper and lower packer Combination, tubing string can long-time pressurize, realize the technique purpose of closing well diffusion after pressure break, at the same can realize drag fracturing construct, Efficiency of construction is high.
In order to realize the utility model above-mentioned purpose, using following technical scheme:
The present embodiment provides a kind of pitching pressure break and closing well diffusion tubing string step by step, as shown in figure 1, including oil pipe 1, it is described The lower end of oil pipe 1 is sequentially connected safety joint 2, upper compression packer 4, sand blower of sliding sleeve 5 and lower compression packer 6, institute It is 2~6 grades that the sand blower of sliding sleeve 5 stated is equipped with series, interior latus rectum stepped change, and pitching diameter is from small to large.
Between the safety joint 2 and upper compression packer 4, between upper compression packer 4 and sand blower of sliding sleeve 5 with And connected by tubing nipple 3 between sand blower of sliding sleeve 5 and lower compression packer 6.
When in use, it is 2~6 grades that sand blower of sliding sleeve is equipped with series to the present embodiment fracturing string, and interior latus rectum stepped change is thrown Bulb diameter is from small to large.Specific work process is as follows:
First, formation testing team completes through wash well operations as requested, under enter fracturing string, enter under tubing string is specific order for figure In:Lower compression packer 6, tubing nipple 3, sand blower of sliding sleeve 5, tubing nipple 3, upper compression packer 4, tubing nipple 3, Safety joint 2, oil pipe 1.
Under enter during, it is necessary to accurate measurement and in detail record oil pipe 1 and downhole tool length, it is ensured that sand blower of sliding sleeve 5 Specking position consistency is designed in position with least significant end, and both errors should be less than 0.5m, should otherwise adjust tool location;Then, above carry, Decentralization sets lower compression packer 6, sits fracture well head, starts Frac unit, and oil pipe 1 throws the ball of minor diameter, and small displacement is just followed Ring is implanted sequentially displacement fluid, until ball is seated on sand blower of sliding sleeve 5, oil pipe starts to build the pressure, and controls discharge capacity, slowly builds the pressure, and sits Seal up compression packer 4.After the completion of waiting to set, continue to improve pressure, the built-in sliding sleeve of sand blower of sliding sleeve 5 is destroyed, with reservoir Connection, oil pressure declines, and the load fluid of predetermined concentration is injected from the direct circulation of oil pipe 1, and old eyelet, importing are entered through sand blower of sliding sleeve 5 Reservoir, opens and splits, extends crack, completes this section of pressing crack construction.
After first paragraph pressure break terminates, closing well, build the pressure, according to pressure condition upper lifting pipe post, solution seals up compression packer 4, Control discharge capacity carries out one hole volume of reacting cycle well-flushing, and when returning fluid's body is without sand grains, well head, upper lifting pipe post solution are unloaded in termination of pumping Envelope lower compression packer 6, upper lifting pipe post to next transformation section.Above step is repeated, until all interval transformations of the well are finished, Rise fracturing string, under enter sand washing, suction, formation testing tubing string.
Horizontal well refracturing and the fracturing string of closing well diffusion that the present embodiment is provided, by pitching, suppress and set Compression packer 4, after sliding sleeve is destroyed in continuation pressurization, pressure break channels open.
Compared with conventional fracturing string, the tubing string is upper and lower to use compression packer, and upper compression packer 4 is with Compression packer 6 is hydraulic setting, above carries the compression packer of deblocking, and specifically, upper compression packer 4 is Y341 Type packer, described lower compression packer 6 is Y211 type mechanical anchor packers, fixed tubular column, cannot be unsealed, Neng Goushi Closing well diffusion, the purpose of supplement reservoir energy after existing pressure break;Meanwhile, sand blower of sliding sleeve configuration series is 2~6 grades, is put into successively Diameter ball from small to large, enables new sand blower of sliding sleeve, sets Y341 packers, and sealing pipe column is solved successively by above carrying, dragging pipe Post can realize that multistage is constructed;The tubing string can realize the purpose of horizontal well refracturing, diffusion, and efficiency of construction can be improved again.
In sum, this pressure break of pitching step by step of the present utility model and closing well diffusion tubing string, optimize upper and lower packer group Close, tubing string can long-time pressurize, realize the technique purpose of closing well diffusion after pressure break, at the same can realize drag fracturing construct, apply Work efficiency high.
Exemplified as above is only for example, not constituting to protection domain of the present utility model to of the present utility model Limitation, every design same or analogous with the utility model is belonged within protection scope of the present invention.

Claims (4)

1. one kind pitching pressure break and closing well diffusion tubing string step by step, including oil pipe(1), it is characterised in that:Described oil pipe(1)Lower end It is sequentially connected safety joint(2), upper compression packer(4), sand blower of sliding sleeve(5)With lower compression packer(6), it is described Sand blower of sliding sleeve(5)It is 2~6 grades to be equipped with series, interior latus rectum stepped change, and pitching diameter is from small to large.
2. as claimed in claim 1 pitching pressure break and closing well diffusion tubing string step by step, it is characterised in that:Described safety joint (2)With upper compression packer(4)Between, upper compression packer(4)With sand blower of sliding sleeve(5)Between and sand blower of sliding sleeve (5)With lower compression packer(6)Between pass through tubing nipple(3)Connection.
3. as claimed in claim 1 or 2 pitching pressure break and closing well diffusion tubing string step by step, it is characterised in that:Described upper compression Formula packer(4)With lower compression packer(6)It is hydraulic setting, above carries the compression packer of deblocking.
4. as claimed in claim 3 pitching pressure break and closing well diffusion tubing string step by step, it is characterised in that:Described upper compression envelope Every device(4)It is Y341 type packers, described lower compression packer(6)It is Y211 type mechanical anchor packers.
CN201621313580.0U 2016-12-02 2016-12-02 A kind of pitching pressure break and closing well diffusion tubing string step by step Active CN206309374U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621313580.0U CN206309374U (en) 2016-12-02 2016-12-02 A kind of pitching pressure break and closing well diffusion tubing string step by step

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621313580.0U CN206309374U (en) 2016-12-02 2016-12-02 A kind of pitching pressure break and closing well diffusion tubing string step by step

Publications (1)

Publication Number Publication Date
CN206309374U true CN206309374U (en) 2017-07-07

Family

ID=59249619

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621313580.0U Active CN206309374U (en) 2016-12-02 2016-12-02 A kind of pitching pressure break and closing well diffusion tubing string step by step

Country Status (1)

Country Link
CN (1) CN206309374U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114607318A (en) * 2022-03-24 2022-06-10 中煤科工集团西安研究院有限公司 Fracturing cooperative construction method for combined production and drilling of multi-layer horizontal well for deep coal bed methane

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114607318A (en) * 2022-03-24 2022-06-10 中煤科工集团西安研究院有限公司 Fracturing cooperative construction method for combined production and drilling of multi-layer horizontal well for deep coal bed methane

Similar Documents

Publication Publication Date Title
CN109723404B (en) Naked eye plugging device and method for coal gas exploration well
CN103306643B (en) A kind of water drainage gas production device and method
CN202108493U (en) Water jetting multi-cluster subsection fracturing strings of horizontal well
CN105134141B (en) A kind of process pipe string
CN209670939U (en) A kind of coal mine gas extraction drill hole long range multi-stage cementing hole packer
CN108678721A (en) Packaged type hydraulic fracturing and injection hole sealing integrated apparatus and its construction method
CN208900072U (en) A kind of novel bag type paste hole packer
CN204941480U (en) The horizontal well completion sleeve pipe of segmentation exploitation and the tubing string of formation thereof can be realized
CN104120997A (en) Pipe column for horizontal well
CN104989325B (en) A kind of method using two-tube gas well liquid loading tubing string gas production arranged side by side
CN206309374U (en) A kind of pitching pressure break and closing well diffusion tubing string step by step
CN204252929U (en) Oil recovery water plugging string
CN112431579B (en) Preset small-diameter pipe internal fracturing device and method for side drilling well and small-hole well
CN107605443B (en) CO (carbon monoxide)2Gas driving and injecting process pipe column structure
CN203808896U (en) Long-section casing damage well expansion pipe double-card casing pipe layered packing repairing device
CN207004498U (en) Infinite stages switching sliding sleeve fracturing tool
CN103939075B (en) A kind of fracturing process improving coal mine gas drainage effect and device
CN203948037U (en) Sectional quantitative injection string
CN206309371U (en) It is a kind of suitable for horizontal well refracturing and the fracturing string of closing well diffusion
CN107191218A (en) A kind of outstanding slag waterinfusion blasting is anti-reflection and the method for mash gas extraction
CN104806211B (en) One kind takes over calm the anger extracting device of oil and method
CN206309372U (en) A kind of horizontal well small displacement drag fracturing tubing string
CN214944177U (en) CO (carbon monoxide)2Oil well driving non-killing oil production pipe column
CN109209284B (en) Long well section casing damage well subsidy reinforcing apparatus
CN206309294U (en) A kind of small displacement horizontal well drag fracturing tubing string

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant