CN206300569U - Destroy equipment and feed intake portion in fuse priming system laboratory - Google Patents

Destroy equipment and feed intake portion in fuse priming system laboratory Download PDF

Info

Publication number
CN206300569U
CN206300569U CN201621318810.2U CN201621318810U CN206300569U CN 206300569 U CN206300569 U CN 206300569U CN 201621318810 U CN201621318810 U CN 201621318810U CN 206300569 U CN206300569 U CN 206300569U
Authority
CN
China
Prior art keywords
heater
commissioning pipe
priming system
equipment
fuse
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621318810.2U
Other languages
Chinese (zh)
Inventor
张彬
李孝玉
黄世银
徐衎
魏晗
熊冉
周森
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Command Of 63981 Army Of Chinese People's Liberation Army
Original Assignee
Command Of 63981 Army Of Chinese People's Liberation Army
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Command Of 63981 Army Of Chinese People's Liberation Army filed Critical Command Of 63981 Army Of Chinese People's Liberation Army
Priority to CN201621318810.2U priority Critical patent/CN206300569U/en
Application granted granted Critical
Publication of CN206300569U publication Critical patent/CN206300569U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • General Induction Heating (AREA)

Abstract

A kind of fuse priming system laboratory destroy equipment and feed intake portion, destroy equipment and be provided with the destruction body of heater with furnace chamber in the fuse priming system laboratory, destroy and be provided with heating furnace below body of heater, top is connected with discharge nozzle, the discharge nozzle is to curving, the portion that feeds intake communicated with furnace chamber is fixed with the side for destroying body of heater, the portion of feeding intake includes commissioning pipe, the dog-house of commissioning pipe outer end and the commissioning pipe tail of the inner, commissioning pipe axis is in commissioning pipe and destroys the junction of body of heater perpendicular to destruction body of heater, commissioning pipe tail is located at the inside for destroying body of heater and stretches into the side wall for destroying body of heater.The utility model meets the condition that burner hearth bottom is not connected with extraneous straight line on the premise of manufacturing cost is not increased, and can simplify device structure, reduces equipment volume.So as to reduce equipment volume, it is easy to operation and equipment to move.

Description

Destroy equipment and feed intake portion in fuse priming system laboratory
Technical field
The utility model is related to priming system Destruction Establishment, and specifically a kind of fuse priming system laboratory is destroyed equipment and fed intake Portion.
Background technology
Some not quick-fried priming systems of generation and remaining priming system that all can be different degrees of after priming system experiment.To ensure business work That makees is smoothly completed, and not quick-fried priming system is processed in time, should eliminate the hidden danger in experiment, is designed as needed Produce meet new demand fuse priming system laboratory destroy equipment, with meet the timely of the not quick-fried fuse priming system of laboratory and Safety is destroyed.
Existing fuse priming system laboratory destruction equipment is still not perfect enough, and the structure design of such as its throw-in part is anti- Only the bomb fragments of burner hearth bottom directly fly to outside by putting into pipeline, cause unnecessary loss, it is necessary to by throw-in part Polymorphic structure is caused, manufacturing cost is improve;In order to ensure that fuse to be destroyed successfully can be put into burner hearth by throw-in part, especially Fuse is forbidden to rest on throw-in part, it is necessary to the pipeline of throw-in part be reduced into lateral dimension or increase angle of inclination, this is all unfavorable Connected with the straight line in the external world in burner hearth bottom is prevented.The distance of throw-in part and burner hearth bottom is increased, causes equipment volume big, heavy The heart is high, improves production cost and uses inconvenience.
The content of the invention
Technical problem to be solved in the utility model is to solve the above problems, there is provided a kind of fuse priming system laboratory pin The equipment of ruining feeds intake portion, can either reduce equipment volume and complexity, burner hearth bottom is prevented from again and is connected with the straight line in the external world.
The fuse priming system laboratory is destroyed equipment and is fed intake portion, and the fuse priming system laboratory is destroyed equipment and is provided with band The destruction body of heater of furnace chamber, to destroy and be provided with heating furnace below body of heater, and top is connected with discharge nozzle, and the discharge nozzle is to a lateral bending Song, prevents furnace chamber bottom to be connected from straight line with the residue-removing opening of discharge nozzle outer end;It is fixed with and furnace chamber in the side for destroying body of heater The portion that feeds intake for communicating, it is characterised in that:
The portion of feeding intake includes the commissioning pipe tail of commissioning pipe, the dog-house of commissioning pipe outer end and the inner, in commissioning pipe and pin The commissioning pipe axis of junction of body of heater is ruined perpendicular to the side wall for destroying body of heater, and commissioning pipe tail is located at the inside for destroying body of heater and stretches Enter to destroy the side wall of body of heater.
The commissioning pipe tail destroy body of heater inside stretch into destroy body of heater side wall length be feed intake bore 0.5~ 1.5 times.
The downside of the commissioning pipe tail inclines downwards, and angle of inclination is 35 ° to 60 °.
Typically, the downside of the commissioning pipe tail inclines downwards 45 °.
Further, the length of the destruction body of heater is 2~3.5 times of internal diameter.
Preferably, the internal diameter of the commissioning pipe is 0.2~0.4 times of footpath in destroying furnace body.
Preferably, the dog-house is provided with end cap.
Preferably, the dog-house end face is horizontally disposed with.
The utility model meets the bar that burner hearth bottom is not connected with extraneous straight line on the premise of manufacturing cost is not increased Part, and device structure can be simplified, reduce equipment volume.
The utility model dexterously breaches traditional direct welded structure on the outside of body of heater, causes ensureing commissioning pipe In the case of diameter, it is difficult to balance the contradiction for reducing equipment volume and preventing burner hearth bottom from not connected with extraneous straight line;To feed intake The tail end in portion is stretched into after body of heater in the welding of body of heater lateral wall, can ideally realize being easy to that input material smoothly falls, simplification feeds intake Portion's structure, significantly reduce commissioning pipe and furnace bottom distance when the pipe diameter that feeds intake is enough, so as to reduce equipment volume, be easy to operation Moved with equipment.
Brief description of the drawings
Fig. 1 is that device structure schematic diagram is destroyed in fuse priming system laboratory,
Fig. 2 is the right view of Fig. 1.
In figure:1-residue-removing opening, 2-discharge nozzle, 3-dog-house, 4-commissioning pipe, 5-casing, 6-destruction body of heater, 7- Road wheel, 8-heating furnace, 9-rotating shaft, 10-commissioning pipe tail, 11-feed intake portion, 12-furnace chamber.
Specific embodiment
The utility model is further illustrated with reference to the accompanying drawings and examples:It is fuse priming system as shown in Fig. 1,2 The overall structure of equipment is destroyed in laboratory, and the fuse priming system laboratory is destroyed equipment and is provided with the destruction body of heater 6 with furnace chamber 12, Destroy and be provided with heating furnace 8 below body of heater, top is connected with discharge nozzle 2, and the discharge nozzle makes the bottom of furnace chamber 12 to curving Straight line is unable to the residue-removing opening 1 of the outer end of discharge nozzle 2 to connect, and be easy to topple over waste material.
The portion 11 that feeds intake communicated with furnace chamber is fixed with the side for destroying body of heater.Destroy body of heater 6 and pass through rotating shaft 9 and bearing It is connected with the casing 5 of both sides, the motor in rotating shaft connecting box body, after Destruction terminates, can be with rotating shaft 9, by waste material Poured from furnace chamber.
Following examples are only a kind of preferred construction of the present utility model, and various prioritization schemes can cross-reference and reality It is existing.
Such as Fig. 2, the commissioning pipe tail 10 of the portion 11 including commissioning pipe 4, the dog-house 3 of commissioning pipe outer end and the inner that feed intake, Commissioning pipe can be simple 1/4 arcuation, make the level of dog-house 3 upwards, and the dog-house is provided with end cap.Commissioning pipe 4 and destruction The commissioning pipe axis of the junction of body of heater 6 is vertical with body of heater 6 is destroyed.
Commissioning pipe tail 10 is located at the inside for destroying body of heater 6 and stretches into the side wall for destroying body of heater 6, and the commissioning pipe tail 10 is in pin Stretch into that to destroy the side wall length of body of heater 6 be electrical path length in commissioning pipe 4 in the inside for ruining body of heater 6.It is easy to if entering very much length and be long Outside commissioning pipe is directly influenced by the damage of explosive.The downside of the commissioning pipe tail 10 inclines downwards, angle of inclination It is 45 °.
As a result of above structure so that the length for destroying body of heater 6 can be only 2~3.5 times of footpath in destroying furnace body.
Simultaneously as employing above structure, the diameter of the commissioning pipe 4 can be with sufficiently large, to destroy the internal diameter of body of heater 6 0.4 times.Meet different fuse species to be destroyed.
The utility model is destroyed device structure and is improved to small-sized laboratory fuse priming system, and on this basis Throw-in part is further improved, continues to breach the obstacle for reducing equipment volume, make the destruction of fuse priming system can be less Carried out in space, and be readily transported and safeguard.

Claims (7)

1. a kind of fuse priming system laboratory is destroyed equipment and is fed intake portion, and the fuse priming system laboratory is destroyed equipment and is provided with band stove The destruction body of heater (6) in chamber (12), to destroy and be provided with heating furnace (8) below body of heater, and top is connected with discharge nozzle (2), the discharging Pipe makes furnace chamber (12) bottom be unable to straight line with the residue-removing opening (1) of discharge nozzle (2) outer end and connects to curving;Destroying body of heater Side be fixed with the portion that feeds intake (11) communicated with furnace chamber, it is characterised in that:
Commissioning pipe tail (10) of the portion that feeds intake (11) including commissioning pipe (4), the dog-house (3) of commissioning pipe outer end and the inner, The commissioning pipe axis of the junction of commissioning pipe (4) and destruction body of heater (6) is perpendicular to the side wall for destroying body of heater (6), commissioning pipe tail (10) located at destroy body of heater (6) inside and stretch into destroy body of heater (6) side wall;The commissioning pipe tail (10) is destroying body of heater (6) side wall length that destruction body of heater (6) is stretched into inside is 0.5~1.5 times of commissioning pipe (4) internal diameter.
2. fuse priming system laboratory according to claim 1 is destroyed equipment and is fed intake portion, it is characterised in that:The commissioning pipe The downside of tail (10) inclines downwards, and angle of inclination is 35 ° to 60 °.
3. fuse priming system laboratory according to claim 2 is destroyed equipment and is fed intake portion, it is characterised in that:The commissioning pipe The downside of tail (10) inclines downwards 45 °.
4. fuse priming system laboratory according to claim 1 is destroyed equipment and is fed intake portion, it is characterised in that the destroying furnace The length of body (6) is 2~3.5 times of internal diameter.
5. fuse priming system laboratory according to claim 1 is destroyed equipment and is fed intake portion, it is characterised in that:The commissioning pipe (4) internal diameter is destroy body of heater (6) internal diameter 0.2~0.4 times.
6. fuse priming system laboratory according to claim 1 is destroyed equipment and is fed intake portion, it is characterised in that:The dog-house It is provided with end cap.
7. fuse priming system laboratory according to any one of claim 1~6 is destroyed equipment and is fed intake portion, it is characterised in that: The dog-house end face is horizontally disposed with.
CN201621318810.2U 2016-12-02 2016-12-02 Destroy equipment and feed intake portion in fuse priming system laboratory Expired - Fee Related CN206300569U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621318810.2U CN206300569U (en) 2016-12-02 2016-12-02 Destroy equipment and feed intake portion in fuse priming system laboratory

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621318810.2U CN206300569U (en) 2016-12-02 2016-12-02 Destroy equipment and feed intake portion in fuse priming system laboratory

Publications (1)

Publication Number Publication Date
CN206300569U true CN206300569U (en) 2017-07-04

Family

ID=59212612

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621318810.2U Expired - Fee Related CN206300569U (en) 2016-12-02 2016-12-02 Destroy equipment and feed intake portion in fuse priming system laboratory

Country Status (1)

Country Link
CN (1) CN206300569U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107883823A (en) * 2017-10-30 2018-04-06 西安近代化学研究所 A kind of small equivalent waste propellant flash burning processing unit

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107883823A (en) * 2017-10-30 2018-04-06 西安近代化学研究所 A kind of small equivalent waste propellant flash burning processing unit
CN107883823B (en) * 2017-10-30 2019-09-27 西安近代化学研究所 A kind of small equivalent waste propellant flash burning processing unit

Similar Documents

Publication Publication Date Title
CN206300569U (en) Destroy equipment and feed intake portion in fuse priming system laboratory
CN206580101U (en) A kind of tablet manufacturing feeding device
CN103438433B (en) Biomass particle burner of cylinder-type feeding system
CN2883266Y (en) Tapered spiral feeder
CN203431832U (en) Biomass pellet combustion machine of cylindrical type feeding system
CN206899833U (en) A kind of sludge bar-producing machine
CN206018654U (en) A kind of thoroughly Disposal System of Mud Burning that burns
CN205893051U (en) Paper mill's sludge treatment system
CN205641977U (en) Melting furnace is used in bar copper production
CN208846722U (en) A kind of electric heater and its heating tube assembly
CN208810190U (en) A kind of ground phosphate rock blanking device for chemical industry processing
CN208253558U (en) A kind of biomass multistage vortex burner
CN207532316U (en) Granular fuel oven
CN206540140U (en) One kind is corrosion-resistant to melt salt device for dragging dregs
CN207929390U (en) A kind of atomizing fishes and shrimps pharmaceutical process plant
CN206207458U (en) One kind material plug type screw feeder
CN206556415U (en) A kind of improved structure of meshbeltfurnace
US20090056600A1 (en) Furnace
CN201385413Y (en) Cooling device for feed inlet of double-screw machine
CN205662563U (en) Reducing furnace that smoke and dust is few
CN207827218U (en) A kind of discharging device of alcoholic
CN205580204U (en) Solid -liquid separation formula smelting furnace
CN209507990U (en) A kind of machine blowing bottle blow head
CN204656080U (en) A kind of cycles, economized heat oil gathering and transporting device
CN206654832U (en) Glass furnace two level charger and the storing hopper for it

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170704

Termination date: 20201202