CN206278525U - A kind of powder barrel-bin - Google Patents

A kind of powder barrel-bin Download PDF

Info

Publication number
CN206278525U
CN206278525U CN201621375193.XU CN201621375193U CN206278525U CN 206278525 U CN206278525 U CN 206278525U CN 201621375193 U CN201621375193 U CN 201621375193U CN 206278525 U CN206278525 U CN 206278525U
Authority
CN
China
Prior art keywords
stack shell
annular slab
shell
powder barrel
shell ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621375193.XU
Other languages
Chinese (zh)
Inventor
黄福利
史先五
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xuzhou Road Bridge Co Ltd
Original Assignee
Xuzhou Road Bridge Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xuzhou Road Bridge Co Ltd filed Critical Xuzhou Road Bridge Co Ltd
Priority to CN201621375193.XU priority Critical patent/CN206278525U/en
Application granted granted Critical
Publication of CN206278525U publication Critical patent/CN206278525U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model is related to a kind of powder barrel-bin, comprising support, auger, conelet, stack shell, Cang Gai, cat ladder, top guardrail and feed pipe;, located at stack shell lower end to constitute discharging opening, the branch is set up in stack shell lower section to support stack shell, the Cang Gai and top guardrail to be located at stack shell upper end, and the cat ladder and feed pipe are located at stack shell and support side for the auger and conelet;The stack shell includes multiple shell rings in cylinder, and is connected by connector between the adjacent shell ring;The supporting plate that the connector includes annular slab, the anchor ear being arranged on the outside of annular slab, is arranged on annular slab middle inside;The shell ring surface of the bottom is additionally provided with many reinforcements of even circumferential distribution;The utility model not only transports installation facility, capacity is adjustable, has saved cost of manufacture, and the intensity of stack shell is considerably increased by anchor ear and reinforcement, using safer.

Description

A kind of powder barrel-bin
Technical field
The utility model is related to engineering construction field, refers in particular to a kind of powder barrel-bin.
Background technology
Current powder barrel-bin is made of welding, because powder barrel-bin volume is big, be difficult transport, cause powder barrel-bin from Initial parts must all be carried out to the manufacturing process of finished product in user job site, increased cost of transportation;Such as prior art A kind of powder barrel-bin is disclosed in 201120553383.7, is that the stack shell includes multiple shell rings, the cylinder with conventional differentiation Section is connected between the adjacent shell ring in cylinder by fastener, and fastener is the T-shaped flange in cross section, this knot Although structure is easily installed and transports, but intensity is relatively low, easy radial deformation after stack shell stress, dangerous higher.
Utility model content
The utility model purpose is provided one kind and is easily installed and transports to overcome the deficiencies in the prior art, and intensity Powder barrel-bin higher.
To reach above-mentioned purpose, the technical solution adopted in the utility model is:A kind of powder barrel-bin, comprising support, auger, Conelet, stack shell, Cang Gai, cat ladder, top guardrail and feed pipe;The auger and conelet are located at stack shell lower end to constitute discharging opening, The branch is set up in stack shell lower section to support stack shell, the Cang Gai and top guardrail to be located at stack shell upper end, the cat ladder and charging Pipe is located at stack shell and support side;The stack shell includes multiple shell rings in cylinder, and by connecting between the adjacent shell ring Fitting is connected;The branch that the connector includes annular slab, the anchor ear being arranged on the outside of annular slab, is arranged on annular slab middle inside Fagging;The upper and lower ends of the annular slab are respectively arranged with multiple first connecting holes;The shell ring is respectively arranged at two ends with multiple Second connecting hole, the first connecting hole of the second connecting hole of the adjacent shell ring respectively with annular slab two ends is tight by bolt and nut It is solidly connected.
Preferably, the anchor ear and supporting plate are fixed by welding on annular slab.
Preferably, it is strip after the annular slab launches, flange is provided with from beginning to end, flange is connected by bolt and nut Constitute.
Preferably, the Cang Gai and auger are connected by connector and adjacent shell ring respectively, wherein be connected with auger Shell ring surface is additionally provided with many reinforcements of even circumferential distribution.
Preferably, it is additionally provided with sealing strip between the shell ring and annular slab;The sealing strip outer application has neutral silicone Fluid sealant.
Preferably, the storehouse covers and is provided with dust arrester.
Preferably, it is additionally provided with rainhat on the outside of the conelet.
Due to the utilization of above-mentioned technical proposal, the utility model has following advantages compared with prior art:
Powder barrel-bin described in the utility model not only transports installation facility, capacity is adjustable, has saved cost of manufacture, and logical Cross anchor ear and reinforcement considerably increases the intensity of stack shell, using safer.
Brief description of the drawings
Technical solutions of the utility model are described further below in conjunction with the accompanying drawings:
Accompanying drawing 1 is the structural representation of powder barrel-bin described in the utility model;
Accompanying drawing 2 is the schematic cross-section of connector in powder barrel-bin described in the utility model.
Wherein:1st, conelet;2nd, support;3rd, rainhat;4th, auger;5th, reinforcement;6th, connector;61st, anchor ear;62nd, flange; 63rd, annular slab;64th, supporting plate;65th, sealing strip;7th, shell ring;8th, Cang Gai;9th, top guardrail;10th, dust arrester;11st, cat ladder.
Specific embodiment
Below in conjunction with the accompanying drawings and specific embodiment the utility model is described in further detail.
Accompanying drawing 1-2 is powder barrel-bin described in the utility model, comprising support 2, auger 4, conelet 1, stack shell, storehouse lid 8, is climbed Ladder 11, top guardrail 9 and feed pipe;The auger 4 and conelet 1 are connected with each other located at stack shell lower end to constitute discharging opening, described , located at stack shell lower section to support stack shell, the storehouse lid 8 and top guardrail 9 are located at stack shell upper end, the cat ladder 11 and charging for support 2 Pipe is located at stack shell and the side of support 2;The stack shell includes multiple shell rings 7 in cylinder, and passes through between the adjacent shell ring 7 Connector 6 is connected;The connector 6 includes annular slab 63, the anchor ear 61 being arranged on the outside of annular slab 63, is arranged on annular slab 63 The supporting plate 64 of middle inside, wherein supporting plate 64 play positioning and supporting role, are easy to annular slab 63 to be connected with shell ring 7, and Anchor ear 61 plays booster action, prevents radial deformation after the junction stress of adjacent cylindrical section 7, and improve third dimension;The ring The upper and lower ends of shape plate 63 are respectively arranged with multiple first connecting holes;The multiple second that is respectively arranged at two ends with of the shell ring 7 is connected Hole, the second connecting hole of the adjacent shell ring 7 is fastened by bolt and nut with first connecting hole at the two ends of annular slab 63 connect respectively Connect;The anchor ear 61 and supporting plate 64 are fixed by welding on annular slab 63;The annular slab 63 is strip after launching, Head and the tail are provided with flange 62, and connecting flange 62 by bolt and nut is constituted;The storehouse lid 8 and auger 4 pass through connector 6 respectively Connected with adjacent shell ring 7, wherein the surface of shell ring 7 being connected with auger 4 is provided with many reinforcements 5 of even circumferential distribution, Because last stress of shell ring 7 is maximum, stiffening effect can be played by reinforcement 5, increase stability;The shell ring 7 and ring Sealing strip 65 is additionally provided between shape plate 63;The outer application of the sealing strip 65 has sealing neutral silicone resin;Set on the storehouse lid 8 There is dust arrester 10, it is to avoid powder barrel-bin produces dust in feed supplement, influence air quality, and play effect of easing stress;It is described small The outside of cone 1 is additionally provided with rainhat 3, prevents rainwater from entering discharging opening, and the raw material with discharge outlet reacts, and influences matter Amount.
Due to the utilization of above-mentioned technical proposal, the utility model has following advantages compared with prior art:
Powder barrel-bin described in the utility model not only transports installation facility, capacity is adjustable, has saved cost of manufacture, and logical Cross anchor ear and reinforcement considerably increases the intensity of stack shell, using safer.
The above is only concrete application example of the present utility model, any limit is not constituted to protection domain of the present utility model System.All use equivalents or equivalence replacement and the technical scheme that is formed, all fall within the utility model rights protection scope it It is interior.

Claims (7)

1. a kind of powder barrel-bin, comprising support, auger, conelet, stack shell, Cang Gai, cat ladder, top guardrail and feed pipe;It is described big , located at stack shell lower end to constitute discharging opening, the branch is set up in stack shell lower section to support stack shell, the Cang Gai and top for cone and conelet Portion's guardrail is located at stack shell upper end, and the cat ladder and feed pipe are located at stack shell and support side;The stack shell includes that multiple is in cylinder Connected by connector between the shell ring of shape, and the adjacent shell ring;Characterized in that, the connector includes annular slab, sets Put the anchor ear on the outside of annular slab, be arranged on the supporting plate of annular slab middle inside;The upper and lower ends of the annular slab set respectively It is equipped with multiple first connecting holes;The shell ring is respectively arranged at two ends with multiple second connecting holes, the second company of the adjacent shell ring Hole is connect to be fastenedly connected by bolt and nut with first connecting hole at annular slab two ends respectively.
2. powder barrel-bin according to claim 1, it is characterised in that:The anchor ear and supporting plate are fixed by welding in On annular slab.
3. powder barrel-bin according to claim 1 and 2, it is characterised in that:The annular slab is strip, head and the tail after launching Flange is provided with, connecting flange by bolt and nut is constituted.
4. powder barrel-bin according to claim 1, it is characterised in that:The Cang Gai and auger pass through connector and phase respectively Adjacent shell ring connection, wherein the shell ring surface being connected with auger is additionally provided with many reinforcements of even circumferential distribution.
5. powder barrel-bin according to claim 1, it is characterised in that:Sealing is additionally provided between the shell ring and annular slab Bar;The sealing strip outer application has sealing neutral silicone resin.
6. powder barrel-bin according to claim 1, it is characterised in that:The storehouse covers and is provided with dust arrester.
7. powder barrel-bin according to claim 1, it is characterised in that:Rainhat is additionally provided with the outside of the conelet.
CN201621375193.XU 2016-12-15 2016-12-15 A kind of powder barrel-bin Expired - Fee Related CN206278525U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621375193.XU CN206278525U (en) 2016-12-15 2016-12-15 A kind of powder barrel-bin

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621375193.XU CN206278525U (en) 2016-12-15 2016-12-15 A kind of powder barrel-bin

Publications (1)

Publication Number Publication Date
CN206278525U true CN206278525U (en) 2017-06-27

Family

ID=59072490

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621375193.XU Expired - Fee Related CN206278525U (en) 2016-12-15 2016-12-15 A kind of powder barrel-bin

Country Status (1)

Country Link
CN (1) CN206278525U (en)

Similar Documents

Publication Publication Date Title
CN201326524Y (en) Composite tower cylinder of wind turbine
CN204852660U (en) Compound pipe of fiber crops winding
CN106640545B (en) Transition connecting piece, concrete tower and concrete tower construction method
CN104164996A (en) Protection-layer-free concrete electric pole and manufacturing method thereof
CN202625924U (en) High-compression-resistance intensive integral septic tank mold with wave crest structural wall
CN206278525U (en) A kind of powder barrel-bin
CN104339455A (en) Novel dry-mixed mortar material storage tank
CN110761954B (en) Precast concrete fan tower barrel with spiral line connecting seam and connecting method
CN201882475U (en) Powder silo
CN201738569U (en) Placing die for coal tower hopper wall
CN101838091A (en) FRP (Fiber Reinforced Plastic) purification can
CN2937361Y (en) Oil storage depot
CN205806716U (en) The box-like steel-plastics composite pipe of Jinsuo in a kind of
CN202379303U (en) Powder silo
CN209568532U (en) A kind of integrated composite pumping plant
CN201478771U (en) Sealing device of cable pipeline
CN205872916U (en) Concatenation formula cement jar
CN105927025A (en) Electric pole
CN206385800U (en) A kind of cylindrical concrete groove tank body
CN201704953U (en) Shear wall water stop screw stem
CN206747042U (en) Mine distributor and tailings recovery device
CN2923586Y (en) Combined internal floating plate for store pot
CN205618307U (en) Connection structure between a concrete tower section of thick bamboo and head tower section of thick bamboo
CN205127658U (en) Pottery desulfurizing tower with novel support that sprays
CN214166031U (en) Combined split type cement bin

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170627

Termination date: 20211215

CF01 Termination of patent right due to non-payment of annual fee