CN206233258U - A kind of Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge - Google Patents

A kind of Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge Download PDF

Info

Publication number
CN206233258U
CN206233258U CN201620903099.0U CN201620903099U CN206233258U CN 206233258 U CN206233258 U CN 206233258U CN 201620903099 U CN201620903099 U CN 201620903099U CN 206233258 U CN206233258 U CN 206233258U
Authority
CN
China
Prior art keywords
wall
suspension bridge
diaphram wall
pear
diaphram
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620903099.0U
Other languages
Chinese (zh)
Inventor
胡建华
刘榕
梁振西
李瑜
崔剑峰
贺耀北
邹德强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Provincial Communications Planning Survey and Design Institute Co Ltd
Original Assignee
HUNAN COMMUNICATION PLANNING AND PROSPECTING DESIGN ACADEMY
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUNAN COMMUNICATION PLANNING AND PROSPECTING DESIGN ACADEMY filed Critical HUNAN COMMUNICATION PLANNING AND PROSPECTING DESIGN ACADEMY
Priority to CN201620903099.0U priority Critical patent/CN206233258U/en
Application granted granted Critical
Publication of CN206233258U publication Critical patent/CN206233258U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model is a kind of Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge, it is related to building field, to solve diaphram wall Anchor Foundation structural strength of the prior art, poor durability, stress is unreasonable, long construction period, and construction cost problem high and design.The Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge includes anchorage and diaphram wall, anchorage is the integrative-structure of concreting with diaphram wall, diaphram wall includes the first diaphragm wall and the second diaphragm wall, first diaphragm wall and the second diaphragm wall are curved wall, both intersections are provided with the top of mid-board, and the first diaphragm wall, the second diaphragm wall and mid-board and are provided with cap.The utility model provide be applied to suspension bridge Pear-Shaped diaphram wall Anchor Foundation excavated volume it is small, structural strength is big, durability is high, short construction period and building cost are low.

Description

A kind of Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge
Technical field
The utility model is related to building field, more particularly to the Pear-Shaped diaphram wall anchorage base for being applied to suspension bridge Plinth.
Background technology
With social economy with science and technology development of going forward side by side, all kinds of bridge constructions rise abruptly and rise, in the same of a large amount of bridge constructions When, people also increasingly pay close attention to the quality and economy of bridge.For a long time, accounted in highway in China bridge it is most of in, Small bridge is prestressed concrete bridge.Due to reasons such as design concept, quality control on construction, beam bridge generally existing foundation ditch change The problems such as shape, crater wall unstability, antiseepage or precipitation fail, not only builds itself to baffle and bring hidden danger to bridge security operation, and Cause a large amount of surrounding enviroment problems.
Diaphram wall Anchor Foundation is made up of anchorage and diaphram wall.Anchorage is the important of suspension bridge anchoring main push-towing rope Works, it passes through main push-towing rope anchor system and tension of main cable is passed into anchor block, then that load is transferred into underground by anchor block is continuous Wall Anchor Foundation, so as to play the anchorage effect of balance tension of main cable.
Diaphram wall Anchor Foundation of the prior art, though possess the advantage of above-mentioned diaphram wall Anchor Foundation, There is big diaphram wall Anchor Foundation excavated volume, structural strength, poor durability, unreasonable stress, long construction period and building The problem of high cost.
Utility model content
The purpose of this utility model is to provide a kind of Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge, with Diaphram wall Anchor Foundation structural strength of the prior art, poor durability are solved, stress is unreasonable, long construction period, and Construction cost problem high.
The utility model is a kind of Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge, including anchorage and underground Diaphragm wall, the anchorage is the integrative-structure of concreting with the diaphram wall;
The diaphram wall includes the first diaphragm wall and the second diaphragm wall, first diaphragm wall and described second continuous Wall is curved wall, and both intersections are provided with mid-board, and first diaphragm wall, second diaphragm wall and the mid-board Top be provided with cap.
Further, the cap includes the first cap and the second cap;
First cap is " L " ellbeam, and second cap is " recessed " word beam.
Further, first diaphragm wall is two radiuses not grade and circle for intersecting with second diaphragm wall, point Wei not great circle wall and roundlet wall.
Further, the great circle diaphram wall and the roundlet diaphram wall are equipped with base plate, it is described it is big circularly Lower diaphragm wall top is provided with anchorage.
Further, the diaphram wall is provided with top board, and the top board is provided with bar-mat reinforcement.
Further, the diaphram wall is provided with inwall.
Further, the great circle is provided with fills out core within the walls.
Further, the roundlet is provided with concrete compartment within the walls.
The beneficial effects of the utility model are:
What the utility model was provided is applied in the Pear-Shaped diaphram wall Anchor Foundation of suspension bridge, including anchorage and ground Lower diaphragm wall, diaphram wall includes the first diaphragm wall and the second diaphragm wall, and cap is provided with the top of diaphram wall.Cap Refer to be arranged on the reinforced concrete continuous beam at the top of the supporting construction of foundation ditch periphery.Cap preferably can connect all of pile foundation To together, making cantilever pile body form elastic restraint in pile crown, pile body horizontal rigidity is increased, and then prevent foundation ditch top edge from producing Cave in.In addition, the level that cap can also undertake bracing members or reinforced concrete support by bracket bears against power and vertically cuts Power, stiffener drag and deformability in the horizontal direction.
Anchorage is the important feature thing that suspension bridge anchors main push-towing rope, and anchorage can preferably pass through suspension bridge anchor system will be main Cable pulling force passes to anchor block, then load is transferred into Anchor Foundation by anchor block, and the gravity offer of anchorage and Anchor Foundation is enough Big resistance prevents Construction of Pylon of Long Span Suspension Bridge from inclining or even collapsing to balance the huge pulling force of pontic main push-towing rope, so as to play balance master The anchorage effect of cable pulling force, is the important bearing system of whole suspension bridge.Anchorage is the one of concreting with diaphram wall Body structure can improve the overall construction intensity and durability of foundation.
In addition, diaphram wall is to build up continuous reinforcing bar together in underground using a kind of trench machine on the ground The foundation engineering of concrete wall.Diaphram wall has efficiency of construction high, short construction period, building cost low and construction quality High the characteristics of.Also have simultaneously when taking up an area less, constructing and vibrate the advantage that small, noise is low, barrier performance is good.
While with These characteristics, its structure is also using specific to dome-shaped supporting construction for arc diaphram wall The advantage of the pressure of " arching " resistance ambient water local products life.The outer Water And Earth Pressures in hole are greatly by the circumference stress of ground-connecting-wall Balance, shearing force is substantially close with moment of flexure, substantially reduces the vertical moment of flexure of wall such that it is able to it is preferable make diaphram wall by Reduce in the horizontal displacement caused by curved, the demand for making the structure stress requirement of deep foundation construction actual with construction is expired Foot.First diaphragm wall and the second diaphragm wall intersection are provided with mid-board, and mid-board preferably meets diaphram wall point of intersection Stress needs, it is possible to increase the overall intensity of diaphram wall and stress performance, further improves the diaphram wall anchorage base The rigidity and durability of plinth.
The utility model also provides a kind of the outstanding of Pear-Shaped diaphram wall Anchor Foundation that suspension bridge is applied to this Cable bridge.
Further, the suspension bridge includes main push-towing rope, and the anchoring body is provided with preceding anchor room, rear anchor room and saddle room, the saddle Room is provided with scattered cable saddle, and the main push-towing rope is scattered by the scattered cable saddle and is connected with the rear anchor room, the scattered cable saddle and the preceding anchor Room connects, and the rear anchor room is connected with the diaphram wall.
The beneficial effects of the utility model:
The suspension bridge is with the above-mentioned Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge relative to prior art institute Have the advantage that identical, here is omitted.
Brief description of the drawings
In order to illustrate more clearly of the utility model specific embodiment or technical scheme of the prior art, below will be right The accompanying drawing to be used needed for specific embodiment or description of the prior art is briefly described, it should be apparent that, describe below In accompanying drawing be some implementation methods of the present utility model, for those of ordinary skill in the art, do not paying creativeness On the premise of work, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is the structural representation of the present embodiment diaphram wall Anchor Foundation;
Fig. 2 is the structural representation of Fig. 1 anchorages;
Fig. 3 is the structural representation of Fig. 1 diaphram walls;
Fig. 4 is the floor map of Fig. 1 diaphram walls;
Fig. 5 is a kind of structural representation of Fig. 1 caps;
Fig. 6 is another structural representation of Fig. 1 caps.
Reference:
1- anchorage 2- cap 3- great circle walls
4- roundlet wall 5- mid-board 6- base plates
7- top board 8- bar-mat reinforcement 9- inwalls
Anchor room before 10- main push-towing rope 11- anchor blocks 12-
14- saddles room 140- in anchor room dissipates cable saddle after 13-
21- " L " ellbeam 22- " recessed " word beams 31- fills out core
41- compartments
Specific embodiment
It is new to this practicality below in conjunction with accompanying drawing to make the purpose of this utility model, technical scheme and advantage clearer The technical scheme of type carries out clear, complete description.Obviously, described embodiment is only that a part of the present utility model is implemented Example, rather than whole embodiments.Based on the embodiment in the utility model, those of ordinary skill in the art are not making wound The every other embodiment obtained under the premise of the property made work, belongs to the scope of the utility model protection.
It is term " " center ", " on ", D score, "left", "right", " perpendicular, it is necessary to explanation in description of the present utility model Directly ", the orientation or position relationship of the instruction such as " level ", " interior ", " outward " are, based on orientation shown in the drawings or position relationship, to be only Described with simplified for the ease of description the utility model, must had rather than the device or element for indicating or implying meaning specific Orientation, with specific azimuth configuration and operation, therefore it is not intended that to limitation of the present utility model.Additionally, term " the One ", " second ", " the 3rd " are only used for describing purpose, and it is not intended that indicating or implying relative importance.
, it is necessary to explanation, unless otherwise clearly defined and limited, term " is pacified in description of the present utility model Dress ", " connected ", " connection " should be interpreted broadly, for example, it may be fixedly connected, or be detachably connected, or one Connection;Can mechanically connect, or electrically connect;Can be joined directly together, it is also possible to be indirectly connected to by intermediary, Can be two connections of element internal.For the ordinary skill in the art, above-mentioned art can be understood with regard to body situation Concrete meaning of the language in the utility model.
Embodiment one
As shown in figs 1 to 6, it is a kind of Pear-Shaped diaphram wall anchorage base for being applied to suspension bridge that the present embodiment is provided Plinth, including anchorage 1 and diaphram wall.
Anchorage 1 is the integrative-structure of concreting with diaphram wall.
Specifically, diaphram wall includes the first diaphragm wall and the second diaphragm wall, and diaphram wall top is provided with cap 2。
In the Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge of the present embodiment, including anchorage 1 and underground Diaphragm wall, diaphram wall includes the first diaphragm wall and the second diaphragm wall, and cap 2 is provided with the top of diaphram wall.Cap 2 Refer to be arranged on the reinforced concrete continuous beam at the top of foundation ditch diaphram wall.Cap 2 preferably can connect all of pile foundation To together, making cantilever pile body form elastic restraint in pile crown, pile body horizontal rigidity is increased, and then prevent foundation ditch top edge from producing Cave in.In addition, the level that cap 2 can also undertake bracing members or reinforced concrete support by bracket bears against power and vertically cuts Power, stiffener drag and deformability in the horizontal direction.
Anchorage 1 is the important feature thing that suspension bridge anchors main push-towing rope 10, and anchorage 1 can preferably pass through suspension bridge anchor system The pulling force of main push-towing rope 10 is passed into anchor block, then load is transferred to by Anchor Foundation by anchor block, the gravity of anchorage 1 and Anchor Foundation is carried For sufficiently large resistance to balance the huge pulling force of pontic main push-towing rope 10, prevent Construction of Pylon of Long Span Suspension Bridge from inclining or even collapsing, so as to rise It is the important bearing system of whole suspension bridge to the anchorage effect of the balance pulling force of main push-towing rope 10.Anchorage 1 is coagulation with diaphram wall The integrative-structure that soil is poured can improve the overall construction intensity and durability of foundation.
In addition, diaphram wall is to build up continuous reinforcing bar together in underground using a kind of trench machine on the ground The foundation engineering of concrete wall.Diaphram wall has efficiency of construction high, short construction period, building cost low and construction quality High the characteristics of.Also have simultaneously and take up an area few, vibrate small during construction, noise is low, the good advantage of barrier performance.
While with These characteristics, its structure is also using specific to dome-shaped supporting construction for arc diaphram wall The advantage of the pressure of " arching " resistance ambient water local products life.The outer Water And Earth Pressures in hole are greatly by the circumference stress of ground-connecting-wall Balance, shearing force is substantially close with moment of flexure, substantially reduces the vertical moment of flexure of wall such that it is able to it is preferable make diaphram wall by Reduce in the horizontal displacement caused by curved, the demand for making the structure stress requirement of deep foundation construction actual with construction is expired Foot.First diaphragm wall and the second diaphragm wall intersection are provided with mid-board 5, and mid-board 5 preferably meets diaphram wall point of intersection Stress need, it is possible to increase the overall intensity of diaphram wall and stress performance, further improve the diaphram wall anchorage The rigidity and durability on basis.
As shown in Figure 5, Figure 6, wherein, cap 2 include the first cap and the second cap.In the present embodiment, underground is continuous The cap 2 at wall two ends sets the first cap, and the first cap is " L " ellbeam 21, and the cap 2 of mid-board 5 sets the second cap, second Cap is " recessed " word beam 22, and cap 2 poured with diaphram wall and first liner respectively it is integral.The diaphram wall " L " ellbeam 21 of Anchor Foundation and " recessed " word beam 22 are trough girder, trough girder has that construction weight is small, building height is low, every Good, system integration effect is good for audio fruit, traffic safety, space section utilization rate high, good appearance the features such as.Trough girder not only subtracts Lacked concrete amount, also make in the center of gravity of structure move, eliminate it is whole to prestress system, using horizontal and vertical prestressing force body System, increases prestressing force bias, reduces the consumption of prestressed strand.
As shown in Figure 3, Figure 4, specifically, the first diaphragm wall and the second diaphragm wall are two radiuses not grade and circle for intersecting, First diaphragm wall is great circle wall 3, and second diaphragm wall is roundlet wall 4.
In the middle of practice of construction, the pressure that diaphram wall is given birth to due to ambient water local products, its radially meeting occurred level displacement, and Horizontal displacement can increase with the increase of cutting depth.In the present embodiment, Pear-Shaped continuous underground wall structure utilizes circular arch The pressure of specific " arching " resistance ambient water local products life of shape supporting construction, its feature has been clearly stated above, this Place repeats no more.In addition to These characteristics, circular diaphragm wall also has smaller, and materials are less, with obvious economy Benefit, and more broad excavation space can be provided, facilitate mechanical execution, operating efficiency is improved, save the advantage of duration.
As shown in Figure 1, Figure 3, wherein, great circle wall 3 in the present embodiment is equipped with base plate 6, great circle wall 3 with roundlet wall 4 Top is provided with anchor block 11.Diaphram wall base plate 6 is subject to the working position of positive hogging moment, and diaphram wall base plate 6 also has Prevent groundwater infiltration.Anchor block 11 is the important component of external prestressing anchor system, and external prestressing relies on anchor block The pulling force of Construction of Pylon of Long Span Suspension Bridge is reached the diaphram wall Anchor Foundation by 11 anchoring power transmissions, prevents the inclination of Construction of Pylon of Long Span Suspension Bridge even Collapse.
Herein it should be added that, base plate 6 can be needed using stepped according to foundation ditch scar version and stress Arrangement, or uniform thickness arrangement.In addition, the anchor type of anchorage 1 is divided into rock bolting and is anchored with soil layer.Specifically, anchorage 1 exists Loading characteristic and corresponding requirements are different during construction and operation.To soil layer anchor foundation, it is in construction period major influence factors The vertical gravity of anchor foundation itself, now, should ensure that foundation bearing capacity and settlement request;During runing, except above-mentioned factor, also Will be subject to main push-towing rope 10 pulling force, now also need emphasis ensure anchorage 1 will not occurred level sliding and topple, i.e., should meet stability Condition.Meanwhile, during runing, also need the sedimentation on basis and control of horizontal displacement in permissible range.To make anchorage 1 have foot Enough securities, it will usually Anchor Foundation is placed on basement rock or well-behaved soil layer as far as possible.
Wherein, the top of roundlet wall 4 is provided with certain thickness and the top board 7 for distributing the pressure of top anchorage 1, top board 7 It is provided with bar-mat reinforcement 8.In the present embodiment, diaphram wall top board 7 is also subject to the working position of positive and negative moment of flexure, specifically, Top board 7 is provided with bar-mat reinforcement 8, and bar-mat reinforcement 8 is built into the longitudinal prestressing system and transverse prestress system of bridge, can be more preferable Raising bridge overall intensity, further reduce even avoid the occurrence of being ftractureed at joint of bridge.
As shown in figure 3, wherein, diaphram wall inner side in the present embodiment is provided with certain thickness inwall 9.Liner Wall 9 is built again inside diaphram wall stifled brick wall or reinforced concrete wall, can be further intentinonally lower continuous The hoop rigidity of wall, improves the water proofing property of diaphram wall.
Herein it should be added that, inwall uses reverse construction, i.e., often excavate a layer soil body from top to down, if One inwall is put, further to strengthen the hoop rigidity of diaphram wall, inwall layering is set, per layer height with every layer of soil Body excavation height is adapted, and the thickness of inwall can be according to the difference of excavation of foundation pit depth, and its thickness can be in the side of ladder Formula is set, it would however also be possible to employ the mode of uniform thickness is set.
As shown in figure 4, therein, the anchor block 11 of great circle wall 3 of the diaphram wall Anchor Foundation has fills out core 31.At this In embodiment, core 31 is filled out for concrete, due to the pulling force of the recipient's main rope of suspension bridge 10 of great circle wall 3, to ensure suspension bridge entirety Security and the diaphram wall Anchor Foundation the scientific and reasonable purpose of load, fill out core 31 in the ground of great circle wall 3 Concrete, filling out the concrete of core 31 preferably so that great circle wall 3 bears the pulling force of main push-towing rope 10 can prevent suspension bridge pontic from inclining very To collapsing.
Wherein, concrete compartment 41 is had in the top board 7 of diaphram wall Anchor Foundation roundlet wall 4.In the present embodiment In, roundlet wall 4 is with respect to the mainly fixed scattered cable saddle crossbeam of great circle wall 3, i.e., smaller with respect to the counterweight of great circle wall 3, therefore in concrete Sandy soil or water are filled up in compartment 41, counterweight is scientific and reasonable, reduce building cost.
Herein it should be added that, concrete in the present embodiment can select modified active powder concrete. Modified active powder concrete is primarily referred to as in RPC mixed with different size and/or the high-strength steel flat flanges of profile. Modified active powder concrete has compression strength and shearing strength very high, and thinner section can be used in structure design Or the cross sectional shape with novelty, so that dead load is more light than normal concrete structure.Meanwhile, modified active powder Last concrete effectively reduces the thickness and scope of building transition region.Its porosity is extremely low, is not only able to prevent radioactive material Matter can resist the corrosion of outside corrosive medium from internal leakage, improve on the whole system uniformity, intensity and Durability, improves bridge overall shock resistance and impact resistance, and then reduces or even avoid maintenance cost, extends and uses Life-span.In addition, the building built using modified active powder concrete even can also avoid using reinforcing bar from reducing, Further reduce the building cost of bridge.
Embodiment two
The present embodiment provides a kind of continuous with a kind of described Pear-Shaped underground for being applied to suspension bridge of above-described embodiment The suspension bridge of wall Anchor Foundation.
In the present embodiment, the suspension bridge has the Pear-Shaped diaphram wall anchor for being applied to suspension bridge in embodiment one All features on heavy stone used as an anchor basis, here is omitted.
As Figure 1-Figure 2, wherein, the suspension bridge includes main push-towing rope 10, and anchorage 1 is provided with preceding anchor room 12, rear anchor room 13 and saddle Room 14, saddle room 14 is provided with scattered cable saddle 140, and main push-towing rope 10 is scattered by dissipating cable saddle 140 and is connected with rear anchor room 13, dissipate cable saddle 140 with it is preceding Anchor room 12 connects, and rear anchor room 13 is connected with diaphram wall.
In the present embodiment, saddle room 14 can preferably accommodate main push-towing rope 10, and there is enough length can make main push-towing rope 10 for it Scatter anchoring.Preceding anchor room 12 and saddle room 14 constitute the protection such as the anchor system of anchorage 1, main push-towing rope 10 and scattered cable saddle 140, safeguard simultaneously Space.The space that anchor room 13 can provide to carry out the protection of the anchor system of anchorage 1, safeguard afterwards, the preferably anchorage 1 of protection suspension bridge Anchor system, and the pulling force of main rope of suspension bridge 10 is preferably reached into the diaphram wall Anchor Foundation.
Finally it should be noted that:Various embodiments above is only used to illustrate the technical solution of the utility model, rather than it is limited System;Although being described in detail to the utility model with reference to foregoing embodiments, one of ordinary skill in the art should Understand:It can still modify to the technical scheme described in foregoing embodiments, or to which part or whole Technical characteristic carries out equivalent;And these modifications or replacement, the essence of appropriate technical solution is departed from this practicality newly The scope of each embodiment technical scheme of type.

Claims (8)

1. a kind of Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge, it is characterised in that including anchorage (1) and underground Diaphragm wall, the anchorage (1) is the integrative-structure of concreting with the diaphram wall;
The diaphram wall includes the first diaphragm wall and the second diaphragm wall, and first diaphragm wall and second diaphragm wall are equal It is curved wall, both intersections are provided with mid-board (5), and first diaphragm wall, second diaphragm wall and the mid-board Top be provided with cap (2).
2. the Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge according to claim 1, it is characterised in that institute Stating cap (2) includes the first cap and the second cap;
First cap is " L " ellbeam (21), and second cap is " recessed " word beam (22).
3. the Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge according to claim 1, it is characterised in that institute It is two radiuses not grade and circle for intersecting, respectively great circle wall and roundlet wall that the first diaphragm wall is stated with second diaphragm wall.
4. the Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge according to claim 3, it is characterised in that institute State great circle wall (3) and be equipped with base plate (6) with the roundlet wall (4), great circle wall (3) top is provided with anchor block (11).
5. the Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge according to claim 4, it is characterised in that institute State diaphram wall and be provided with top board (7), the top board (7) is provided with bar-mat reinforcement (8).
6. the Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge according to claim any one of 3-5, it is special Levy and be, the diaphram wall is provided with inwall (9).
7. the Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge according to claim 4, it is characterised in that institute State to be provided with great circle wall (3) and fill out core (31).
8. the Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge according to claim 5, it is characterised in that institute State in roundlet wall (4) and be provided with concrete compartment (41).
CN201620903099.0U 2016-08-18 2016-08-18 A kind of Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge Active CN206233258U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620903099.0U CN206233258U (en) 2016-08-18 2016-08-18 A kind of Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620903099.0U CN206233258U (en) 2016-08-18 2016-08-18 A kind of Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge

Publications (1)

Publication Number Publication Date
CN206233258U true CN206233258U (en) 2017-06-09

Family

ID=58986248

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620903099.0U Active CN206233258U (en) 2016-08-18 2016-08-18 A kind of Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge

Country Status (1)

Country Link
CN (1) CN206233258U (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107988906A (en) * 2017-12-12 2018-05-04 中交公局第二工程有限公司 A kind of high intensity anchorage
CN108049313A (en) * 2017-12-12 2018-05-18 中交公局第二工程有限公司 A kind of anchor body construction method
CN108252214A (en) * 2017-12-12 2018-07-06 中交公局第二工程有限公司 A kind of anchorage construction method
CN109930485A (en) * 2019-01-21 2019-06-25 中交公路长大桥建设国家工程研究中心有限公司 A kind of design method on ground-connecting-wall gravity type Compound Anchorage basis
CN111119221A (en) * 2020-01-17 2020-05-08 东南大学 Shallow buried anchorage foundation base anti-sliding device, size determination method and construction method
CN111501548A (en) * 2020-04-22 2020-08-07 中交一公局集团有限公司 Anchor block structure and construction method thereof
CN112049009A (en) * 2020-08-13 2020-12-08 中铁大桥勘测设计院集团有限公司 Shallow formula raft type anchorage that buries
CN113006113A (en) * 2021-03-04 2021-06-22 浙江大学 Composite anchorage foundation of enlarged-diameter steel pipe pile of underground diaphragm wall and construction method of composite anchorage foundation

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107988906A (en) * 2017-12-12 2018-05-04 中交公局第二工程有限公司 A kind of high intensity anchorage
CN108049313A (en) * 2017-12-12 2018-05-18 中交公局第二工程有限公司 A kind of anchor body construction method
CN108252214A (en) * 2017-12-12 2018-07-06 中交公局第二工程有限公司 A kind of anchorage construction method
CN109930485A (en) * 2019-01-21 2019-06-25 中交公路长大桥建设国家工程研究中心有限公司 A kind of design method on ground-connecting-wall gravity type Compound Anchorage basis
CN111119221A (en) * 2020-01-17 2020-05-08 东南大学 Shallow buried anchorage foundation base anti-sliding device, size determination method and construction method
CN111501548A (en) * 2020-04-22 2020-08-07 中交一公局集团有限公司 Anchor block structure and construction method thereof
CN111501548B (en) * 2020-04-22 2021-11-19 中交一公局集团有限公司 Anchor block structure and construction method thereof
CN112049009A (en) * 2020-08-13 2020-12-08 中铁大桥勘测设计院集团有限公司 Shallow formula raft type anchorage that buries
CN113006113A (en) * 2021-03-04 2021-06-22 浙江大学 Composite anchorage foundation of enlarged-diameter steel pipe pile of underground diaphragm wall and construction method of composite anchorage foundation
CN113006113B (en) * 2021-03-04 2022-05-06 浙江大学 Composite anchorage foundation of enlarged-diameter steel pipe pile of underground diaphragm wall and construction method of composite anchorage foundation

Similar Documents

Publication Publication Date Title
CN206233258U (en) A kind of Pear-Shaped diaphram wall Anchor Foundation for being applied to suspension bridge
CN203782684U (en) Anti-skid pile provided with crossbeam
CN103485363A (en) Three-dimensional continuous frame type reinforced concrete structure retaining wall
CN102653945A (en) Foundation reinforcing and replacing structure and construction method thereof
CN104652475A (en) Truss type retaining wall
CN107119699A (en) A kind of friction pile and its construction method based on the beam of uniform strength
CN106522292A (en) Grouting combined prestressed anchor rod static pressure pile rectification and reinforcement method
CN106869138A (en) A kind of load retaining wall Retaining Structure with Double-row Piles and its foundation ditch excavation method
CN110004973B (en) Landslide prevention protection retaining wall
CN107237343A (en) A kind of many wall type nodular diaphragm walls as bridge foundation for soft soil foundation
CN101498133B (en) Method and supporting construction for enlarging basement top-down method earth excavation space
CN204919602U (en) Compound anchored retaining wall by tie rods
CN213448541U (en) Arch bridge foundation of limestone foundation under deep round gravel layer
CN210766863U (en) Multi-arch rib anchoring plate retaining wall
CN111485571A (en) Arch bridge foundation of limestone foundation under deep round gravel layer and construction method thereof
CN206616602U (en) A kind of outdoor construction elevator strengthening of foundation device
CN109944162A (en) A kind of Combined light anchorage and construction method for large-tonnage Hoisting with Cableway System
CN110485637A (en) A kind of high anti-seismic formula building bar cage of achievable fast pouring
CN203639929U (en) Split open caisson and pile composite anchor foundation
CN212801168U (en) Single-column pier bridge concreties antidumping reinforced structure
CN202064319U (en) Semicircular wave breaker structure
CN110080314B (en) Method for reducing side friction resistance of pile foundation
CN210013239U (en) Prevent landslide protection retaining wall
CN209555962U (en) One kind being suitable for III class stake of cast-in-situ bored pile and cushion cap connection structure
CN208219667U (en) Foundation pit supporting construction based on campshed and inner support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 410000 Hunan province Changsha Kaifu District, Furong Road two No. 158

Co-patentee after: Liang Zhenxi

Patentee after: Hunan Traffic Planning Survey and Design Institute Co Ltd

Address before: 410000 Hunan province Changsha Kaifu District, Furong Road two No. 158

Co-patentee before: Liang Zhenxi

Patentee before: Hunan Communication Planning and Prospecting Design Academy

CP01 Change in the name or title of a patent holder