CN206220594U - A kind of in-site installation steel parking lot - Google Patents

A kind of in-site installation steel parking lot Download PDF

Info

Publication number
CN206220594U
CN206220594U CN201621249570.5U CN201621249570U CN206220594U CN 206220594 U CN206220594 U CN 206220594U CN 201621249570 U CN201621249570 U CN 201621249570U CN 206220594 U CN206220594 U CN 206220594U
Authority
CN
China
Prior art keywords
parking lot
landing
parking
site installation
installation steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621249570.5U
Other languages
Chinese (zh)
Inventor
徐秀龙
高红鹰
徐璐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Glad Logical Naval Architecture And Ocean Engineering In Nantong Design Co Ltd
Original Assignee
Glad Logical Naval Architecture And Ocean Engineering In Nantong Design Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Glad Logical Naval Architecture And Ocean Engineering In Nantong Design Co Ltd filed Critical Glad Logical Naval Architecture And Ocean Engineering In Nantong Design Co Ltd
Priority to CN201621249570.5U priority Critical patent/CN206220594U/en
Application granted granted Critical
Publication of CN206220594U publication Critical patent/CN206220594U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of in-site installation steel parking lot;The technical problem of solution:For the technological deficiency problem that the parking lot of the conventional steel bar concrete structure referred in background technology is present.The technical scheme of use:A kind of in-site installation steel parking lot, including it is horizontally disposed no less than one layer for the landing that parks cars, support is realized by pillar between landing per adjacent levels, automobile climb and fall guidance tape and the upper and lower staircase of personnel are set between the landing per adjacent levels;Landing is made up of the parking deck no less than a piece and is fixedly connected between deck of respectively stopping;Automobile import and export is set on the landing of the bottom, automatic payment machine is set at automobile import and export.Advantage:This parking lot is whole-steel, so that the compact dimensions in parking lot, lightweight, and is easy to build.

Description

A kind of in-site installation steel parking lot
Technical field
The utility model is related to a kind of in-site installation steel parking lot, belongs to parking lot technical field.
Background technology
As the increasingly improvement that people live, family car popularity rate are skyrocketed through, parking problem is caused increasingly to be dashed forward Go out.Particularly residential quarter, Central Shopping area (CBD), hospital, station, airport, scenic spot etc..Therefore, constrain everybody significantly driving The convenience of car trip, on parking problem, the parking facility of China lags far behind the U.S. or European countries.
Traditional parking lot is reinforced concrete structure, or is built on underground or ground, it is necessary to site operation construction, is applying Between the duration, the road on periphery is taken, facility is engaged in the operations such as the transport of construction material, stacking, and time-consuming.In addition, traditional Parking lot is difficult in following enlarging or reconstruction, not to mention resettlement and reuse.
The content of the invention
Technical problem to be solved in the utility model is:For the conventional steel bar concrete structure referred in background technology Parking lot exist technological deficiency problem.
Design philosophy of the present utility model is to provide a kind of use whole-steel and the parking lot for assembling at the scene.
In order to solve the above technical problems, the technical solution adopted in the utility model is:
A kind of in-site installation steel parking lot, including it is horizontally disposed no less than one layer for stopping for parking cars Car platform, support is realized between the landing per adjacent levels by pillar, between the landing per adjacent levels Automobile climb and fall guidance tape and the upper and lower staircase of personnel are set;Landing is made up of and first of respectively stopping the parking deck no less than a piece It is fixedly connected between plate;Automobile import and export is set on the landing of the bottom, automatic payment is set at automobile import and export Machine.
Parking lot in technical solutions of the utility model is whole-steel, so that the compact dimensions in parking lot, lightweight, And be easy to build.Lengthen and increase in the case where former parking lot is unaffected, to increase parking stall.Removing in parking lot Afterwards, still can use.This parking lot can be built in level land, waterborne, mountain valley etc., can be widely applied to house, airport, car Stand, scenic spot nearby etc..
Improvement to technical solutions of the utility model, is fixedly connected between each parking deck using welding manner.This practicality Parking deck in new technique scheme, using steel standard plate in workshop production line balance, can so ensure quality, carry High efficiency.The flow that workshop makes has pretreatment, priming paint, assembly, welding and application etc., it is ensured that quality, can be with streamline Operation, improves efficiency.Scene is arrived into the transport of parking deck, by specific purpose tool, assembled in situ welding, main structural engineering is complete Into.The systems such as illumination, marking signal, cleaning, charging charge, monitoring, charging are installed, you can enable.Parking deck is in workshop system Make, in-site installation greatly shortens the duration.Parking deck can be with production line balance, to ensure Quality advance efficiency.
Further improvement to technical solutions of the utility model, the gradient of automobile climb and fall guidance tape is less than 12.5 °.This parking , being designed using staggered floor, the gradient up and down of vehicle is less than 12.5 degree so that climb and fall is safer.
Further improvement to technical solutions of the utility model, in-site installation steel parking lot also includes Car license recognition Monitoring system and cell phone intelligent charging system.Parking lot is equipped with Intelligent Recognition and Fare Collection System, it is possible to achieve unmanned.Enter one Step, parking lot of the present utility model is equipped with a considerable amount of charging piles, and power supply electrical automobile is used.
Compared with prior art, its advantage is the utility model:
1st, parking lot of the present utility model, parking lot is whole-steel, so that the compact dimensions in parking lot, weight Gently, and be easy to build.
2nd, parking lot of the present utility model, parking lot is designed using staggered floor, and the gradient up and down of vehicle is less than 12.5 Degree so that climb and fall is safer;.
3rd, parking lot of the present utility model, is steel construction parking lot, it is easy to reconstruct, extend, can also entirety strange land Rebuild, building waste will not be produced.
4th, parking lot of the present utility model, uses the slab and girder of pillar support, therefore, parking lot is not necessarily Build level land, it is also possible to build that waterborne, the ground such as between lakeside, mountain valley in.
5th, parking lot of the present utility model, is full steel structure parking lot, for the parking lot for riverside or lakeside, Floating parking lot is can be made into, it is overall in plant construction, it is dragged to destination and installs i.e. usable.
6th, parking lot of the present utility model, using semiclosed design, gravity-flow ventilation is good, therefore does not set force ventilation, Energy-conserving and environment-protective.
7th, parking lot of the present utility model, using high definition Car license recognition monitoring system, adds cell phone intelligent and pays system System, this parking lot can be in principle unmanned parking lot
8th, parking lot of the present utility model, the upper and lower staircase of personnel is designed using standard module, transport to Site Welding Install, for large parking lot, it is also possible to install elevator.
9th, parking lot of the present utility model, the top or bottom that parking lot is imported and exported can serve as other purposes, make This parking lot has multi-functional.
Brief description of the drawings
Fig. 1 is the plan of the utility model individual layer landing.
Fig. 2 is the profile (by taking 5 layers of parking lot as an example) of the utility model parking lot.
In figure:1. landing, 2. pillar, 3. automobile climb and fall guidance tape, the 4. upper and lower staircase of personnel, deck of 5. stopping.
Specific embodiment
Technical solutions of the utility model are described in detail below, but protection domain of the present utility model is not limited to The embodiment.
To make content of the present utility model more obvious understandable, done into one below in conjunction with accompanying drawing 1-2 and specific embodiment The description of step.
In order that the purpose of this utility model, technical scheme and advantage become more apparent, below in conjunction with accompanying drawing and implementation Example, is further elaborated to the utility model.It should be appreciated that specific embodiment described herein is only used to explain this Utility model, is not used to limit the utility model.
Embodiment:The present embodiment is by taking 5 layers of parking lot as an example.
As illustrated in fig. 1 and 2, it is the in-site installation steel parking lot of the present embodiment, including five layers of horizontally disposed use Support is realized by pillar 2 between the landing 1 for parking cars, the landing of every adjacent levels, per adjacent upper and lower Automobile climb and fall guidance tape 3 and personnel's upper and lower staircase 4 are set between the landing of layer;The gradient of automobile climb and fall guidance tape is less than 12.5°.Landing is constituted and respectively fixed using welding manner between parking deck and connected by the parking deck 5 no less than a piece Connect;Automobile import and export is set on the landing of the bottom, automatic payment machine is set at automobile import and export.In-site installation steel Matter parking lot also includes Car license recognition monitoring system and cell phone intelligent charging system.
The Specific construction process of the parking lot of the present embodiment is as follows:
All of material such as steel plate, angle steel and round steel in the present embodiment parking lot, cleaned, derusting by sandblasting, priming paint Drying pretreatment.The cutting of steel plate uses numerical control automatic blanking;Parking deck 5 uses automatically or semi-automatically welds jigsaw;Strengthen Aggregate is installed and is also adopted by automatically or semi-automatically welding;The welding for strengthening panel and the web of girder can use automatic welding, and stop The welding on car deck 5 uses semi-automatic or manual welding.So as to produce the plate of standard, it is suitable for transport, meanwhile, mix standard Hanger, for entrucking, on-site hoisting.
Scene is transported on parking deck 5, and standard plate is lifted on into special cart group (by 2- using truck crane or other instruments 3 dolly compositions) on, can rotate, shift and height regulation.Spot welding is fixed, and parking uses semi-automatic welding, purlin between deck 5 Material is connected and pillar uses manual welding.Cleaned after the completion of welding, polished and repairing paint.
Parking lot agent structure is completed, and installs the upper and lower staircase 4 of automobile climb and fall guidance tape 3, personnel and railing, welding job one Terminate, that is, clean, polish and repairing paint.
The drainage system in parking lot employs the struts of part-structure, therefore does not arrange additional conduits.If nearby had Fire water pipeline, it may be connected to parking lot.
At the same time, electrician can march into the arena laying cable, install illumination and closed-circuit television CCTV monitoring systems and charge is System.
Automatic payment machine, import and export/Fare Collection System and illumination are carried out after the completion of parking lot and charging system (if any) is adjusted Formula, qualified rear referable is used.
After parking lot completion is paid, can at any time be lengthened as needed, if being designed with consideration, also can at any time be added layer. The construction period of layer is being lengthened and is adding, the operation to parking lot is substantially unaffected.If to be moved to parking lot, from upper and Under, only the position that need to weld at the scene carries out surface trimming, then the plate of standard is transported into new address is assembled.
A kind of in-site installation steel parking lot in the present embodiment, mainly by whole-steel slab and girder and branch column combination Form, using fixed welding manner connection, the particularly finishing system of high-quality and implementation, it is ensured that steel construction between structure Anti-corrosion function, long service life.
The utility model is not directed to partly same as the prior art or can be realized using prior art.
Although as described above, having been represented with reference to specific preferred embodiment and having described the utility model, it must not It is construed to the limitation to the utility model itself.The spirit and scope of the present utility model of appended claims definition are not being departed from Under the premise of, can various changes can be made in the form and details to it.

Claims (4)

1. a kind of in-site installation steel parking lot, it is characterised in that:Including it is horizontally disposed no less than one layer for stopping The landing of vehicle is put, support is realized by pillar between the landing per adjacent levels, stopping per adjacent levels Automobile climb and fall guidance tape and personnel's upper and lower staircase are set between car platform;Landing is made up of the parking deck no less than a piece And be fixedly connected between each parking deck;Automobile import and export is set on the landing of the bottom, is set at automobile import and export Put automatic payment machine.
2. in-site installation steel parking lot as claimed in claim 1, it is characterised in that using weldering between each parking deck The mode of connecing is fixedly connected.
3. in-site installation steel parking lot as claimed in claim 1, it is characterised in that the gradient of automobile climb and fall guidance tape Less than 12.5 °.
4. in-site installation steel parking lot as claimed in claim 1, it is characterised in that in-site installation steel Multilayer parking Field also includes Car license recognition monitoring system and cell phone intelligent charging system.
CN201621249570.5U 2016-11-18 2016-11-18 A kind of in-site installation steel parking lot Active CN206220594U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621249570.5U CN206220594U (en) 2016-11-18 2016-11-18 A kind of in-site installation steel parking lot

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621249570.5U CN206220594U (en) 2016-11-18 2016-11-18 A kind of in-site installation steel parking lot

Publications (1)

Publication Number Publication Date
CN206220594U true CN206220594U (en) 2017-06-06

Family

ID=58790499

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621249570.5U Active CN206220594U (en) 2016-11-18 2016-11-18 A kind of in-site installation steel parking lot

Country Status (1)

Country Link
CN (1) CN206220594U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106368465A (en) * 2016-11-18 2017-02-01 南通欣通船舶与海洋工程设计有限公司 Field mounted steel multi-storey parking space

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106368465A (en) * 2016-11-18 2017-02-01 南通欣通船舶与海洋工程设计有限公司 Field mounted steel multi-storey parking space

Similar Documents

Publication Publication Date Title
CN206785050U (en) A kind of vertical transport circular stereo garage
CN206397251U (en) The steel structure platform that steel structure platform frame unit and assembling are built
CN103835218B (en) Pavement in covered bridge type Multifunctional air
CN206591862U (en) A kind of subway overhead station construction protecting platform car
CN202324576U (en) Rail-mounted platform system used for installing cornice and ceiling aluminium sheet curtain wall
CN104763212B (en) Photovoltaic ecological paradise intelligent car storing dock
CN206220594U (en) A kind of in-site installation steel parking lot
CN106869552A (en) Underground rotating type stereo carport
CN113481814A (en) Novel assembly type green pedestrian overpass and use method thereof
CN206538685U (en) Twin shaft pier and middle binder truss move integrally system
CN105604368A (en) Track type stereo garage and control method thereof
CN104878838B (en) A liter support reinforced concrete building method of construction is changed in one kind supporting
CN104989139A (en) Circular ring circulation rotating garage partially or totally arranged over ground
CN108114551A (en) Construction site dust controlling method
CN106368465A (en) Field mounted steel multi-storey parking space
CN115874594A (en) Translation load receiving system and translation load receiving method for ocean booster station
CN106592438B (en) Twin shaft pier and middle binder truss move integrally construction method
JP7097882B2 (en) Urban transportation and logistics system
CN204804406U (en) Part or whole sets up rotatory garage of ring circulation on ground
CN204826804U (en) Big -and -middle -sized vehicle stereo garage with overhaul layer
CN114348882A (en) Hoisting method of refining tower
CN205558410U (en) Runway type stereo garage
CN102182336B (en) Underground garage
CN102182321B (en) Construction method of underground garage
CN207017100U (en) A kind of bicycle expressway girder steel paving structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant