CN206204232U - A kind of naphtha cut of the built-in condenser of tower top band enters desulfurization rectifying column - Google Patents

A kind of naphtha cut of the built-in condenser of tower top band enters desulfurization rectifying column Download PDF

Info

Publication number
CN206204232U
CN206204232U CN201621290584.1U CN201621290584U CN206204232U CN 206204232 U CN206204232 U CN 206204232U CN 201621290584 U CN201621290584 U CN 201621290584U CN 206204232 U CN206204232 U CN 206204232U
Authority
CN
China
Prior art keywords
reboiler
tower body
steam
condenser
tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621290584.1U
Other languages
Chinese (zh)
Inventor
毛永成
艾中国
陈永金
白雪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Panjin Dual Source Petrochemical Co Ltd
Original Assignee
Panjin Dual Source Petrochemical Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Panjin Dual Source Petrochemical Co Ltd filed Critical Panjin Dual Source Petrochemical Co Ltd
Priority to CN201621290584.1U priority Critical patent/CN206204232U/en
Application granted granted Critical
Publication of CN206204232U publication Critical patent/CN206204232U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Production Of Liquid Hydrocarbon Mixture For Refining Petroleum (AREA)

Abstract

Enter desulfurization rectifying column the utility model discloses a kind of naphtha cut of the built-in condenser of tower top band, including bottom of towe return duct, support feet and oil well pump, the support feet is arranged on the bottom of reboiler, the right side top of the reboiler is provided with steam access tube, the reboiler is internally provided with steam runner pipe, the reboiler left side is provided with bottom of towe connecting tube at the top position of steam exit, and the bottom of towe return duct is arranged on the top middle position of reboiler.There is provided preheater, the reaction efficiency of naphtha and hydrogen can be improved, the efficiency of naphtha desulfurization is improve, while condenser is arranged in tower, flowed back using liquid self gravitation, reflux pump is eliminated, while reducing taking up room for equipment, pipe arrangement cost is saved, tower temperature can more effectively be adjusted, prevent heavy component from being steamed from tower top, the carrying out for alloing distillation process continual and steady, it is ensured that product quality.

Description

A kind of naphtha cut of the built-in condenser of tower top band enters desulfurization rectifying column
Technical field
The utility model belongs to naphtha cut desulfurizer technical field, and in particular to a kind of built-in condenser of tower top band Naphtha cut enter desulfurization rectifying column.
Background technology
Rectifying column is a kind of tower vapor-liquid contacting apparatus for carrying out rectifying.There are plate column and two kinds of main Types of packed tower. Continuous rectifying tower and batch fractionating tower can be divided into according to mode of operation again.Steam is entered by bottom of towe.The gas phase for evaporating and decline Liquid carries out counter current contacting, and during two are in contact, volatile (low boiling) component in lower descending liquid is constantly shifted in gas phase, gas phase In difficult volatilization (higher boiling) component constantly shift in downward descending liquid, closer to tower top, its volatile components concentration heals gas phase Height, and lower descending liquid is closer to bottom of towe, its difficult volatile component is then more enriched with, so as to reach the purpose of Component seperation.Risen by tower top Gas phase enter condenser, a part for the liquid of condensation returns to tower top and enters in rectifying column as phegma, remaining part Then taken out as distillate.The liquid of bottom of towe outflow, part feeding reboiler therein, heating evaporation returns to tower into gas phase In, another part liquid takes out as kettle raffinate.
Existing rectifying tower structure is complicated.Condenser is arranged on outside tower, occupies substantial amounts of space, and waste a lot Material, heavy constituent easily steams tower top, causes the purity of rectifying product and reduces.
Utility model content
The purpose of this utility model is to provide a kind of naphtha cut of the built-in condenser of tower top band to enter desulfurization rectifying column, It is arranged on outside tower with solving the condenser proposed in above-mentioned background technology, occupies substantial amounts of space, and waste many materials Material, heavy constituent easily steams tower top, the problem for causing the purity of rectifying product to reduce.
To achieve the above object, the utility model provides following technical scheme:A kind of stone brain of the built-in condenser of tower top band Oil distillate enters desulfurization rectifying column, including bottom of towe return duct, support feet and oil well pump, and the support feet is arranged on the bottom of reboiler Portion, the right side top of the reboiler is provided with steam access tube, and reboiler right side near the lower position of steam access tube Place is provided with bottom product outlet, and the reboiler is internally provided with steam runner pipe, and the left side lower section of reboiler is provided with Steam exit, the reboiler left side is provided with bottom of towe connecting tube, the bottom of towe at the top position of steam exit Return duct is arranged on the top middle position of reboiler, and tower body is provided with the left of bottom of towe return duct, under the tower body Side is provided with preheater, and the preheater right-hand member is provided with naphtha access port, institute near the lower position of bottom of towe connecting tube State and hydrogen access port is provided with below naphtha access port, the left side top of the preheater is provided with oil plant access tube, institute State tower body left side and be provided with tower body steam access port at the top position of oil plant access tube, the tower body steam access port Top is provided with oil pick-up tube, and the tower body left side is provided with tower body steam exit, and tower at the top position of oil pick-up tube Body inner upper is provided with condenser, and overhead reflux pipe, and tower body right side are provided with above the tower body near overhead reflux The lower position of pipe is provided with overhead product outlet, and machine body base, the oil well pump peace are provided with the left of the preheater Mounted in the top of machine body base, the oil well pump, condenser and preheater are electrically connected with external control panel.
Preferably, the steam runner pipe is provided with two altogether, and two steam runner pipes are separately mounted to steam and pick out Inside mouth and tower body.
Preferably, the reboiler is fixedly connected with tower body by bottom of towe connecting tube and bottom of towe return duct.
Preferably, the tower body is fixed with condenser by overhead reflux pipe.
Preferably, the tower body, preheater and reboiler lower end are provided with two support feets.
Compared with prior art, the beneficial effects of the utility model are:The utility model is scientific and reasonable for structure, uses safety It is convenient, there is provided preheater, can improve the reaction efficiency of naphtha and hydrogen, the efficiency of naphtha desulfurization is improve, while Condenser is arranged in tower, is flowed back using liquid self gravitation, reflux pump is eliminated, while reducing the occupancy of equipment Space, saves pipe arrangement cost, can more effectively adjust tower temperature, prevents heavy component from being steamed from tower top, makes the distillation process can be with Continual and steady carrying out, it is ensured that product quality.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the schematic diagram of preheater of the present utility model 11;
In figure:1- bottom of towe connecting tube, 2- bottom of towe return duct, 3- steam runner pipe, 4- steam access tube, 5- bottom products go out Mouth, 6- support feets, 7- reboilers, 8- steam exit, 9- hydrogen access port, 10- naphthas access port, 11- preheaters, 12- Machine body base, 13- oil well pumps, 14- oil pick-up tubes, 15- oil plants access tube, 16- tower body steam access port, 17- tower body steam are picked out Mouth, 18- condensers, 19- overhead refluxes pipe, the outlet of 20- overhead products, 21- tower bodies.
Specific embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the utility model embodiment is carried out Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of the utility model, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment for being obtained, belongs to the scope of the utility model protection.
Fig. 1 and Fig. 2 is referred to, the utility model provides a kind of technical scheme:A kind of stone brain of the built-in condenser of tower top band Oil distillate enters desulfurization rectifying column, including bottom of towe return duct 2, support feet 6 and oil well pump 13, and support feet 6 is arranged on the bottom of reboiler 7 Portion, the right side top of reboiler 7 is provided with steam access tube 4, and the right side of reboiler 7 near the lower position of steam access tube 4 Place is provided with bottom product outlet 5, and reboiler 7 is internally provided with steam runner pipe 3, and the left side lower section of reboiler 7 is provided with Steam exit 8, the left side of reboiler 7 is provided with bottom of towe connecting tube 1, bottom of towe backflow at the top position of steam exit 8 Pipe 2 is arranged on the top middle position of reboiler 7, and the left side of bottom of towe return duct 2 is provided with tower body 21, the lower section of tower body 21 Preheater 11 is provided with, the right-hand member of preheater 11 is provided with naphtha access port 10, stone near the lower position of bottom of towe connecting tube 1 The lower section of cerebrol access port 10 is provided with hydrogen access port 9, and the left side top of preheater 11 is provided with oil plant access tube 15, tower body 21 left sides are provided with tower body steam access port 16 at the top position of oil plant access tube 15, tower body steam access port 16 it is upper Side is provided with oil pick-up tube 14, and the left side of tower body 21 is provided with tower body steam exit 17 at the top position of oil pick-up tube 14, and The inner upper of tower body 21 is provided with condenser 18, and the top of tower body 21 is provided with overhead reflux pipe 19, and the right side of tower body 21 is close to The lower position of overhead reflux pipe 19 is provided with overhead product outlet 20, and the left side of preheater 11 is provided with machine body base 12, Oil well pump 13 is arranged on the top of machine body base 12, and oil well pump 13, condenser 18 and preheater 11 are electric with external control panel Property connection.
In order that naphtha can carry out rectifying with more efficient, in the present embodiment, it is preferred that in the present embodiment, it is preferred that Steam runner pipe 3 is provided with two altogether, and two steam runner pipes 3 are separately mounted to inside steam exit 8 and tower body 21.
Bottom of towe high concentration hardly possible volatile component can normally carry out the backflow of rectifying again for convenience, excellent in the present embodiment Choosing, reboiler 7 is fixedly connected with tower body 21 by bottom of towe connecting tube 1 and bottom of towe return duct 2.
In order that bottom of towe high concentration volatile components can normally complete backflow, the purity of rectifying, the present embodiment are lifted In, it is preferred that tower body 21 is fixed with condenser 18 by overhead reflux pipe 19.
In order that the fixation that this equipment can be stablized, in the present embodiment, it is preferred that tower body 21, preheater 11 and reboiler 7 Lower end is provided with two support feets 6.
Condenser of the present utility model 18 is the parts of refrigeration system, belongs to one kind of heat exchanger, can be gas or steam It is transformed into liquid, by the heat in pipe, in the way of quickly, in the air passed near pipe.The course of work of condenser 18 It is the process of a heat release, so the temperature of condenser 18 is all higher, power plant discharges turbine with many condensers 18 Steam condensed.With condenser 18 come the refrigeration steam of condensate ammonia and freon etc in refrigeration plant.Petrochemistry work Hydro carbons and other chemical evapns are condensed in industry with condenser 18.In still-process, steam is transformed into the device of liquid Referred to as condenser 18.All of condenser 18 is all the heat of gas or steam to be taken away and is operated.
Operation principle of the present utility model and use flow:The naphtha cut of the built-in condenser of tower top band enters desulfurization essence Evaporate after tower installs, by external control panel, make the device equal normal work electrical with external control panel, from naphtha Access port 10 adds the naphtha for needing rectifying, while being passed through hydrogen from hydrogen access port 9, preheater 11 carries out heating makes hydrogen Reacted with the sulphur in naphtha, oil well pump 13 work by oil plant access tube 15 extract preheater 11 inside naphtha by Oil pick-up tube 14 is entered into inside tower body 21, while accessing high-temperature steam, naphtha from steam access tube 4 and tower body steam access port Enter into tower body 21, under high temperature action, volatile component is entered into inside condenser 18 in naphtha, after being condensed By overhead product outlet 20 discharge, while be particularly easy in gaseous component volatilization gas carried out again by overhead reflux pipe 19 it is cold But, the component of difficult volatilization flows to the bottom of tower body 21 in naphtha, is entered into reboiler 7 by bottom of towe connecting tube 1, by boiling again Device 7 is heated again, the component part volatilization of difficult volatilization is entered into tower body 21 by bottom of towe return duct 2, by condensation Device 18 is cooled down, and is discharged by overhead product outlet 20, and the composition that cannot be volatilized inside reboiler 7 is discharged by bottom product outlet 5, tower Steam inside the inside of body 21 and reboiler 7 is connect by tower body steam exit 17 and steam respectively after heat transfer cooling is carried out Outlet 8 is discharged, then accesses new vapours, the inside of tower body 21 and the internal-internal temperature of reboiler 7 is maintained all the time certain In the range of.
While there has been shown and described that embodiment of the present utility model, for the ordinary skill in the art, It is appreciated that these embodiments can be carried out various changes in the case where principle of the present utility model and spirit is not departed from, repaiies Change, replace and modification, scope of the present utility model is defined by the appended claims and the equivalents thereof.

Claims (5)

1. a kind of naphtha cut of the built-in condenser of tower top band enters desulfurization rectifying column, including bottom of towe return duct(2), support feet (6)And oil well pump(13), it is characterised in that:The support feet(6)Installed in reboiler(7)Bottom, the reboiler(7)'s Right side top is provided with steam access tube(4), and reboiler(7)Right side is near steam access tube(4)Lower position set There is bottom product to export(5), the reboiler(7)It is internally provided with steam runner pipe(3), and reboiler(7)Left side lower section It is provided with steam exit(8), the reboiler(7)Left side is near steam exit(8)Top position at be provided with bottom of towe Connecting tube(1), the bottom of towe return duct(2)Installed in reboiler(7)Top middle position, and bottom of towe return duct(2)'s Left side is provided with tower body(21), the tower body(21)Lower section be provided with preheater(11), the preheater(11)Right-hand member is close to Bottom of towe connecting tube(1)Lower position be provided with naphtha access port(10), the naphtha access port(10)Lower section set It is equipped with hydrogen access port(9), the preheater(11)Left side top be provided with oil plant access tube(15), the tower body(21)It is left Side is near oil plant access tube(15)Top position at be provided with tower body steam access port(16), the tower body steam access port (16)Top be provided with oil pick-up tube(14), the tower body(21)Left side is near oil pick-up tube(14)Top position at be provided with tower Body steam exit(17), and tower body(21)Inner upper is provided with condenser(18), the tower body(21)Top be provided with Overhead reflux pipe(19), and tower body(21)Right side is near overhead reflux pipe(19)Lower position be provided with overhead product outlet (20), the preheater(11)Left side be provided with machine body base(12), the oil well pump(13)Installed in machine body base(12) Top, the oil well pump(13), condenser(18)And preheater(11)It is electrically connected with external control panel.
2. a kind of naphtha cut of built-in condenser of tower top band according to claim 1 enters desulfurization rectifying column, its feature It is:The steam runner pipe(3)Two, and two steam runner pipes are provided with altogether(3)It is separately mounted to steam exit(8) And tower body(21)It is internal.
3. a kind of naphtha cut of built-in condenser of tower top band according to claim 1 enters desulfurization rectifying column, its feature It is:The reboiler(7)With tower body(21)By bottom of towe connecting tube(1)With bottom of towe return duct(2)It is fixedly connected.
4. a kind of naphtha cut of built-in condenser of tower top band according to claim 1 enters desulfurization rectifying column, its feature It is:The tower body(21)With condenser(18)By overhead reflux pipe(19)It is fixed.
5. a kind of naphtha cut of built-in condenser of tower top band according to claim 1 enters desulfurization rectifying column, its feature It is:The tower body(21), preheater(11)And reboiler(7)Lower end is provided with two support feets(6).
CN201621290584.1U 2016-11-29 2016-11-29 A kind of naphtha cut of the built-in condenser of tower top band enters desulfurization rectifying column Expired - Fee Related CN206204232U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621290584.1U CN206204232U (en) 2016-11-29 2016-11-29 A kind of naphtha cut of the built-in condenser of tower top band enters desulfurization rectifying column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621290584.1U CN206204232U (en) 2016-11-29 2016-11-29 A kind of naphtha cut of the built-in condenser of tower top band enters desulfurization rectifying column

Publications (1)

Publication Number Publication Date
CN206204232U true CN206204232U (en) 2017-05-31

Family

ID=58747024

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621290584.1U Expired - Fee Related CN206204232U (en) 2016-11-29 2016-11-29 A kind of naphtha cut of the built-in condenser of tower top band enters desulfurization rectifying column

Country Status (1)

Country Link
CN (1) CN206204232U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107213663A (en) * 2017-07-19 2017-09-29 成都尚智恒达科技有限公司 The carbon disulfide rectifying column of condenser built in a kind of tower top band

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107213663A (en) * 2017-07-19 2017-09-29 成都尚智恒达科技有限公司 The carbon disulfide rectifying column of condenser built in a kind of tower top band

Similar Documents

Publication Publication Date Title
CN205925048U (en) Retrieve batch distillation device of ethanol in china cypress paper production process
CN100584421C (en) Differential pressure low-energy-consumption distillation method and equipment
CN205730426U (en) A kind of rectifying column
CN205269088U (en) Vacuum rectifying apparatus with built -in roots vacuum pump
CN102875329B (en) A kind of heat pump distillation is separated technique and the device of primary isoamyl alcohol isomers
CN102423539B (en) Energy-saving technology of catalytic reaction distillation process and device thereof
CN109876485A (en) Acetic acid recovery is from backheat rectifier unit and method
CN101187523A (en) Preparation method for obtaining super high pure oxygen
CN106431835A (en) Novel technology and device for separating ethyl alcohol from water through differential-pressure thermally coupled distillation
CN110105216B (en) Self-backheating rectification method and device
CN206204232U (en) A kind of naphtha cut of the built-in condenser of tower top band enters desulfurization rectifying column
CN202315370U (en) Energy-saving device used in catalytic reaction rectifying process
CN103466549B (en) High-purity chlorine gas rectifying technology and equipment thereof
CN106512463A (en) Gas and liquid separation device of rectifying tower
CN106730968A (en) A kind of integrated air rectification and purification device
CN203461817U (en) High-purity chlorine gas rectification device
CN110078582A (en) Cyclohexane separation device and method for cyclohexanone and cyclohexanol production
CN213294754U (en) Normal-pressure energy-saving continuous fractionating device
CN104606910A (en) Heat pump rectifying device based on heat storage technology and starting method of heat pump rectifying device
CN205340191U (en) Rectification condensing equipment of ethanol recovery purification
CN205323257U (en) Ethanol differential pressure distillation plant with flash distillation
JP2004114029A (en) Method of separating and recovering water-soluble volatile component in waste water
CN206334377U (en) A kind of gas-liquid separation device of rectifying column
CN102583395A (en) Heat pump rectification method for refining trichlorosilane
CN201880386U (en) Rectifying device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170531

Termination date: 20191129

CF01 Termination of patent right due to non-payment of annual fee