CN206194178U - Leaking stoppage trainer - Google Patents
Leaking stoppage trainer Download PDFInfo
- Publication number
- CN206194178U CN206194178U CN201620988149.XU CN201620988149U CN206194178U CN 206194178 U CN206194178 U CN 206194178U CN 201620988149 U CN201620988149 U CN 201620988149U CN 206194178 U CN206194178 U CN 206194178U
- Authority
- CN
- China
- Prior art keywords
- pressure
- valve
- leak
- leakage
- trainer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Filling Or Discharging Of Gas Storage Vessels (AREA)
Abstract
The utility model discloses a leaking stoppage trainer, leaking stoppage trainer includes high -pressure gas cylinder group, there are decompression transfer valve and pressure reducer in high -pressure gas cylinder group through the pipe connection, the low reaches of decompression transfer valve and pressure reducer are connected with a plurality of output pipeline, and all connect gradually solenoid valve, manual valve on every output pipeline and revealed the stage property, wherein, wherein, the solenoid valve all is connected with PLC, by PLC control solenoid's work. The utility model discloses a leak source that leaking stoppage trainer was provided with the various ways leaks, can supply the daily use title page leaking stoppage bag of fire fighter, tie up the leaking stoppage area, paste leaking stoppage tool group, leakage stoppage material such as magnetic pressure leaking stoppage ware, high temperature high pressure injecting glue leaking stoppage rifle carry out leaking stoppage basic skill training, also can be used to assess the the training effect who trains personnel.
Description
Technical field
The utility model belongs to fire drill apparatus field, and in particular to a kind of leak stopping trainer, the device is mainly used
In the leak stopping training of gas leakage.
Background technology
In fire brigade, in order to improve the ability at the fire-fighting work personnel reply scene of being in danger, usually need to carry out various
Simulated training, leak stopping training is one of them particularly important training program.Leak stopping mentioned here refers to put out a fire and meeting an urgent need
The close measure taken for leakage accidents such as storage tank, pipelines in rescue.This closure training is substantially by reason at present
Tested by study and to leakage material object, also not used for the professional facility of leakage blockage simulation training.
Utility model content
For problems of the prior art, the purpose of this utility model is to provide a kind of leak stopping trainer, should
Leak stopping trainer is provided with the leak source leakage of diversified forms, is available for closure leak-off pocket in firefighterses routine use, ties up leak stopping
The leak stoppers such as band, stickup leak stoppage tool group, magnetic pressure leak blockage device, HTHP injecting glue plugging gun carry out leak stopping basic skills instruction
Practice, it can also be used to which the training effect to trainer is examined.
To achieve the above object, the utility model uses following technical scheme:
A kind of leak stopping trainer, the leak stopping trainer includes high-pressure gas cylinder group, and the high-pressure gas cylinder group is led to
Piping is connected with decompression transfer valve and pressure reducer, and the downstream connection of the decompression transfer valve and pressure reducer has several efferent ducts
Road, is connected with magnetic valve, hand-operated valve and leakage stage property in turn on each output channel, leakage is provided with the leakage stage property
Point;Wherein, the magnetic valve is connected with PLC, and the work of magnetic valve is controlled by the PLC.
Further, it is provided with pressure gauge on the conveyance conduit in the middle of the high-pressure gas cylinder group to the output channel.
Further, the gas access of the output channel is provided with pressure transmitter, the pressure transmitter and the PLC
Connection.
Further, the output channel is connected with the leakage stage property by fast insert-pull joint, and the leakage stage property
Include but are not limited to the tank body of circular hole leak, the tank body with slit leakage hole, the tank body with sand holes leak,
Flange root with leak and the elbow with leak.
Further, pressure pocket, the pressure pocket and the inwall welded seal for revealing stage property are provided with the leakage stage property,
Leakage point is set in the range of pressure pocket on the inwall of leakage stage property, pressure pocket is provided with the interface being connected with to air pipe.
Further, the source outlet of the high-pressure gas cylinder group sets aeration valve, air bleeding valve and pressure gauge;The aeration valve
For to gases at high pressure are filled in gas bomb group, the air bleeding valve to be used for residual air in exhaust system, and the pressure gauge is used to monitor
The gas storage pressure in the bottle.
Further, the downstream connection of the decompression transfer valve and pressure reducer has three output channels, is available for three groups of personnel same
When simulated training.
The utility model has following Advantageous Effects:
1st, whole system can realize that various gases are leaked in a variety of manners at various pressures, can integrate,
Can also partly select, the need for various use unit hands-ons can be met.
2nd, PLC is automatically controlled, and any one place or many places leakage, plugging operations time and work can be voluntarily selected before user's training
Industry performance will automatically be recorded and judged by program, can be used for daily workout, it is also possible to for examining.
3rd, liquid or gas is made to be capable of achieving simulated leakage, pole full of storage tank by the design of tank interior pressure pocket
Big has saved water source or source of the gas.The design can also make same tank body realize completing simultaneously the leakages of multi-form such as air-liquid and
Different leak sources can be made individually to control.
4th, the pressure of gas leakage can have a high regard for meaning to adjust by adjustable decompressing, to complete the instruction of the leak stopping under any pressure
Practice.
5th, the design of changeable type fast insert-pull joint can realize many of training content under conditions of overall volume is reduced
Sample, various sizes, various types of leak stopping training are completed by changing simulated leakage stage property.
6th, strong applicability, whole system is selectively equipped in various scene platforms achievable several scenes simulation and lets out
Leakage.
Brief description of the drawings
Fig. 1 is the structural representation of the leak stopping trainer of the application.
Specific embodiment
Below, refer to the attached drawing, is more fully illustrated to the utility model, is shown shown in the drawings of of the present utility model
Example property embodiment.However, the utility model can be presented as various multi-forms, it is not construed as being confined to what is described here
Exemplary embodiment.And these embodiments are to provide, so that the utility model is fully and completely, and will be of the present utility model
Scope fully conveys to one of ordinary skill in the art.
For ease of explanation, herein can using " on ", the space relative terms such as D score " left side " " right side ", for saying
The element or feature shown in bright figure are relative to another element or the relation of feature.It should be understood that except in figure
Outside the orientation for showing, spatial terminology is intended to include device different azimuth in use or operation.If for example, in figure
Device is squeezed, be stated as being located at the element of other elements or feature D score will be located into other elements or feature " on ".Cause
This, exemplary term D score can be comprising both upper and lower orientation.Device can otherwise position and (be rotated by 90 ° or be located at
Other orientation), can correspondingly be explained used herein of the relative explanation in space.
As shown in figure 1, this application provides a kind of leak stopping trainer, the leak stopping trainer includes high-pressure gas cylinder group
1, high-pressure gas cylinder group 1 is connected with the downstream of decompression transfer valve 2 and pressure reducer 3, decompression transfer valve 2 and pressure reducer 3 by pipeline
Several output channels are connected with, magnetic valve 4, hand-operated valve 5 and leakage stage property 6 is connected with each output channel in turn, let out
Leakage point 7 is provided with dew stage property 6;Wherein, magnetic valve 4 is connected with PLC, and the work of magnetic valve 4 is controlled by PLC.
Pressure gauge 8 is provided with conveyance conduit in the middle of high-pressure gas cylinder group 1 to output channel.
The gas access of output channel is provided with pressure transmitter 9, and pressure transmitter 9 is connected with PLC.
Output channel is connected with leakage stage property 6 by fast insert-pull joint 10, and leakage stage property 6 includes but are not limited to band
There are tank body, the tank body with slit leakage hole, the tank body with sand holes leak, the flange with leak of circular hole leak
Root and the elbow with leak.
Pressure pocket 11, pressure pocket 11 and the inwall welded seal of leakage stage property 6 are provided with leakage stage property 6, road is being revealed
Leakage point 7 is set on the inwall of tool 6 in the range of pressure pocket, and pressure pocket 11 is provided with the interface being connected with to air pipe.
The source outlet of high-pressure gas cylinder group 1 sets aeration valve 12, air bleeding valve 13 and pressure gauge 14;Aeration valve 12 be used for
Filling gases at high pressure in gas bomb group, air bleeding valve 12 is used for residual air in exhaust system, and pressure gauge 14 is used to monitor gas bomb internal pressure
Power.
The downstream connection of decompression transfer valve 2 and pressure reducer 3 has three output channels, is available for three groups of personnel while simulating instruction
Practice.
High-pressure gas cylinder group 1 is made up of 6 20MPa gas bombs.
The leak stopping trainer course of work of the application is:
The source of the gas leaked as gas by high-pressure gas cylinder group 1, source outlet sets aeration valve 12, air bleeding valve 13 and pressure
Table 14, aeration valve 12 is used for gases at high pressure are filled in gas bomb group, and air bleeding valve 13 is used for residual air, pressure gauge 14 in exhaust system
For monitoring the gas storage pressure in the bottle.Gases at high pressure enter pressure reducer 3 after the transfer valve 2 that depressurizes, and pressure reducer 3 can according to circumstances be set
Output pressure after gas decompression, the outlet of pressure reducer 3 sets safety valve 15 and pressure gauge 8, and safety valve 15 is used to prevent from exporting gas
Body pressure bears pressure and causes danger beyond the highest of low pressure line, and pressure gauge 8 is used for the output pressure of gas after monitoring decompression.
Gas after decompression is delivered at each road normally closed solenoid valve 4 through the delivery valve that depressurizes, and the front end of each magnetic valve 4 sets pressure transmitter 9,
The monitoring leakage of pressure transmitter 9 start after system pressure and pass to PLC, PLC program by different leak source leak pressures and
The contrast of non-leak pressure numerical value judges the performance of plugging operations.After the leak source for needing leakage is selected by PLC program,
Corresponding magnetic valve 4 is opened, and compressed gas enter leak source stage property, and personnel carry out plugging operations.
Pressure pocket 11 is provided with simulation tank body or the stage property of other main facilitieses leakage, pressure pocket 11 welds close with tank skin
Envelope, sets leakage point 7 in the range of pressure pocket on tank skin, and the spare interface of pressure pocket 11 is connected with supply air line, and this design can
So that compressed gas are full of i.e. achievable simulated leakage after pressure pocket, it is not necessary to make gas full of whole tank body, can also realize same
One tank body or stage property realize gas, the multiple spot of liquid is leaked simultaneously.Can be in limited space by fast insert-pull joint 10
The training of various different sizes, type leakage is realized by way of changing leakage stage property.After leak stopping training terminates, trainer
Can gesture, report or press button by way of teaching process personnel plugging operations complete, operating personnel are under PLC program
Up to complete instruct, program activity duration and operation performance are carried out automatic decision and be given training fraction and select achieve or
Output.System can also set several groups of identical leak sources, and packet examination tourney is carried out for instruction person.
It is described above simply to illustrate that the utility model, it is understood that the utility model be not limited to the above implementation
Example, meets the various variants of the utility model thought within protection domain of the present utility model.
Claims (7)
1. a kind of leak stopping trainer, it is characterised in that the leak stopping trainer includes high-pressure gas cylinder group, the high pressure storage
Gas cylinders group is connected with decompression transfer valve and pressure reducer by pipeline, and the downstream connection of the decompression transfer valve and pressure reducer has some
Individual output channel, is connected with magnetic valve, hand-operated valve and leakage stage property in turn on each output channel, set on the leakage stage property
It is equipped with leakage point;Wherein, the magnetic valve is connected with PLC, and the work of magnetic valve is controlled by the PLC.
2. leak stopping trainer according to claim 1, it is characterised in that the high-pressure gas cylinder group to the efferent duct
Pressure gauge is provided with conveyance conduit in the middle of road.
3. leak stopping trainer according to claim 1, it is characterised in that the gas access of the output channel is provided with
Pressure transmitter, the pressure transmitter is connected with the PLC.
4. leak stopping trainer according to claim 1, it is characterised in that the output channel leads to the leakage stage property
Cross fast insert-pull joint connection, and it is described leakage stage property include but are not limited to circular hole leak tank body, with crack
The tank body of leak, the tank body with sand holes leak, the flange root with leak and the elbow with leak.
5. leak stopping trainer according to claim 1, it is characterised in that be provided with pressure pocket in the leakage stage property,
The pressure pocket and the inwall welded seal of leakage stage property, leakage point is set in the range of pressure pocket on the inwall of leakage stage property,
Pressure pocket is provided with the interface being connected with to air pipe.
6. leak stopping trainer according to claim 1, it is characterised in that the source outlet of the high-pressure gas cylinder group sets
Put aeration valve, air bleeding valve and pressure gauge;The aeration valve is used for gases at high pressure are filled in gas bomb group, and the air bleeding valve is used for
Residual air in exhaust system, the pressure gauge is used to monitor the gas storage pressure in the bottle.
7. leak stopping trainer according to claim 1, it is characterised in that the downstream of the decompression transfer valve and pressure reducer
Three output channels are connected with, three groups of personnel simulated training simultaneously is available for.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620988149.XU CN206194178U (en) | 2016-08-30 | 2016-08-30 | Leaking stoppage trainer |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620988149.XU CN206194178U (en) | 2016-08-30 | 2016-08-30 | Leaking stoppage trainer |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206194178U true CN206194178U (en) | 2017-05-24 |
Family
ID=58727723
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620988149.XU Active CN206194178U (en) | 2016-08-30 | 2016-08-30 | Leaking stoppage trainer |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206194178U (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107293176A (en) * | 2017-08-13 | 2017-10-24 | 北京管通科技开发有限责任公司 | A kind of pressure sealing analog simulation training points-scoring system and method |
CN108470490A (en) * | 2018-05-19 | 2018-08-31 | 张繁荣 | A kind of pipeline wrapping training system |
CN108506738A (en) * | 2018-04-11 | 2018-09-07 | 天津安固密封技术有限公司 | A kind of harmful influence non-stop plugging drilling system and drilling method |
CN109459184A (en) * | 2018-12-13 | 2019-03-12 | 广西电网有限责任公司电力科学研究院 | The device and its application method of electrical equipment SF6 gas leakage standard source are provided |
CN109584665A (en) * | 2018-11-23 | 2019-04-05 | 国网天津市电力公司电力科学研究院 | Sulfur hexafluoride leaks simulator and leak detection Training Methodology |
CN112071145A (en) * | 2020-09-07 | 2020-12-11 | 广东电网有限责任公司 | Gas leakage simulation device |
-
2016
- 2016-08-30 CN CN201620988149.XU patent/CN206194178U/en active Active
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107293176A (en) * | 2017-08-13 | 2017-10-24 | 北京管通科技开发有限责任公司 | A kind of pressure sealing analog simulation training points-scoring system and method |
CN108506738A (en) * | 2018-04-11 | 2018-09-07 | 天津安固密封技术有限公司 | A kind of harmful influence non-stop plugging drilling system and drilling method |
CN108470490A (en) * | 2018-05-19 | 2018-08-31 | 张繁荣 | A kind of pipeline wrapping training system |
CN109584665A (en) * | 2018-11-23 | 2019-04-05 | 国网天津市电力公司电力科学研究院 | Sulfur hexafluoride leaks simulator and leak detection Training Methodology |
CN109459184A (en) * | 2018-12-13 | 2019-03-12 | 广西电网有限责任公司电力科学研究院 | The device and its application method of electrical equipment SF6 gas leakage standard source are provided |
CN109459184B (en) * | 2018-12-13 | 2024-03-08 | 广西电网有限责任公司电力科学研究院 | Device for providing SF6 gas leakage standard source of electrical equipment and using method thereof |
CN112071145A (en) * | 2020-09-07 | 2020-12-11 | 广东电网有限责任公司 | Gas leakage simulation device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206194178U (en) | Leaking stoppage trainer | |
CN206194177U (en) | Leaking stoppage trainer | |
CN205541529U (en) | Multi -media leaking stoppage trainer based on PLC linkage | |
CN203433733U (en) | Simulation apparatus for chemical disaster accident | |
CN201765743U (en) | Chemical pipeline blocking leakage under pressure test training integrated equipment | |
CN206162920U (en) | Dangerization article tank wagon trainer | |
CN205690086U (en) | Oil and gas pipes gas leakage monitoring and detection analog systems | |
CN204143749U (en) | Harmful influence production area simulated leakage trainer | |
CN203259431U (en) | Alternative positive/negative pressure testing device for plastic pipelines | |
CN207690341U (en) | Low temperature groove tank car leakage accident with pressure disposes simulation training device | |
CN213543979U (en) | Test experiment device for simulating leakage fault of aviation hydraulic pipeline | |
CN101509605A (en) | Method for recovering relief gas in process for examining and repairing gas pipe network | |
RU2279140C1 (en) | Device for training specialists in removal of gas leaks from gas pipelines | |
CN204463661U (en) | Portable leakage blockage simulation training facilities | |
CN104500977A (en) | Test system for pipeline maintenance and repair technology | |
CN103810916A (en) | Fire-fighting leakage training experiment device | |
CN203706478U (en) | Emergent leaking stoppage fire fighting simulation training apparatus with pressure | |
CN207637326U (en) | A kind of pressure sealing analog simulation training device | |
CN204629095U (en) | A kind of pipeline dimension damage repair technology pilot system | |
CN211506803U (en) | Multifunctional gas pipeline leakage stoppage training device | |
CN107731039B (en) | Low temperature groove tank car leakage accident with pressure disposes simulation training device | |
CN216957219U (en) | Leakage-simulating fire-fighting leakage-stopping double-tank type training device | |
CN204990827U (en) | Multi -functional leaking stoppage fire control training facilities | |
CN113129724A (en) | Simulation system for emergency disposal of leakage of dangerous chemicals | |
CN206974622U (en) | A kind of carbon dioxide drive equipment leak detection combination unit |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |