CN206189680U - Steel sheet rib bearing structure curtain system - Google Patents

Steel sheet rib bearing structure curtain system Download PDF

Info

Publication number
CN206189680U
CN206189680U CN201621243344.6U CN201621243344U CN206189680U CN 206189680 U CN206189680 U CN 206189680U CN 201621243344 U CN201621243344 U CN 201621243344U CN 206189680 U CN206189680 U CN 206189680U
Authority
CN
China
Prior art keywords
steel plate
plate rib
rib
curtain wall
steel sheet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621243344.6U
Other languages
Chinese (zh)
Inventor
殷兵利
董彪
蔡红林
李涛
钱方
刘艺
张文渊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Southwest Architectural Design and Research Institute Co Ltd
Original Assignee
China Southwest Architectural Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Southwest Architectural Design and Research Institute Co Ltd filed Critical China Southwest Architectural Design and Research Institute Co Ltd
Priority to CN201621243344.6U priority Critical patent/CN206189680U/en
Application granted granted Critical
Publication of CN206189680U publication Critical patent/CN206189680U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a steel sheet rib bearing structure curtain system, including being used for the steel sheet rib bearing structure to the support of curtain wall construction atress, steel sheet rib bearing structure includes that vertical steel sheet rib of placing and hanging on the major structure and level arrange and be located the prestressing force stretch -draw part that carries out the drawknot between the steel sheet rib, perhaps the steel sheet rib placed of level and vertical layout and be located the prestressing force stretch -draw part that carries out the drawknot between the steel sheet rib. The utility model discloses a steel sheet rib is as the atress member of curtain wall construction, make full use of steel sheet rib flexural section modulus and the big characteristics of cross -section inertia couple, under the prerequisite of guaranteeing structure safety, realized striding greatly the penetrating support system of space glass curtain wall, the steel rib board vision lattice of " straight, tall and straight " feels strong, changes and realizes that the mechanics is beautiful unified with the building midea.

Description

A kind of steel plate rib supporting construction curtain wall system
Technical field
The utility model is related to building curtain wall design field, more particularly to a kind of steel plate rib supporting construction curtain wall system System.
Background technology
At present for the support force structure system of long-span space glass curtain, in order to undertake curtain wall deadweight and horizontal load, Its support force structure is complex, and architectural appearance visual effect is poor.
Utility model content
Goal of the invention of the present utility model is:For above-mentioned problem, there is provided a kind of to ensure structure safety Under the premise of, realize the penetrating steel plate rib supporting construction curtain wall system of long-span space glass curtain wall.
The technical scheme implementation of the utility model technology:A kind of steel plate rib supporting construction curtain wall system, its feature exists In:Including the steel plate rib supporting construction for being supported to curtain wall construction stress, the steel plate rib supporting construction includes vertical placement And hang steel plate rib on the body construction and prestressed stretch-draw portion horizontally disposed and that drawknot is carried out between steel plate rib Part, or horizontal positioned steel plate rib and be vertically arranged and the prestressed stretch-draw part of drawknot carried out between steel plate rib.
Steel plate rib supporting construction curtain wall system described in the utility model, its described prestressed stretch-draw part passes through steel plate Rib, and connected with corresponding steel plate rib by fixture, the prestressed stretch-draw part two ends set with corresponding foundation structure respectively The fixed seat connection put, the steel plate rib two ends connect with the connector set in corresponding foundation structure respectively.
Steel plate rib supporting construction curtain wall system described in the utility model, its described prestressed stretch-draw part is prestress steel Rope or prestressed draw-bar, when the prestressed stretch-draw part is prestressed cable, the drag-line of described prestressed cable one end The drag-line fixing end of tension side and its other end is connected with corresponding foundation structure respectively, when the prestressed stretch-draw part is pre- During stress pull bar, the pull bar fixing end at the prestressed draw-bar two ends is connected with corresponding foundation structure respectively.
Steel plate rib supporting construction curtain wall system described in the utility model, its described curtain wall system is frame curtain wall, institute Frame curtain wall is stated including Aluminum alloy column and aluminum alloy cross beam, the Aluminum alloy column by curtain-wall stand-column connecting plate with it is vertical Place or the steel plate rib of horizontal positioned is connected, the two neighboring steel plate rib of vertical placement or horizontal positioned is spliced by steel rib Plate links together, when the steel plate rib is vertically placed, the position of the steel plate rib and the cloth set of Aluminum alloy column Correspondence is put, the position of the prestressed stretch-draw part is corresponding with the position integral multiple of aluminum alloy cross beam, when the steel During rib of slab horizontal positioned, the position of the steel plate rib is corresponding with the position integral multiple of aluminum alloy cross beam, it is described it is pre- should The position of power tensioning part is corresponding with the position of Aluminum alloy column.
Steel plate rib supporting construction curtain wall system described in the utility model, its described curtain wall system is point-supporting curtain, described Point-supporting curtain includes glass fixture, and the glass fixture is connected with the steel plate rib of vertical placement or horizontal positioned, vertical to place Or the two neighboring steel plate rib of horizontal positioned is linked together by steel rib splice plate, the steel plate rib and prestressed stretch-draw portion Position of the position of part with glass fixture is corresponding.
The utility model, as the primary structure member of curtain wall construction, takes full advantage of steel plate rib by curved section mould using steel plate rib The characteristics of amount and cross sectional moment of inertia are big, on the premise of structure safety is ensured, realizes the penetrating branch of long-span space glass curtain wall Support body system, the steel ribs vision lattice sense of " straight, tall and straight " is strong, is more easy to realize beautiful and beauty of architecture the unification of mechanics.
Brief description of the drawings
Fig. 1 is the cross-sectional schematic diagram that frame curtain wall light plate rib is vertically placed.
Fig. 2 is that vertically the perpendicular of placement cuts open schematic diagram to frame curtain wall light plate rib.
Fig. 3 is the cross-sectional schematic diagram that point-supporting curtain light plate rib is vertically placed.
Fig. 4 is that vertically the perpendicular of placement cuts open schematic diagram to point-supporting curtain light plate rib.
Fig. 5 is the cross-sectional schematic diagram of frame curtain wall light plate rib horizontal positioned.
Fig. 6 is that the perpendicular of frame curtain wall light plate rib horizontal positioned cuts open schematic diagram.
Fig. 7 is the cross-sectional schematic diagram of point-supporting curtain light plate rib horizontal positioned.
Fig. 8 is that the perpendicular of point-supporting curtain light plate rib horizontal positioned cuts open schematic diagram.
Marked in figure:1 is steel plate rib, and 2 is prestressed stretch-draw part, and 3 is fixture, and 4a is drag-line tension side, and 4b is drag-line Fixing end, 4c is pull bar fixing end, and 5 is Aluminum alloy column, and 6 is aluminum alloy cross beam, and 7 is curtain-wall stand-column connecting plate, and 8 spell for steel rib Fishplate bar, 9 is glass fixture.
Specific embodiment
Below in conjunction with the accompanying drawings, the utility model is described in detail.
In order that the purpose of this utility model, technical scheme and advantage become more apparent, below in conjunction with accompanying drawing and implementation Example, is further elaborated to the utility model technology.It should be appreciated that specific embodiment described herein is only used to The utility model is explained, is not used to limit utility model.
Embodiment 1:As illustrated in fig. 1 and 2, a kind of steel plate rib supporting construction curtain wall system, including for being received to curtain wall construction The steel plate rib supporting construction of power support, the steel plate rib supporting construction includes vertical placement and suspension steel plate on the body construction Rib 1 and prestressed stretch-draw part 2 horizontally disposed and that drawknot is carried out between steel plate rib 1, the prestressed stretch-draw part 2 Through steel plate rib 1, and connected with corresponding steel plate rib 1 by fixture 3, the prestressed stretch-draw part 2 is prestress steel Rope, the drag-line tension side 4a of described prestressed cable one end and the drag-line fixing end 4b of its other end respectively with left and right basis The fixed seat connection set in structure, the two ends of steel plate rib 1 are connected with the connector set in upper and lower foundation structure respectively, Curtain wall is undertaken by the vertical steel plate rib placed to conduct oneself with dignity and horizontal load, ensured by the prestressed stretch-draw part between steel plate rib Outside-plate stabilizing when steel rib receives curved.
In the present embodiment, the curtain wall system is frame curtain wall, and the frame curtain wall includes the He of Aluminum alloy column 5 Aluminum alloy cross beam 6, the Aluminum alloy column 5 is connected by curtain-wall stand-column connecting plate 7 with the vertical steel plate rib 1 placed, and is vertically put The two neighboring steel plate rib 1 put is linked together by steel rib splice plate 8, and position and the aluminium alloy of the steel plate rib 1 stand The position correspondence of post 5, the position of the prestressed stretch-draw part 2 and the position integral multiple of aluminum alloy cross beam 6 Correspondence, if at one times, i.e., between the corresponding adjacent aluminum alloy cross beam of spacing between adjacent prestressed stretch-draw part Spacing is equal, if during twice, the spacing between adjacent prestressed stretch-draw part is between its corresponding adjacent aluminum alloy cross beam The twice of spacing, according to concrete engineering and load calculated case by that analogy, in the present embodiment, the cloth of prestressed stretch-draw part Seated position is corresponding by the way of one times with the position of aluminum alloy cross beam.
Embodiment 2:As shown in Figures 3 and 4, the curtain wall system is point-supporting curtain, and the point-supporting curtain includes glass fixture 9, the glass fixture 9 is connected with the vertical steel plate rib 1 placed, and the vertical two neighboring steel plate rib 1 placed is spliced by steel rib Plate 8 links together, the position of the steel plate rib 1 and prestressed stretch-draw part 2 with the position pair of glass fixture 9 Should.Other structures are substantially the same manner as Example 1.
Embodiment 3:As it can be seen in figures 5 and 6, the steel plate rib 1 of the steel plate rib supporting construction including horizontal positioned and vertical Arrangement and the prestressed stretch-draw part 2 of drawknot is carried out between steel plate rib 1, the prestressed stretch-draw part 2 is that prestressing force draws Bar, the pull bar fixing end 4c at the prestressed draw-bar two ends is connected with upper and lower foundation structure respectively, the two ends of steel plate rib 1 point It is not connected with the connection otic placode set in left and right foundation structure, horizontal flexural member is used as by the steel plate rib of horizontal positioned, is led to Outside-plate stabilizing when the prestressed stretch-draw part crossed between steel plate rib undertakes curtain wall deadweight and ensures that steel rib receives curved.
In the present embodiment, the curtain wall system is frame curtain wall, and the frame curtain wall includes the He of Aluminum alloy column 5 Aluminum alloy cross beam 6, the Aluminum alloy column 5 is connected by curtain-wall stand-column connecting plate 7 with the steel plate rib 1 of horizontal positioned, and level is put The two neighboring steel plate rib 1 put is linked together by steel rib splice plate 8, and the position of the steel plate rib 1 is horizontal with aluminium alloy The position integral multiple correspondence of beam 6, the position of the prestressed stretch-draw part 2 and the position of Aluminum alloy column 5 Correspondence.
Embodiment 4:As shown in FIG. 7 and 8, the curtain wall system is point-supporting curtain, and the point-supporting curtain includes glass fixture 9, the glass fixture 9 is connected with the steel plate rib 1 of horizontal positioned, and the two neighboring steel plate rib 1 of horizontal positioned is spliced by steel rib Plate 8 links together, the position of the steel plate rib 1 and prestressed stretch-draw part 2 with the position pair of glass fixture 9 Should.Other structures are substantially the same manner as Example 3.
Preferred embodiment of the present utility model is the foregoing is only, is not used to limit the utility model, it is all at this Any modification, equivalent and improvement made within the spirit and principle of utility model etc., should be included in the utility model Protection domain within.

Claims (5)

1. a kind of steel plate rib supporting construction curtain wall system, it is characterised in that:Including the steel plate for being supported to curtain wall construction stress Rib supporting construction, the steel plate rib supporting construction includes vertical placement and suspension steel plate rib on the body construction(1)And water Plain cloth is put and positioned at steel plate rib(1)Between carry out the prestressed stretch-draw part of drawknot(2), or horizontal positioned steel plate rib(1) And be vertically arranged and positioned at steel plate rib(1)Between carry out the prestressed stretch-draw part of drawknot(2).
2. steel plate rib supporting construction curtain wall system according to claim 1, it is characterised in that:The prestressed stretch-draw part (2)Through steel plate rib(1), and by fixture(3)With corresponding steel plate rib(1)Connection, the prestressed stretch-draw part(2)Two ends Respectively with the fixed seat connection set in corresponding foundation structure, the steel plate rib(1)Two ends set with corresponding foundation structure respectively The connector connection put.
3. steel plate rib supporting construction curtain wall system according to claim 2, it is characterised in that:The prestressed stretch-draw part (2)It is prestressed cable or prestressed draw-bar, when the prestressed stretch-draw part(2)During for prestressed cable, it is described it is pre- should The drag-line tension side of power cable wire one end(4a)And the drag-line fixing end of its other end(4b)Connected with corresponding foundation structure respectively, When the prestressed stretch-draw part(2)During for prestressed draw-bar, the pull bar fixing end at the prestressed draw-bar two ends(4c)Respectively Connected with corresponding foundation structure.
4. the steel plate rib supporting construction curtain wall system according to claim 1,2 or 3, it is characterised in that:The curtain wall system It is frame curtain wall, the frame curtain wall includes Aluminum alloy column(5)And aluminum alloy cross beam(6), the Aluminum alloy column(5) By curtain-wall stand-column connecting plate(7)With vertical placement or the steel plate rib of horizontal positioned(1)Connection, vertical placement or level are put The two neighboring steel plate rib put(1)By steel rib splice plate(8)Link together, when the steel plate rib(1)During vertical placement, institute State steel plate rib(1)Position and Aluminum alloy column(5)Position correspondence, the prestressed stretch-draw part(2)Cloth Seated position and aluminum alloy cross beam(6)Position integral multiple correspondence, when the steel plate rib(1)During horizontal positioned, the steel plate Rib(1)Position and aluminum alloy cross beam(6)Position integral multiple correspondence, the prestressed stretch-draw part(2)Cloth Seated position and Aluminum alloy column(5)Position correspondence.
5. the steel plate rib supporting construction curtain wall system according to claim 1,2 or 3, it is characterised in that:The curtain wall system It is point-supporting curtain, the point-supporting curtain includes glass fixture(9), the glass fixture(9)Placed or horizontal positioned with vertical Steel plate rib(1)The two neighboring steel plate rib of connection, vertical placement or horizontal positioned(1)By steel rib splice plate(8)Connection Together, the steel plate rib(1)With prestressed stretch-draw part(2)Position and glass fixture(9)Position pair Should.
CN201621243344.6U 2016-11-21 2016-11-21 Steel sheet rib bearing structure curtain system Active CN206189680U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621243344.6U CN206189680U (en) 2016-11-21 2016-11-21 Steel sheet rib bearing structure curtain system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621243344.6U CN206189680U (en) 2016-11-21 2016-11-21 Steel sheet rib bearing structure curtain system

Publications (1)

Publication Number Publication Date
CN206189680U true CN206189680U (en) 2017-05-24

Family

ID=58726767

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621243344.6U Active CN206189680U (en) 2016-11-21 2016-11-21 Steel sheet rib bearing structure curtain system

Country Status (1)

Country Link
CN (1) CN206189680U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108331215A (en) * 2018-04-25 2018-07-27 中国建筑西南设计研究院有限公司 A kind of combination stressed curtain wall construction system
CN108412095A (en) * 2018-03-16 2018-08-17 杭州市建筑设计研究院有限公司 A kind of lattice supporting framework of high large span curtain wall
CN109339300A (en) * 2018-11-12 2019-02-15 华侨大学 A kind of drag-line Glass Rib curtain wall system
CN109339302A (en) * 2018-11-12 2019-02-15 华侨大学 A kind of steel and aluminum combined unit glass curtain wall
CN114607077A (en) * 2022-04-11 2022-06-10 山东津单幕墙有限公司 Steel plate rib curtain wall system
CN114737708A (en) * 2022-06-14 2022-07-12 北京建工集团有限责任公司 Frame curtain wall system suitable for horizontal super large span and vertical super high span

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108412095A (en) * 2018-03-16 2018-08-17 杭州市建筑设计研究院有限公司 A kind of lattice supporting framework of high large span curtain wall
CN108412095B (en) * 2018-03-16 2020-02-18 杭州市建筑设计研究院有限公司 Truss supporting structure of high-large-span curtain wall
CN108331215A (en) * 2018-04-25 2018-07-27 中国建筑西南设计研究院有限公司 A kind of combination stressed curtain wall construction system
CN109339300A (en) * 2018-11-12 2019-02-15 华侨大学 A kind of drag-line Glass Rib curtain wall system
CN109339302A (en) * 2018-11-12 2019-02-15 华侨大学 A kind of steel and aluminum combined unit glass curtain wall
CN109339302B (en) * 2018-11-12 2023-11-21 华侨大学 Steel-aluminum combined unit type glass curtain wall
CN114607077A (en) * 2022-04-11 2022-06-10 山东津单幕墙有限公司 Steel plate rib curtain wall system
CN114607077B (en) * 2022-04-11 2023-09-12 山东津单幕墙有限公司 Steel plate rib curtain wall system
CN114737708A (en) * 2022-06-14 2022-07-12 北京建工集团有限责任公司 Frame curtain wall system suitable for horizontal super large span and vertical super high span

Similar Documents

Publication Publication Date Title
CN206189680U (en) Steel sheet rib bearing structure curtain system
CN105332452B (en) Cable curtain wall supporting system and its construction method of a kind of top provided with steel truss
CN106088360B (en) A kind of two-tube lower edge connecting node of large span list truss structure and truss structure
CN105544820B (en) Curtain wall support steel structure and its construction method outside curved surface with spring assembly sunpender
CN107268422A (en) Across the self-anchored type suspension cable arched girder co-operative system bridge such as one kind
CN110295548A (en) The makeshift device of mechanical balance is maintained under the bridge construction technique of fitting the arch first then fitting the girder
CN205976120U (en) Braced system and large -span stone material moulding of large -span stone material moulding
CN108331215A (en) A kind of combination stressed curtain wall construction system
CN204609099U (en) The netted furred ceiling of large span
US3872632A (en) Suspended structure
CN104763088B (en) For the cable wire supporting network of the netted ceiling system of large span
CN2447437Y (en) Double-wirerope adjusting fixing means for use in point-connecting glass curtain wall
JP2005023525A (en) Mullion support structure of curtain wall and its construction method
CN218492796U (en) Hidden cable type curtain wall connection assembly
CN204609089U (en) For the cable wire supporting network of the netted ceiling system of large span
JP2005146772A (en) Roof supporting structural body unit, large space roof structure and construction methods of them
CN101343900B (en) Large-span non-upright post curtain wall system
CN215254919U (en) Scenic pavilion based on integral tensioning structure
CN205855864U (en) A kind of building tower crane of stable safety
CN214576704U (en) A safe ladder of hanging for steel construction factory building construction
CN204753343U (en) Single tower cable -stay bridge of bridge floor is arranged to non - symmetry plane broken line
CN213114967U (en) Steel grid structure with good stability for building production
CN202450535U (en) Safe suspension device for open cut foundation pit
CN213141177U (en) Concrete member hoist device
CN214899969U (en) High-strength subway bridge

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant