CN206186109U - Mix building heating heat preservation device - Google Patents
Mix building heating heat preservation device Download PDFInfo
- Publication number
- CN206186109U CN206186109U CN201621260432.7U CN201621260432U CN206186109U CN 206186109 U CN206186109 U CN 206186109U CN 201621260432 U CN201621260432 U CN 201621260432U CN 206186109 U CN206186109 U CN 206186109U
- Authority
- CN
- China
- Prior art keywords
- water
- heating
- mixing
- pipeline
- mix
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Preparation Of Clay, And Manufacture Of Mixtures Containing Clay Or Cement (AREA)
Abstract
The utility model discloses a mix building heating heat preservation device, include mixed water pitcher (7) that link to each other through hot water waterline (17) and add hot -water cylinder (9), mix water pitcher (7) through first water intaking pipeline (11), a in -take pump (8) link to each other with water source (12), it still is connected with mix device (14) through warm water waterline (13) to mix water pitcher (7), add hot -water cylinder (9) through second water intaking pipeline (15), the 2nd in -take pump (10) link to each other with water source (12), it still is not connected through delivery duct line (16) and aggregate storehouse ground pipe laying line (2) to add hot -water cylinder (9). The utility model discloses two systems integrate with mix water and aggregate heating heat preservation, reach the nimble mix water temperature of adjusting, guarantee the purpose of aggregate temperature, have optimized on -the -spot heat preservation, curing condition simultaneously, and energy saving when reaching the heat preservation effect satisfies highlands winter construction requirement.
Description
Technical field
The utility model is related to the heating and heat-insulating device of mixing building, the particularly heating and thermal insulation of mixing water heating and aggregate bin
Structure.
Background technology
Current China's new energy installed capacity is 1.7 hundred million KW, occupies the first in the world, accounts for the 1/4 of whole world total amount.According to
" 13 " planning for the expansion of power grids, it is contemplated that to the year two thousand twenty, national generation of electricity by new energy installed capacity is up to 4.1 hundred million KW, wherein wind-powered electricity generation 2.4
Hundred million KW.Highlands is good because of its wind condition, is increasingly becoming planning wind field area the most suitable, same opportunity the advantages of arable land is few
Pool-size is also being improved, therefore blower foundation quality requirement is also gradually stepped up.
Huaneng Group Butuo second phase (mending you) wind power plant is located in Butuo County Bu Er townshiies and Huo Lie townshiies territorial scope, and project planning is built
If 25 single-machine capacity 2.0MW blower fan units, wherein limit a power 1.5MW, wind power plant total installation of generating capacity 49.5MW.Wind power plant
Using FD108C-000105HSM type wind power generating sets, all superstructures such as blower fan unit are relied on and are embedded in blower foundation in advance
Foundation ring is supported, and foundation ring radius 2.15m axial fan hubs centre-height is 85m, and unit and tower always weigh about 318.5t.
Because most of current Sichuan province wind power plant be located at alpine region, such as Ganzi, Aba Prefecture, Goats in Liangshan Prefecture, such
Areas comprehensive situation is similar to Butuo County, and positioned at highlands, weather conditions are severe, and economy falls behind relatively, to concrete construction
Especially winter construction causes heating and the attemperator of certain difficulty, particularly aggregate and sandstone, in order to smoothly complete
Blower foundation concrete placings are, it is necessary to the adaptable heating in mixing plant attemperator of design and construction environment.
The content of the invention
The technical problems to be solved in the utility model is:A kind of heating in mixing plant attemperator is provided, compared to existing heating
Heat-insulation system, mixing water heating and aggregate heating and thermal insulation two-in-one no longer work independently, and reach flexible modulation mixing water water
The purpose of temperature, while further improving the effect of aggregate bin aggregate heating and thermal insulation, energy saving.
The technical solution of the utility model is as follows:
A kind of heating in mixing plant attemperator, including the mixing water pot and heating jug being connected by hot water waterline,
Mixing water pot is connected through the first water intaking pipeline, the first water pump with water source, and mixing water pot also passes through warm water waterline and mix
Device is connected, and heating jug is connected through the second water intaking pipeline, the second water pump with water source, and heating jug also passes through steam pipeline
Line is connected with aggregate bin buried pipeline;The buried pipeline is close to aggregate bin ground lower surface, and buried pipeline is S-shaped, and adjacent two
It is groove between root pipeline, is filled with outermost two grooves and Heat Conduction Material is filled with thermal insulation mortar, remaining groove;Institute
The partition wall upper end stated between adjacent aggregate bin is provided with air exchange window.Heating tank and blending tank independently take cold water, are provided simultaneously with adding
Hot water can be supplied to blending tank by the heating tank of hot merit energy again, and then passing through the cold and hot mixed warm water of blending tank can be directly defeated
MIXING SYSTEM CONTROLLED BY is delivered to, and the steam that the hot water from heating tank is formed can supply aggregate bin heating and thermal insulation, then by MIXING SYSTEM CONTROLLED BY
Warm water supply and aggregate bin hot water supply be incorporated into together, save the consumption of heating material.Further, this programme changes
Enter the structure of aggregate bin ground preheating embedding line, groove structure added between adjacent two pipelines of pre-buried steam pipe line,
In addition to thermal insulation mortar is filled in the groove at most two ends, Heat Conduction Material is filled in remaining groove.Such purpose is to improve heat transfer
Efficiency, reduce the loss of heat energy, due to the presence of groove, jet chimney increases with the contact area of aggregate bin bottom surface, relatively
In the design of existing un-grooved, heat transfer area is increased.The Heat Conduction Material placed in groove rapidly can conduct groove surfaces
Heat absorption and be transferred to its top stack aggregate in.Thermal insulation mortar is placed in the groove of outermost end, for limiting heat
Scattered and disappeared to two ends outside.The exchange of hot-air is carried out between adjacent aggregate bin by the air exchange window on partition wall, is formed
Convection current, further balances the temperature of each aggregate bin, makes full use of heat energy.
The aggregate bin enters vapour direction and is followed successively by sand feed bin, gravelstone feed bin and middle building stones storehouse along steam pipeline.Due to
Pipeline pressure and temperature in steam course of conveying can be reduced, therefore, when considering that pipeline is moved towards, in view of specific heat capacity property is not
Together, pay the utmost attention to enter sand feed bin, next to that gravelstone feed bin, is finally middle building stones storehouse, so heat can be sufficiently sharp
With.
Air exchange window has two, the isometry position on partition wall, is mounted therein with the opposite ventilation fan of airflow direction,
Used in air exchange fan forms the interior circulation in storehouse in the air in each aggregate bin of forced circulation.
The heating jug is coal-burning boiler.
The Heat Conduction Material is the steel plate for overlapping successively, and the heat conductivility of steel plate is better than aggregate bin ground, by one block of block steel
It is put into groove after plate superposition is fixed, laminated steel plate is brought rapidly up from after surrounding heat absorption, is conducted to heat as heat-conducting medium
The aggregate that top is piled up.Steel plate easily makes, and constructs very convenient.
The partition wall and ceiling surface of the aggregate bin have adiabator layer, in order to reduce shadow of the outside climatic to aggregate bin
Ring, partition wall and ceiling inner surface are each coated with insulation material.
The utility model is integrated mixing water of the prior art heating with aggregate heating and thermal insulation two systems, no longer
Work independently, reach flexible modulation mixing water water temperature, it is ensured that the purpose of aggregate temperature.The utility model optimize scene insulation,
Curing condition, energy saving while reaching heat insulation effect meets highlands winter construction requirement.
Brief description of the drawings
Fig. 1 is planar structure schematic diagram of the present utility model;
Fig. 2 is the structural representation of aggregate bin in the utility model.
Specific embodiment
As shown in Fig. 1~2, heating in mixing plant attemperator is included by mixing that hot water waterline 17 is connected with heat-exchanger pump
Heshui tank 7 and heating jug 9, heating jug 9 are coal-burning boiler.Mixing water pot 7 is through the first water intaking pipeline 11, the first water pump 8
It is connected with water source 12, mixing water pot 7 is also connected by warm water waterline 13 with mixing device 14, and heating jug 9 takes through second
Water pipeline 15, the second water pump 10 are connected with water source 12, and heating jug 9 is also by steam pipeline 16 and aggregate bin underground pipe
Line 2 is connected, and buried pipeline 2 is close to aggregate bin ground lower surface, and aggregate bin enters vapour direction and is followed successively by sand material along steam pipeline
Storehouse 18, gravelstone feed bin 19 and middle building stones storehouse 20, the partition wall 3 and ceiling surface of aggregate bin have adiabator layer.Buried pipeline 2 is in S
Shape, is rectangular recess 4 between adjacent two pipelines, thermal insulation mortar is filled with outermost two grooves 4, in remaining groove 4
Filled with Heat Conduction Material 5, Heat Conduction Material 5 is the steel plate for overlapping successively.The upper end of partition wall 3 between adjacent aggregate bin is provided with air friendship
Window 6 is changed, air exchange window 6 has two, the isometry position on partition wall 3, be mounted therein with the opposite ventilation fan of airflow direction.
Heating tank 9 is used to heat up water, and on the one hand provides steam to aggregate bin bottom, and defrosting heating is carried out to sandstone aggregate, on the other hand carries
In supplying hot water to blending tank 7, hot water and cold water are controlled by controlling two water pump (heat-exchanger pump and the first water pump) times of pumping
Ratio, and then the flexibly temperature of control mixing water.
Claims (6)
1. a kind of heating in mixing plant attemperator, it is characterised in that:Including the mixing water being connected by hot water waterline (17)
Tank (7) and heating jug (9), mixing water pot (7) are connected through the first water intaking pipeline (11), the first water pump (8) with water source (12),
Mixing water pot (7) is also connected by warm water waterline (13) with mixing device (14), and heating jug (9) is through the second water intaking pipeline
(15), the second water pump (10) is connected with water source (12), and heating jug (9) is also by steam pipeline (16) and aggregate bin ground
Buried pipeline (2) is connected;
The buried pipeline (2) is close to aggregate bin ground lower surface, and buried pipeline (2) is S-shaped, is recessed between adjacent two pipelines
It is filled with groove (4), outermost two grooves (4) and Heat Conduction Material (5) is filled with thermal insulation mortar, remaining groove (4);
Partition wall (3) upper end between the adjacent aggregate bin is provided with air exchange window (6).
2. a kind of heating in mixing plant attemperator according to claim 1, it is characterised in that:The aggregate bin is defeated along steam
Send pipeline to enter vapour direction and be followed successively by sand feed bin (18), gravelstone feed bin (19) and middle building stones storehouse (20).
3. a kind of heating in mixing plant attemperator according to claim 1, it is characterised in that:Air exchange window (6) has
Two, the isometry position on partition wall (3) is mounted therein with the opposite ventilation fan of airflow direction.
4. a kind of heating in mixing plant attemperator according to claim 1, it is characterised in that:The heating jug (9) is
Coal-burning boiler.
5. a kind of heating in mixing plant attemperator according to claim 1, it is characterised in that:The Heat Conduction Material (5) is
The steel plate for overlapping successively.
6. a kind of heating in mixing plant attemperator according to claim 1, it is characterised in that:The partition wall of the aggregate bin
And ceiling surface has adiabator layer (3).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621260432.7U CN206186109U (en) | 2016-11-21 | 2016-11-21 | Mix building heating heat preservation device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621260432.7U CN206186109U (en) | 2016-11-21 | 2016-11-21 | Mix building heating heat preservation device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206186109U true CN206186109U (en) | 2017-05-24 |
Family
ID=58725462
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621260432.7U Active CN206186109U (en) | 2016-11-21 | 2016-11-21 | Mix building heating heat preservation device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206186109U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114505956A (en) * | 2022-03-07 | 2022-05-17 | 中国十七冶集团有限公司 | Winter construction heat preservation device for mixing station and construction method |
-
2016
- 2016-11-21 CN CN201621260432.7U patent/CN206186109U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114505956A (en) * | 2022-03-07 | 2022-05-17 | 中国十七冶集团有限公司 | Winter construction heat preservation device for mixing station and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104728979B (en) | A kind of Renovation of air-conditioning system method and apparatus of application all-weather solar heat supply | |
CN104344603B (en) | Utilize buried pipe ground-source heat pump system and the method for paddy electricity auxiliary heat supplying/cooling | |
CN207050228U (en) | A kind of solid heat storage device | |
CN105910200A (en) | Double-end air source heat pump system with floor heating module made of phase change heat storage material | |
CN106545876A (en) | Method for heating shaft by using flue gas generated after heat storage and oxidation of gas | |
CN105009998A (en) | Solar energy and geothermal energy composite greenhouse | |
CN107975859A (en) | A kind of regenerative electrochemical geothermal system | |
CN206186109U (en) | Mix building heating heat preservation device | |
CN204762526U (en) | Compound greenhouse of solar energy and geothermal energy | |
CN101387458A (en) | Low grade heat energy directly utilizing system and method | |
CN101625161B (en) | Double heat absorption combined solar energy air heater | |
CN206113086U (en) | Solar floor heating system | |
CN203628815U (en) | Fire pit-coil pipe-Kang coupled heating system | |
CN204063227U (en) | A kind of combination energy-saving heating system comprising UTILIZATION OF VESIDUAL HEAT IN Cycling hot-blast heating system | |
CN202902417U (en) | Environment-protecting and energy-saving superconducting pipe floor heating system | |
CN101387459B (en) | Solar and superficial layer geoenergy complementary construction energy utilization method | |
CN214353343U (en) | High and cold high-altitude concrete aggregate preheating system | |
CN203848366U (en) | Solar air combination heat supply system for village and small town houses | |
CN204901901U (en) | Radiate heating plant with phase -change thermal floor that air source heat pump combines | |
CN204787317U (en) | New forms of energy boiler | |
CN202747613U (en) | Geothermal energy heating device of petroleum transmission pipeline | |
CN103216005A (en) | Green constant temperature building | |
CN103759322B (en) | Combustion pool-coil pipe-kang coupling heating system | |
CN203274037U (en) | Convection and radiation compound type solar hot air heating system | |
CN204165170U (en) | Utilize the buried pipe ground-source heat pump system of the auxiliary cold-storage/accumulation of heat of paddy electricity |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |