CN206180541U - High stability line conductor conductor spacer - Google Patents

High stability line conductor conductor spacer Download PDF

Info

Publication number
CN206180541U
CN206180541U CN201621185493.1U CN201621185493U CN206180541U CN 206180541 U CN206180541 U CN 206180541U CN 201621185493 U CN201621185493 U CN 201621185493U CN 206180541 U CN206180541 U CN 206180541U
Authority
CN
China
Prior art keywords
support bar
bar
annular guide
bracing piece
guide post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621185493.1U
Other languages
Chinese (zh)
Inventor
戴强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201621185493.1U priority Critical patent/CN206180541U/en
Application granted granted Critical
Publication of CN206180541U publication Critical patent/CN206180541U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

High stability line conductor conductor spacer, including first bracing piece and second bracing piece, the one end of first bracing piece articulates with the one end of second bracing piece, and a lead wire gripper device is all installed to the other end of first bracing piece and the other end of second bracing piece, the lead wire gripper device includes the dead lever, and an elastic plate is all installed at the both ends of dead lever, the utility model discloses a push rod motor combines with annular guide bar, makes first bracing piece and second bracing piece use by oneself and fixes suitable angle to make the second bracing piece can carry out interval control to the wire of different angles, annular guide bar can the firm degree of the annular guide bar of maximum improvement for circle annular rod, avoids annular guide bar to damage.

Description

High stability line conductor conductor spacer
Technical field
The utility model is related to a kind of conductor spacer, specifically a kind of high stability line conductor conductor spacer.
Background technology
Line conductor is arranged using horizontal split, to prevent damaging because of whiplash, as soon as every segment distance, will with conductor spacer Two wires are fixed, and make two cable keeping parallelism states.Because the influence of wind-force is that wire produces vibration, conductor spacer is caused to turn round Bent, slip and fracture.Can wear and tear wire after conductor spacer distortion, be wire strand breakage, can more seriously make wire fracture, conductor spacer fracture Just lose the protective action of itself completely afterwards, wire can equally be damaged because of whiplash.Existing high stability line conductor interval Rod is only used for parallel polygon control survey spacing, it is impossible to which the wire to there is certain angle enters line space control.Existing adjustable line Line conductor conductor spacer is lighter due to itself, it is impossible to play stabilization to circuit well.
Utility model content
The purpose of this utility model is to provide a kind of high stability line conductor conductor spacer, can solve the problem that above mentioned problem.
The utility model to achieve the above object, is achieved through the following technical solutions:Between a kind of high stability line conductor Every rod, including first support bar and second support bar, one end of first support bar is hinged with one end of second support bar, first The other end of strut and the other end of second support bar are respectively mounted a wire clamping device, and the wire clamping device includes solid Fixed pole, the two ends of fix bar are respectively mounted an elastic plate, and cable clip, the curved tabular knot of cable clip are installed in the end of elastic plate Structure, the cable clip on two elastic plates is mutually fastened can form a tubular structure, and elastic plate is the resilient platy structure of tool, Annular guide post is installed, annular guide post is annular pole, the center of circle of annular guide post and first support bar in first support bar Pin joint with second support bar is overlapped, and arcuate socket is opened up in second support bar, and annular guide post passes through arcuate socket, and annular is oriented to The several through holes of side Zhou Kaishe of bar, the sidepiece of second support bar installs push-rod electric machine, and the pull bar of push-rod electric machine can be inserted with through hole Cooperation is connect, the sidepiece of first support bar installs air-bubble level.First extension bar is installed in first support bar, the first extension bar The first weighted spherical ball is installed in end, and the second extension bar is installed in second support bar, and the second weighted spherical ball is installed in the end of the second extension bar, Spring is installed, the 3rd weighted spherical ball is installed at the middle part of spring between the first weighted spherical ball and the second weighted spherical ball.
In order to further realize the purpose of this utility model, following technical scheme can also be used:The first support bar Sidepiece to set first raised.It is raised that the sidepiece of the second support bar sets second.
The utility model has the advantage of:First weighted spherical ball of the present utility model, the second weighted spherical ball and the 3rd weighted spherical ball association With coordinating, the quality at high stability line conductor conductor spacer two ends and middle part is improve, so as to substantially increase high stability line For the stabilization of power transmission line, spring of the present utility model can be such that weighted spherical ball is led in high stability circuit to line conductor conductor spacer Stabilization is played to high stability line conductor conductor spacer by swing when line conductor spacer is given a shock, so that high stability Line conductor conductor spacer plays stabilization to power transmission line.Push-rod electric machine of the present utility model is combined with annular guide post, makes the One support bar and second support bar can use by oneself and be fixed to suitable angle, so that second support bar can be to different angles Wire enters line space control, and annular guide post can farthest improve annular guide post firmness, keep away for annular pole Exempt from annular guide post to damage.Push-rod electric machine of the present utility model can be adjusted to suitable angular in first support bar and second support bar Coordinate with through hole grafting when spending, first support bar and second support bar is fixed on suitable angle.Elasticity of the present utility model Plate coordinates for the resilient platy structure of tool can facilitate cable clip to open with cable.On two elastic plates of the present utility model Cable clip mutually fastens and can form a tubular structure cable clip can be made to adapt to the profile of cable, reduces cable clip and cable Friction.Air-bubble level of the present utility model can facilitate operating personnel to observe the angle case of cable.The utility model also has Have the advantages that simple for structure compact, cheap for manufacturing cost and easy to use.
Brief description of the drawings
Fig. 1 is main structure diagram of the present utility model;Fig. 2 is left view structural representation of the present utility model.
Specific embodiment
High stability line conductor conductor spacer, as shown in figure 1, including first support bar 3 and second support bar 8, first One end of strut 3 is hinged with one end of second support bar 8, and the other end of first support bar 3 and the other end of second support bar 8 are equal One wire clamping device is installed, the wire clamping device includes fix bar 9, and the two ends of fix bar 9 are respectively mounted an elasticity Cable clip 1 is installed in plate 2, the end of elastic plate 2, and the curved platy structure of cable clip 1, the cable clip 1 on two elastic plates 2 is mutual Fastening can form a tubular structure, and elastic plate 2 is the resilient platy structure of tool, annular is installed in first support bar 3 and is oriented to Bar 5, annular guide post 5 is annular pole, the center of circle and first support bar 3 and the pin joint of second support bar 8 of annular guide post 5 Overlap, arcuate socket 12 is opened up in second support bar 8, annular guide post 5 passes through arcuate socket 12, the side Zhou Kaishe of annular guide post 5 Several through holes 6, the sidepiece of second support bar 8 installs push-rod electric machine 7, and the pull bar of push-rod electric machine 7 can coordinate with the grafting of through hole 6, The sidepiece of first support bar 3 installs air-bubble level 4.First extension bar 19 is installed in first support bar 3, the first extension bar 19 The first weighted spherical ball 20 is installed in end, and the second extension bar 23 is installed in second support bar 8, and the end of the second extension bar 23 installs second Weighted spherical ball 21, installs spring 22 between the first weighted spherical ball 20 and the second weighted spherical ball 21, the 3rd weighted spherical ball is installed at the middle part of spring 22 14。
First weighted spherical ball 20 of the present utility model, the second weighted spherical ball 21 and the coordinated of the 3rd weighted spherical ball 24, improve height Stability line line conductor conductor spacer two ends and the quality at middle part, so as to substantially increase high stability line conductor conductor spacer for The stabilization of power transmission line, spring of the present utility model 22 can be such that weighted spherical ball 24 is subject in high stability line conductor conductor spacer Stabilization is played to high stability line conductor conductor spacer by swing during vibrations, so that high stability line conductor is spaced Rod plays stabilization to power transmission line.Swing buffering smaller compared to the influence that fixed buffering is caused to circuit.The utility model Push-rod electric machine 7 combined with annular guide post 5, first support bar 3 and second support bar 8 is used by oneself and be fixed to suitable angle Degree, so that second support bar 8 can enter line space control to the wire of different angles, annular guide post 5 can for annular pole Farthest to improve the annular firmness of guide post 5, it is to avoid annular guide post 5 is damaged.Push-rod electric machine of the present utility model 7 Can coordinate with the grafting of through hole 6 when first support bar 3 and second support bar 8 are adjusted to proper angle, make the He of first support bar 3 Second support bar 8 is fixed on suitable angle.Elastic plate of the present utility model 2 can be conveniently electric for the resilient platy structure of tool Cable clip 1 is opened and coordinated with cable.Cable clip 1 on two elastic plates 2 of the present utility model is mutually fastened and can form a tubulose Structure can make cable clip 1 adapt to the profile of cable, reduce the friction of cable clip 1 and cable.Bubble level of the present utility model Instrument 4 can facilitate operating personnel to observe the angle case of cable.
The sidepiece of the first support bar 3 sets the first projection 10.First projection 10 of the present utility model can increase by The deadweight of one support bar 3, improves the stability of high stability line conductor conductor spacer.
The sidepiece of the second support bar 8 sets the second projection 11.Second projection 11 of the present utility model can increase by The deadweight of one support bar 3, improves the stability of high stability line conductor conductor spacer.
The technical solution of the utility model is not restricted in the range of embodiment described in the utility model.This practicality is new The technology contents of the not detailed description of type are known technology.

Claims (3)

1. high stability line conductor conductor spacer, it is characterised in that:Including first support bar (3) and second support bar (8), first One end of support bar (3) is hinged with one end of second support bar (8), the other end and second support bar (8) of first support bar (3) The other end be respectively mounted a wire clamping device, the wire clamping device includes fix bar (9), the two ends of fix bar (9) An elastic plate (2) is respectively mounted, cable clip (1), cable clip (1) curved platy structure, two are installed in the end of elastic plate (2) Cable clip (1) on elastic plate (2) is mutually fastened and can form a tubular structure, and elastic plate (2) is the resilient tabular knot of tool Structure, installs annular guide post (5) in first support bar (3), annular guide post (5) is annular pole, the circle of annular guide post (5) The heart is overlapped with the pin joint of first support bar (3) and second support bar (8), and arcuate socket (12), ring are opened up in second support bar (8) Shape guide post (5) through arcuate socket (12), the several through holes of the side Zhou Kaishe (6) of annular guide post (5), second support bar (8) Sidepiece installs push-rod electric machine (7), and the pull bar of push-rod electric machine (7) can coordinate with through hole (6) grafting, the side of first support bar (3) Air-bubble level (4) is installed in portion, and the first extension bar (19), the end peace of the first extension bar (19) are installed in first support bar (3) The first weighted spherical ball (20) is filled, the second extension bar (23) is installed in second support bar (8), the end of the second extension bar (23) installs the Two weighted spherical balls (21), install spring (22), the middle part peace of spring (22) between the first weighted spherical ball (20) and the second weighted spherical ball (21) Fill the 3rd weighted spherical ball (24).
2. high stability line conductor conductor spacer according to claim 1, it is characterised in that:The first support bar (3) Sidepiece first raised (10) are set.
3. high stability line conductor conductor spacer according to claim 1, it is characterised in that:The second support bar (8) Sidepiece second raised (11) are set.
CN201621185493.1U 2016-11-04 2016-11-04 High stability line conductor conductor spacer Expired - Fee Related CN206180541U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621185493.1U CN206180541U (en) 2016-11-04 2016-11-04 High stability line conductor conductor spacer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621185493.1U CN206180541U (en) 2016-11-04 2016-11-04 High stability line conductor conductor spacer

Publications (1)

Publication Number Publication Date
CN206180541U true CN206180541U (en) 2017-05-17

Family

ID=58681088

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621185493.1U Expired - Fee Related CN206180541U (en) 2016-11-04 2016-11-04 High stability line conductor conductor spacer

Country Status (1)

Country Link
CN (1) CN206180541U (en)

Similar Documents

Publication Publication Date Title
KR101979416B1 (en) A Distribution Track Space Maintenance
CN206180541U (en) High stability line conductor conductor spacer
CN206180542U (en) Adjustable line conductor conductor spacer
CN205164037U (en) Mini -type arm strength device
CN203967633U (en) A kind of aerial cable aid
KR100830711B1 (en) Distribution line supporting apparatus
CN215448768U (en) Sponge eye-shade tensile test machine
CN105119226A (en) Stockbridge damper on power transmission line
CN204012590U (en) Stockbridge damper
CN205178446U (en) Last stockbridge damper of transmission line
CN209237291U (en) One kind aiminging drill device
CN210091824U (en) Insulator with damping device
CN204161241U (en) A kind of navigator support
CN204068155U (en) A kind of lead spacer with pooling feature
CN206820801U (en) The self-timer of mobile phone can be placed anyhow
CN202031193U (en) Anti-seismic device of building
CN105920836A (en) Game clamping jaw having hanging measurement function
CN202395403U (en) Adjustable anti-resonance cardan
CN207910397U (en) A kind of pipeline hidden danger arrester
CN105896437A (en) Conductor spacing device
CN204668880U (en) A kind of conductor spacing device
CN205562883U (en) Optic fibre swing joint device
CN205460636U (en) High -speed rope skipping of bearing
CN208227270U (en) A kind of telescopic earphone wire-wrap board with cellphone support function
CN110429544A (en) Double bundle conductor anti-bouncing spacer soft connection device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170517

Termination date: 20171104

CF01 Termination of patent right due to non-payment of annual fee