CN206178969U - Engineering cost progress monitoring device - Google Patents
Engineering cost progress monitoring device Download PDFInfo
- Publication number
- CN206178969U CN206178969U CN201621212755.9U CN201621212755U CN206178969U CN 206178969 U CN206178969 U CN 206178969U CN 201621212755 U CN201621212755 U CN 201621212755U CN 206178969 U CN206178969 U CN 206178969U
- Authority
- CN
- China
- Prior art keywords
- unit
- casing
- elastic component
- observation window
- schedule monitoring
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
This patent application belongs to the auxiliary construction equipment field, specifically discloses an engineering cost progress monitoring device, including box, construction progress display unit, touching unit, the control unit and progress control unit, be equipped with first observation window and a plurality of second observation window on the box, construction progress display unit corresponds the setting with first observation window, progress control unit corresponds the setting with the second observation window, the touching unit is fixed on construction progress display unit, when construction progress display unit rotates, touching unit trigger switch, but progress control unit is in on -state. Compare with traditional progress monitoring device, this scheme can realize two -way feedback, and staff and cost personnel carry out fine understanding each other, the carrying out of the work of not being convenient for.
Description
Technical field
The utility model belongs to building auxiliary equipment field.
Background technology
At present, the engineering that enterprise can be to being accepted before bid for being responsible for calling for bid makes construction costs, existing cost
The information that flow is provided for staff according to owner, and the information for oneself being obtained to site inspection is carried out to the engineering accepted
The work that cost is calculated.Due to the cumbersome of cost work, it is necessary to the work to cost staff exercises supervision, and at present can only
The cost of cost staff is worked by related personnel is exercised supervision, do not meet the requirement now to office automatic, together
When need extra work personnel, cause the waste of human resources.
Number of patent application is the patent of CN201520794193.2, discloses a kind of construction costs progress control system, is wrapped
Included servomotor, left shaft holder, screw mandrel, nut, right axle bearing, pole, controller, control panel, connecting rod, progress plate and
Indicator lamp;The left surface of progress plate is provided with control panel and controller, and controller is controlled located at the top of control panel
Panel is connected with controller.It is unintelligible to construction costs progress that the program overcomes cost staff, it is difficult to construction costs
Progress and working time distribution carry out Reasonable adjustment, the shortcoming for increasing work management difficulty.
However, although cost personnel can know that the progress of work, but whether staff is not aware that cost personnel
Solution situation, the program can only unidirectionally be fed back, it is impossible to so that staff and cost personnel are understood well each other, be not easy to
The development of work.
Utility model content
The purpose of this utility model is to provide a kind of construction costs Schedule monitoring device of energy Two-way Feedback.
In order to achieve the above object, base case of the present utility model provides a kind of construction costs Schedule monitoring device, bag
Casing, construction speed display unit, touching unit, control unit and Schedule monitoring unit are included, the casing is provided with the first sight
Window and multiple second observation windows are examined, the construction speed display unit is correspondingly arranged with the first observation window, the Schedule monitoring list
Unit is correspondingly arranged with the second observation window, and the touching unit is fixed on construction speed display unit, the construction speed displaying
During unit rotational, touching unit triggers switch, Schedule monitoring unit is in can conducting state.
The principle of this base case is:Workmen complete after construction, often operation then rotate once construct into
Degree display unit, with the job schedule for telling monitoring personnel current.Meanwhile, monitoring personnel is knowing the job schedule of workmen
Afterwards, then monitoring unit is controlled, monitoring information is shown, allow workmen to understand the situation of monitoring.
The beneficial effect of this base case is:After construction speed display unit being rotated due to necessary workmen, progress
Monitoring unit can just be in the state that can be turned on, and monitoring personnel can just carry out the operation of Schedule monitoring unit, effectively avoid
The maloperation of monitoring personnel.Compared with traditional Schedule monitoring device, this programme can realize Two-way Feedback, staff and cost
Personnel are understood well each other, are not easy to the development of work.
Scheme two:Scheme is preferred based on this, and the construction speed display unit includes polygon prism, and the polygon prism turns
Dynamic to be arranged in casing, each side of the polygon prism is provided with construction speed bar.Each side of polygon prism then represents one
Individual construction speed, simple structure, it is that may be viewed by rotate corresponding side and be directed at the first observation window, is checked conveniently.
Scheme three:This is preferred for scheme two, the Schedule monitoring unit include electromagnet, installing plate, the first elastic component,
Lantern and iron block are folded, the installing plate is fixed in casing, and first elastic component is connected between installing plate and iron block, institute
The one end for stating folding lantern is fixed on a mounting board, and the other end is fixed on iron block, and first elastic component is located at and folds lantern
Interior, when the electromagnet is powered off, iron block is located at the top of the second observation window, and when the electromagnet is powered, iron block is inhaled with electromagnet
Draw together, the folding lantern is provided with Schedule monitoring bar.
When workmen rotate polygon prism after, then the circuit of electromagnet be in can conducting state, now, monitoring personnel is only needed
Control the switch of electromagnet, electromagnet to produce magnetic force, you can to draw down iron plate, and then stretch folding lantern so that fold
Schedule monitoring bar on lantern is located at the position of the second observation window, you can the progress of convenient construction personnel's checking monitoring.
Scheme four:This is preferred for scheme three, and the touching unit includes being arranged on top and and the polygon prism of polygon prism
The corresponding projection in each side, each projection gradually increases along clockwise direction, described control unit include push rod, frizzen and
Controlling organization, the controlling organization includes depression bar, the second elastic component, the 3rd elastic component, mounting seat and controlling switch, the push rod
It is corresponding with projection, and slide laterally and be arranged in casing, the elastic component is connected between casing and push rod, and the frizzen is consolidated
It is scheduled on push rod, the mounting seat is fixed in casing, the controlling switch is arranged in mounting seat, the 3rd elastic component connects
It is connected between depression bar and mounting seat, the other end that the depression bar is connected with the 3rd elastic component is hinged in casing, the control machine
The quantity of structure is corresponding with the quantity of observation window, and each controlling switch controls a circuit for electromagnet.
Cause that frizzen is located at different positions according to raised thickness difference, so as to promote depression bar to trigger control open
Close so that electromagnet is in the state that can be turned on.
Scheme five:This is preferred for scheme four, and the 3rd elastic component is rubber parts.Rubber parts have good
Insulating effect, high safety.
Scheme six:This is preferred for scheme five, and the surface of the iron block is provided with one layer of antirust coat.Antirust coat can be played
Good anti-rust action, can improve the service life of iron block.
Brief description of the drawings
Fig. 1 is a kind of structural representation of construction costs Schedule monitoring device of the utility model embodiment.
Fig. 2 is the sectional view of Fig. 1.
Fig. 3 is the structural representation of polygon prism in the present embodiment.
Fig. 4 is the structural scheme of mechanism of touching unit in the present embodiment.
Specific embodiment
The utility model is described in further detail below by specific embodiment:
Reference in Figure of description includes:Casing 10, the first observation window 101, the second observation window 102, electromagnet
20th, iron block 30, folding lantern 40, installing plate 50, polygon prism 60, raised 71, push rod 72, frizzen 73, pressing plate 74, controlling switch
75th, mounting seat 76, the 3rd elastic component 77, the second elastic component 78.
As shown in figure 1, a kind of construction costs Schedule monitoring device, including casing 10, construction speed display unit, touching list
Unit, control unit and Schedule monitoring unit, casing 10 are provided with the first observation window 101 and six the second observation windows 102, construct into
Degree display unit is correspondingly arranged with the first observation window 101, and Schedule monitoring unit is correspondingly arranged with the second observation window 102, and touching is single
Unit is fixed on construction speed display unit, when the construction speed display unit is rotated, touching unit triggers switch, progress prison
Control unit is in can conducting state.
As shown in Fig. 2 Schedule monitoring unit includes electromagnet 20, installing plate 50, the first elastic component, folding lantern 40 and iron
Block 30.Installing plate 50 is fixed in casing 10, and the first elastic component is connected between installing plate 50 and iron block 30, folds lantern 40
Upper end is fixed on installing plate 50, and lower end is fixed on iron block 30.The surface of iron block 30 is provided with one layer of antirust coat.Antirust coat
Good anti-rust action can be played, the service life of iron block 30 can be improved.First elastic component is located at and folds in lantern 40, electromagnet
During 20 power-off, iron block 30 is located at the top of the second observation window 102, and when electromagnet 20 is powered, iron block 30 attracts with electromagnet 20
Together, fold lantern 40 and be provided with Schedule monitoring bar.Wherein, the first elastic component uses stainless steel stage clip, and using effect is more preferable.Enter
Degree monitoring bar is marked with pre-set monitoring information, and it is mutually matched with the progress of the side of polygon prism 60.Electromagnet 20 is total
Two switches are had, by monitoring personnel control, another switch is triggered a switch when then being rotated by polygon prism 60.
As shown in figure 3, construction speed display unit includes a polygon prism 60, polygon prism 60 uses six prisms, with second
The quantity correspondence of observation window 102.Polygon prism 60 is rotatably arranged in casing 10, each side of polygon prism 60 be provided with construct into
Degree bar.Each side of polygon prism 60 then represents a construction speed, and simple structure rotates corresponding side alignment first and observes
Window 101 may be viewed by, and check conveniently.
As shown in figure 4, touching unit includes being arranged on the top of polygon prism 60 and each side is corresponding with polygon prism 60
Raised 71, each projection 71 gradually increases along clockwise direction.Control unit includes push rod 72, frizzen 73 and controlling organization,
Controlling organization includes depression bar, the second elastic component 78, the 3rd elastic component 77, mounting seat 76 and controlling switch 75, push rod 72 and projection
71 correspondences, and slide laterally and be arranged in casing 10.Elastic component is connected between casing 10 and push rod 72, and frizzen 73 is fixed on
On push rod 72, mounting seat 76 is fixed in casing 10, and controlling switch 75 is arranged in mounting seat 76, and the 3rd elastic component 77 is connected to
Between depression bar and mounting seat 76, the other end that depression bar is connected with the 3rd elastic component 77 is hinged in casing 10.The number of controlling organization
Amount is corresponding with the quantity of observation window, and each controlling switch 75 controls a circuit for electromagnet 20.3rd elastic component 77
It is rubber parts.Rubber parts have good insulating effect, high safety.Second elastic component 78 uses stainless steel pressure
Spring, coefficient of elasticity is high, and using effect is good.
During concrete operations, workmen completes an operation and then rotates a construction speed display unit after construction, often,
So as to inform monitoring personnel construction speed.Meanwhile, electromagnet 20 can be at conducting state.In addition, when monitoring personnel is applied knowing
After the job schedule of workman person, then monitoring unit is controlled so that electromagnet 20 is powered, electromagnet 20 produces magnetic force, you can by iron
Piece draws down, and then stretches folding lantern 40 so that the Schedule monitoring bar folded on lantern 40 is located at the second observation window 102
Position, you can the progress of convenient construction personnel's checking monitoring.
After rotating construction speed display unit due to necessary workmen, Schedule monitoring unit can just be in the shape that can be turned on
State, monitoring personnel can just carry out the operation of Schedule monitoring unit, effectively avoid the maloperation of monitoring personnel.Enter with traditional
Degree supervising device is compared, and this programme can realize Two-way Feedback, and staff and cost personnel are understood well each other, inconvenience
In the development of work.
Above-described is only embodiment of the present utility model, and the general knowledge such as known concrete structure and characteristic is herein in scheme
Excessive description is not made.It should be pointed out that for a person skilled in the art, not departing from the premise of the utility model structure
Under, some deformations and improvement can also be made, these should also be considered as protection domain of the present utility model, and these are all without influence
Effect and practical applicability that the utility model is implemented.This application claims protection domain should be with the content of its claim
It is defined, specific embodiment in specification etc. records the content that can be used for explaining claim.
Claims (6)
1. a kind of construction costs Schedule monitoring device, it is characterised in that including casing, construction speed display unit, touching unit,
Control unit and Schedule monitoring unit, the casing are provided with the first observation window and multiple second observation windows, the construction speed
Display unit is correspondingly arranged with the first observation window, and the Schedule monitoring unit is correspondingly arranged with the second observation window, and the touching is single
Unit is fixed on construction speed display unit, when the construction speed display unit is rotated, touching unit triggers switch, progress prison
Control unit is in can conducting state.
2. a kind of construction costs Schedule monitoring device according to claim 1, it is characterised in that:The construction speed displaying
Unit includes polygon prism, and the polygon prism is rotatably arranged in casing, and each side of the polygon prism is provided with construction speed
Bar.
3. a kind of construction costs Schedule monitoring device according to claim 2, it is characterised in that:The Schedule monitoring unit
Including electromagnet, installing plate, the first elastic component, folding lantern and iron block, the installing plate is fixed in casing, first bullet
Property part be connected between installing plate and iron block, it is described fold lantern one end fix on a mounting board, the other end is fixed on iron block
On, first elastic component is located at and folds in lantern, and when the electromagnet is powered off, iron block is located at the top of the second observation window, institute
When stating electromagnet energization, together with electromagnet attraction, the folding lantern is provided with Schedule monitoring bar to iron block.
4. a kind of construction costs Schedule monitoring device according to claim 3, it is characterised in that:The touching unit includes
The top of polygon prism and projection corresponding with each side of polygon prism are arranged on, each projection gradually increases along clockwise direction,
Described control unit includes push rod, frizzen and controlling organization, and the controlling organization includes depression bar, the second elastic component, the 3rd bullet
Property part, mounting seat and controlling switch, the push rod is corresponding with projection, and slides laterally and be arranged in casing, and the elastic component connects
It is connected between casing and push rod, the frizzen is fixed on push rod, the mounting seat is fixed in casing, the controlling switch
In mounting seat, the 3rd elastic component is connected between depression bar and mounting seat, and the depression bar is connected with the 3rd elastic component
The other end be hinged in casing, the quantity of the controlling organization is corresponding with the quantity of observation window, and each controlling switch
One circuit of electromagnet of control.
5. a kind of construction costs Schedule monitoring device according to claim 4, it is characterised in that:3rd elastic component is
Rubber parts.
6. a kind of construction costs Schedule monitoring device according to claim 5, it is characterised in that:The surface of the iron block sets
There is one layer of antirust coat.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621212755.9U CN206178969U (en) | 2016-11-10 | 2016-11-10 | Engineering cost progress monitoring device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621212755.9U CN206178969U (en) | 2016-11-10 | 2016-11-10 | Engineering cost progress monitoring device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206178969U true CN206178969U (en) | 2017-05-17 |
Family
ID=58684461
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621212755.9U Expired - Fee Related CN206178969U (en) | 2016-11-10 | 2016-11-10 | Engineering cost progress monitoring device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206178969U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114005349A (en) * | 2021-11-26 | 2022-02-01 | 四川建筑职业技术学院 | Construction progress model for building engineering management |
-
2016
- 2016-11-10 CN CN201621212755.9U patent/CN206178969U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114005349A (en) * | 2021-11-26 | 2022-02-01 | 四川建筑职业技术学院 | Construction progress model for building engineering management |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106405002B (en) | A kind of multi-faceted air detecting device of room air detection | |
CN206178969U (en) | Engineering cost progress monitoring device | |
CN104197471B (en) | Control method, device and the air conditioner of air conditioner and mobile control terminal | |
CN206906004U (en) | A kind of rotary switch test equipment | |
CN205722240U (en) | The efficient alarming device in a kind of construction site | |
CN204536408U (en) | A kind of multi-usage electroscope | |
CN205655172U (en) | Mobilizable stage lamp | |
CN203432038U (en) | Adjustable fresh air inlet | |
CN203321165U (en) | Pedal auxiliary door opening device | |
CN205735565U (en) | A kind of structural sheeting drilling equipment | |
CN206366553U (en) | A kind of multifunction combined vent cabinet | |
CN209694416U (en) | A kind of teaching accounting computerization combined experimental device | |
CN209280491U (en) | A kind of miniaturization weight freely falling body test device | |
CN207806057U (en) | A kind of device for closed guard gate's door leaf to be fixed | |
CN206936504U (en) | A kind of multifunctional cutting machine | |
CN206474236U (en) | A kind of building foundation engineering disposed waste high efficiency treatment machine | |
CN208298401U (en) | A kind of instructional device for pilot's Expert English language training by qualified teachers | |
CN2884388Y (en) | Electrically driving education experimental bench | |
CN206038791U (en) | Testboard of inspection electric control lock performance | |
CN205297579U (en) | High -efficient portable rock drill | |
CN208110378U (en) | A kind of unattended equipment room environment remote centralized control apparatus | |
CN207390794U (en) | A kind of elevator(lift) machine room step device and elevator(lift) machine room | |
CN205645571U (en) | Multi -functional insulating bar of 10kV improved generation | |
CN210743838U (en) | Dual-power switch operating mechanism | |
CN203227910U (en) | Solder bath method solderability tester |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170517 Termination date: 20211110 |