CN206144594U - Cigarette dust pelletizing system is fallen in tunnel - Google Patents

Cigarette dust pelletizing system is fallen in tunnel Download PDF

Info

Publication number
CN206144594U
CN206144594U CN201621056465.XU CN201621056465U CN206144594U CN 206144594 U CN206144594 U CN 206144594U CN 201621056465 U CN201621056465 U CN 201621056465U CN 206144594 U CN206144594 U CN 206144594U
Authority
CN
China
Prior art keywords
tunnel
spray pipe
pipe
valve
sparge pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621056465.XU
Other languages
Chinese (zh)
Inventor
周硕
杭宝国
李祯
席小龙
郭文豪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Civil Aviation Airport Construction Engineering Co Ltd
Original Assignee
No 4 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No 4 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd filed Critical No 4 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority to CN201621056465.XU priority Critical patent/CN206144594U/en
Application granted granted Critical
Publication of CN206144594U publication Critical patent/CN206144594U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses a cigarette dust pelletizing system is fallen in tunnel, explode construction trolley frame, spray pipe, high penstock and valve including boring, the brill explodes the construction trolley frame and is the portal frame, the spray pipe is located to bore and is exploded on the construction trolley frame, the spray pipe is arranged along boring the gate -type frame that explodes the construction trolley frame, the spray pipe transversely is equipped with two rows, the equipartition has the hole for water spraying on the spray pipe, the spray pipe is connected with high penstock, high penstock is connected with the valve, the hole for water spraying all be equipped with two rows on every spray pipe, the valve be the gate valve, the utility model discloses a spray pipe spun high pressure water curtain, the bonding dust to with the bankrupt poisonous gas reaction who gives birth to of tunnel implosion, thereby play the effect of falling the cigarette and removing dust, optimized the air circumstance in the tunnel, ensured good construction operation environment.

Description

Dust collection system is dropped in tunnel
Technical field
This utility model is related to dust collection system is dropped in technical field of tunnel construction, more particularly to tunnel.
Background technology
Constructing tunnel, the domestic main construction technology using " drilling and blasting method ", using explosive blasting rock, transport rock ballast at present Appear outer, form the cross-section in tunnel.The method uses of the remote past, comparative maturity, but is exactly explosion the drawbacks of maximum Can cause in tunnel, to form substantial amounts of flue dust and harmful gass.Typically require, after explosion in tunnel, to need ventilation 15 minutes, with Flue dust in discharge tunnel etc., but with the progress of construction, the continuous growth in tunnel is passed through fresh wind using ventilation blower and reaches The effect of flue dust is discharged in dilution can be caused construction environment in tunnel also worse and worse, is not reached occupational health worse and worse Require, ventilation blower ventilation time is long, high cost.
The content of the invention
This utility model aims to solve the problem that the deficiencies in the prior art, and provides, it is therefore an objective to Drop fume and dust, optimizes the air ambient in tunnel, it is ensured that good construction operation environment.
This utility model for achieving the above object, is employed the following technical solutions:Dust collection system is dropped in tunnel, including is bored quick-fried Builder's staging, sparge pipe, high-pressure water pipe and valve, the construction of explosion stand is portal frame, and the sparge pipe quick-fried is applied located at boring On work stand, along the portal frame of construction of explosion stand, the sparge pipe arranges that the sparge pipe is transversely provided with two rows, the spray Hole for water spraying is evenly equipped with water pipe, the sparge pipe is connected with high-pressure water pipe, and the high-pressure water pipe is connected with valve.
Further, described sparge pipe is coating steel pipe.
Further, described sparge pipe is connected by plastic flexible pipe with high-pressure water pipe.
Further, described hole for water spraying is equipped with two rows on every sparge pipe.
Further, a diameter of 2mm of described hole for water spraying, spacing is 100mm.
Further, described valve is gate valve.
The beneficial effects of the utility model are:The high pressure water curtain that this utility model is sprayed by sparge pipe, bond dust, and The toxic gas reaction for going bankrupt raw with tunnel implosion, so as to play a part of to drop fume and dust, optimizes the air ambient in tunnel, Good construction operation environment is ensure that, compared with the conventional simple ventilation by ventilation blower, same air quality is reached, can be shown The ventilation time for reducing ventilation blower is write, energy-saving and emission-reduction, cost-effective purpose is reached.
Description of the drawings
Fig. 1 is structural representation of the present utility model;
In figure:1- valves;2- high-pressure water pipe;3- construction of explosion stands;4- sparge pipes;5- hole for water sprayings;
It is described in detail below with reference to embodiment of the present utility model referring to the drawings.
Specific embodiment
The utility model is described in further detail with reference to the accompanying drawings and examples:
As shown in figure 1, dust collection system is dropped in tunnel, including construction of explosion stand 3, sparge pipe 4, high-pressure water pipe 2 and valve Door 1, the construction of explosion stand 3 are portal frame, and, on construction of explosion stand 3, the sparge pipe 4 is along brill for the sparge pipe 4 The portal frame arrangement of quick-fried builder's staging 3, the sparge pipe 4 are transversely provided with two rows, hole for water spraying 5 are evenly equipped with the sparge pipe 4, The sparge pipe 4 is connected with high-pressure water pipe 2, and the high-pressure water pipe 2 is connected with valve 1.
Further, described sparge pipe 4 is coating steel pipe.
Further, described sparge pipe 4 is connected by plastic flexible pipe with high-pressure water pipe 2.
Further, described hole for water spraying 5 is equipped with two rows on every sparge pipe 4.
Further, described 5 a diameter of 2mm of hole for water spraying, spacing is 100mm.
Further, described valve 1 is gate valve.
During construction, in the tunnel in explosion 1 minute, valve 1 is opened, water under high pressure is sprayed from hole for water spraying 5, forms water curtain, water Curtain can bond dust, and the toxic gas reaction for going bankrupt raw with tunnel implosion, so as to play a part of to drop fume and dust.
This utility model is exemplarily described above in conjunction with accompanying drawing, it is clear that this utility model is implemented not to be received The restriction of aforesaid way, if the various improvement that method design of the present utility model and technical scheme are carried out are employed, or without Improvement directly applies to other occasions, within protection domain of the present utility model.

Claims (6)

1. dust collection system is dropped in tunnel, it is characterised in that including construction of explosion stand (3), sparge pipe (4), high-pressure water pipe (2) With valve (1), the construction of explosion stand (3) is portal frame, and the sparge pipe (4) is on construction of explosion stand (3), described Along the portal frame of construction of explosion stand (3), sparge pipe (4) arranges that the sparge pipe (4) is transversely provided with two rows, the sparge pipe (4) hole for water spraying (5) is evenly equipped with, the sparge pipe (4) is connected with high-pressure water pipe (2), the high-pressure water pipe (2) and valve (1) Connection.
2. dust collection system is dropped in tunnel according to claim 1, it is characterised in that described sparge pipe (4) is zinc-plated Steel pipe.
3. dust collection system is dropped in tunnel according to claim 1, it is characterised in that described sparge pipe (4) and high pressure Water pipe (2) is connected by plastic flexible pipe.
4. dust collection system is dropped in tunnel according to claim 1, it is characterised in that described hole for water spraying (5) is per root Sparge pipe is equipped with two rows on (4).
5. dust collection system is dropped in tunnel according to claim 1, it is characterised in that described hole for water spraying (5) is a diameter of 2mm, spacing are 100mm.
6. dust collection system is dropped in tunnel according to claim 1, it is characterised in that described valve (1) is gate valve.
CN201621056465.XU 2016-09-14 2016-09-14 Cigarette dust pelletizing system is fallen in tunnel Active CN206144594U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621056465.XU CN206144594U (en) 2016-09-14 2016-09-14 Cigarette dust pelletizing system is fallen in tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621056465.XU CN206144594U (en) 2016-09-14 2016-09-14 Cigarette dust pelletizing system is fallen in tunnel

Publications (1)

Publication Number Publication Date
CN206144594U true CN206144594U (en) 2017-05-03

Family

ID=58618467

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621056465.XU Active CN206144594U (en) 2016-09-14 2016-09-14 Cigarette dust pelletizing system is fallen in tunnel

Country Status (1)

Country Link
CN (1) CN206144594U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113914921A (en) * 2021-08-30 2022-01-11 江苏徐工工程机械研究院有限公司 Dust settling device and method for tunnel drilling and blasting construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113914921A (en) * 2021-08-30 2022-01-11 江苏徐工工程机械研究院有限公司 Dust settling device and method for tunnel drilling and blasting construction
CN113914921B (en) * 2021-08-30 2023-09-01 江苏徐工工程机械研究院有限公司 Tunnel drilling and blasting method construction dust fall device and method thereof

Similar Documents

Publication Publication Date Title
CN203978343U (en) The simple and easy drilling hole dust collector device that drilling construction is used
CN103422876A (en) Environment-friendly coal mine underground ventilation and dedusting safety system
CN102235175A (en) Smoke elimination and dust settlement construction method for long and large tunnel and dust settlement station used in construction method
CN206144594U (en) Cigarette dust pelletizing system is fallen in tunnel
CN202031630U (en) Spray dust reducing device for gold mine
CN103174389A (en) Drilling construction blowout prevention and dust fall device
CN203564927U (en) Low-energy-consumption dust removal system
CN204476458U (en) A kind of underground mine use dust guard efficiently
CN104879158A (en) Dry type drilled hole orifice dust elimination and noise reduction device and implementation method thereof
CN201851148U (en) Simple tunnel dust settling station
CN206397538U (en) A kind of water mist dust fall device of utilization tunnel high-pressure water pipe
CN203564928U (en) Low-cost purifying device applied to large-particle dust
CN104096432A (en) Water-mist deduster
CN204327169U (en) A kind of underground mine tunnel water curtain resistance dirt device for reducing dust
AU2021104396A4 (en) method for detoxification, dust reduction and smoke elimination after tunnel blasting by spraying pressurized alkaline water curtain with different diameter steel pipes
CN203066911U (en) Blowout control and dustfall device for drilling engineering
CN205117394U (en) Geomantic omen linkage blasting atomizer
CN203925351U (en) A kind of for firedamp taking-out discharging drilling orifice dust catcher
CN206707748U (en) A kind of machine tunneling fume extractor
CN104632191B (en) It is a kind of to drill with the defogging method for boring geology imager
CN208330447U (en) A kind of tunnel veil dust-extraction unit
CN206386148U (en) Windwater spraying device for reducing dust
CN206304529U (en) A kind of high-efficiency dust remover in the same direction
CN207694480U (en) The purification system of industrial chimney flue gas
CN205570001U (en) Be applied to dust collector in tunnel

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: No.173, No.2 Xingang Road, Tanggu, Binhai New Area, Tianjin, 300456

Patentee after: Civil Aviation Airport Construction Engineering Co.,Ltd.

Address before: No.173, No.2 Xingang Road, Tanggu, Binhai New Area, Tianjin, 300456

Patentee before: NO.4 ENGINEERING COMPANY LTD. OF CCCC FIRST HARBOR ENGINEERING Co.,Ltd.