CN206134127U CN201621147658.6U CN201621147658U CN206134127U CN 206134127 U CN206134127 U CN 206134127U CN 201621147658 U CN201621147658 U CN 201621147658U CN 206134127 U CN206134127 U CN 206134127U
Authority
CN
China
Prior art keywords
fixed
wire rope
steel wire
arc
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621147658.6U
Other languages
Chinese (zh)
Inventor
汤海霞
陈自平
汪磊
王亮
刘天慈
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Suizhou Power Supply Co of State Grid Hubei Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Suizhou Power Supply Co of State Grid Hubei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Suizhou Power Supply Co of State Grid Hubei Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201621147658.6U priority Critical patent/CN206134127U/en
Application granted granted Critical
Publication of CN206134127U publication Critical patent/CN206134127U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

The utility model provides a rod number board fixing device relates to the electric device field, and fixed stable good to rod number board, it is more convenient to install, the technical scheme of the utility model lie in: including two mounts and connect the wire rope of two mounts, the mount includes the arc, connects at the connecting plate of arc front end and the fixed plate of being connected with the connecting plate other end, and the medial surface of the arc of two mounts is relative, the fixed plate is used for fixed rod number board, all be equipped with the through -hole that passes for the bolt on connecting plate and the fixed plate, two the parallel bolted connection that just passes through of connecting plate of mount, two the relative nevertheless contactless of tail end of mount, one of them fixed plate end of fixed has a wire rope, and another fixed plate tail end is equipped with a wire rope fastener, can make wire rope pass and fix wire rope.

Description

A kind of pole tag fixing device
Technical field
The utility model is related to electric device field, specially a kind of pole tag fixing device.
Background technology
To the fixation of cement pole pole tag, generally using iron wire, twisting is tied up after the circle of shaft one on electricity overhead power transmission line Prick, its drawback makes binding insecure, and iron wire easily disconnects and loosens, tie up so as to causing pole tag fixation insecure, and adopting The operation of bundle mode is complex, is unfavorable for improving efficiency of construction.
Utility model content
The utility model provides a kind of new pole tag fixing device, the good stability fixed to pole tag, installs It is convenient.
The technical solution of the utility model is:It is described including the steel wire rope of two fixed mounts of two fixed mounts and connection Fixed mount includes arc, the connecting plate for being connected to arc front edge of board and the fixed plate being connected with the connecting plate other end, and two solid The medial surface for determining the arc of frame is relative, and the fixed plate is used to fix pole tag, is equipped with the connecting plate and fixed plate The through hole passed through to bolt, the connecting plate of two fixed mounts is parallel and is bolted, two fixed mounts Tail end is relative but does not contact, and one of fixed plate tail end is fixed with steel cable, and another fixed plate tail end is provided with a steel Cord fastener, can make steel wire penetrating and steel wire rope is fixed.
Used as the preferred of such scheme, the fixed plate is vertical with connecting plate, and fixed plate extends to the outside of arc.
Used as the preferred of such scheme, the arc is made up of hard elastic material.
Used as the preferred of such scheme, the steel wire rope fastening device is convex on the outside of correspondence arc tail end including being fixed on Platform, the boss is provided with two orthogonal through holes, and one of through hole is to through steel wire rope, another through hole is provided with Bolt, and the screw rod of bolt is provided with to the through hole of steel wire penetrating, bolt passes through nut check.
Used as the preferred of such scheme, when bolt is after nut check, the axis of the through hole on bolt is located at steel wire rope The lower section of the axis of through hole on the boss for being passed through.
The beneficial effects of the utility model are:During work high above the ground, it is not necessary to which excessive operation can be carried out to pole tag It is fixed;Arc has elasticity, and has interval between two arc tail ends, is easy to change the crooked radian of arc, applicable In the cement pole of different-diameter, expand use range.
Description of the drawings
Fig. 1 is structural representation of the present utility model.
Fig. 2 is the structural representation of steel wire rope fastening device in the utility model.
Specific embodiment
Embodiment of the present utility model is described in detail below in conjunction with accompanying drawing.
As depicted in figs. 1 and 2, the structure of the present embodiment includes the steel wire rope 4 of two fixed mounts of two fixed mounts and connection, The fixed mount includes arc 1, the connecting plate 3 for being connected to the front end of arc 1 and the fixed plate being connected with the other end of connecting plate 3 2, the medial surface of the arc 1 of two fixed mounts is relative, and the fixed plate 2 is used to fix pole tag, the connecting plate 3 and fixation It is equipped with the through hole passed through to bolt on plate 2, the connecting plate 3 of two fixed mounts is parallel and is bolted, two The tail end of the fixed mount is relative but does not contact, and the tail end of one of fixed plate 2 is fixed with steel cable 4, and another is fixed The tail end of plate 2 is provided with a steel wire rope fastening device 5, and steel wire rope 4 can be made to pass through and be fixed to steel wire rope 4.
In the present embodiment, the fixed plate 2 is vertical with connecting plate 3, and fixed plate 2 extends to the outside of arc 1.
In the present embodiment, the arc 1 is made up of hard elastic material.
In the present embodiment, the steel wire rope fastening device 5 includes being fixed on the boss 7 on the outside of the correspondence tail end of arc 1, The boss 7 is provided with two orthogonal through holes, and one of through hole is to through steel wire rope 4, another through hole is provided with Bolt 6, and the screw rod of bolt 6 is provided with to the through hole of steel wire penetrating, bolt 6 is locked by nut 8.
In the present embodiment, when bolt 6 is after the locking of nut 8, the axis of the through hole on bolt 6 is worn positioned at steel wire rope The lower section of the axis of through hole on the boss 7 crossed.
The operation principle of the present embodiment is:
Pole tag is bolted in fixed plate on ground, then two arcs is enclosed within outside cement pole in high-altitude Side, by the through hole of the bolt on the through hole and boss of steel wire penetrating boss, and tenses on steel wire rope from opposite side, makes two arcs Shape plate holds tightly cement pole.Then the nut on bolt is tightened, bolt is locked, due to when bolt is after nut check, spiral shell The axis of the through hole on bolt is located at the lower section of the axis of through hole on the boss that steel wire rope is passed through, so now after clamping screw, Bolt can drive steel wire rope to move down a segment distance, make the corresponding through-bore axis of section steel wire rope axis runout boss, from And lock on steel wire rope.Dismounting makes to only need to open bolt, you can from boss extract steel wire rope out.
Preferred embodiment of the present utility model is these are only, the utility model is not limited to, for this area Technical staff for, the utility model can have various modifications and variations.It is all it is of the present utility model spirit and principle within, Any modification, equivalent substitution and improvements made etc., should be included within protection domain of the present utility model.

Claims (5)

1. a kind of pole tag fixing device, it is characterised in that:Including the steel wire rope of two fixed mounts of two fixed mounts and connection, institute Fixed mount is stated including arc, the connecting plate for being connected to arc front edge of board and the fixed plate being connected with the connecting plate other end, two The medial surface of the arc of fixed mount is relative, and the fixed plate is used to fix pole tag, is all provided with the connecting plate and fixed plate There is a through hole passed through to bolt, the connecting plate of two fixed mounts is parallel and is bolted, two fixed mounts Tail end it is relative but do not contact, one of fixed plate tail end is fixed with steel cable, and another fixed plate tail end is provided with one Steel wire rope fastening device, can make steel wire penetrating and steel wire rope is fixed.
2. pole tag fixing device according to claim 1, it is characterised in that:The fixed plate is vertical with connecting plate, and Fixed plate to the outside of arc extends.
3. pole tag fixing device according to claim 2, it is characterised in that:The arc is hard elastic material system Into.
4. pole tag fixing device according to claim 3, it is characterised in that:The steel wire rope fastening device includes fixing Boss on the outside of correspondence arc tail end, the boss is provided with two orthogonal through holes, one of through hole to Through steel wire rope, another through hole is provided with bolt, and the screw rod of bolt is provided with to the through hole of steel wire penetrating, and bolt passes through Nut check.
5. pole tag fixing device according to claim 4, it is characterised in that:When bolt is after nut check, bolt On the axis of through hole be located at the lower section of the axis of through hole on the boss that passed through of steel wire rope.
CN201621147658.6U 2016-10-21 2016-10-21 Rod number board fixing device Expired - Fee Related CN206134127U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621147658.6U CN206134127U (en) 2016-10-21 2016-10-21 Rod number board fixing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621147658.6U CN206134127U (en) 2016-10-21 2016-10-21 Rod number board fixing device

Publications (1)

Publication Number Publication Date
CN206134127U true CN206134127U (en) 2017-04-26

Family

ID=58575475

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621147658.6U Expired - Fee Related CN206134127U (en) 2016-10-21 2016-10-21 Rod number board fixing device

Country Status (1)

Country Link
CN (1) CN206134127U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112598997A (en) * 2020-11-30 2021-04-02 国网山东省电力公司滨州供电公司 Pole sign assists mounting tool

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112598997A (en) * 2020-11-30 2021-04-02 国网山东省电力公司滨州供电公司 Pole sign assists mounting tool

Similar Documents

Publication Publication Date Title
CN202034506U (en) Lead hanging hook of earth wire
CN205558788U (en) Iron tower cat ladder
CN206134127U (en) Rod number board fixing device
CN105140676B (en) A kind of insulating bar auxiliary device for being used to install clamping plate type ground wire connector
CN204344018U (en) A kind of drilling rod loading attachment of rig
CN203312696U (en) 10KV line electrified seam-joining hanging buckling-type insulation baffle plate
CN203398639U (en) Vibration-proof hammer moving recovering device for overhead ground wire
CN203135351U (en) Wall cable holt hoop iron
CN201663250U (en) Turnable grounding wire hook
CN207218125U (en) A kind of high-voltage line ground wire lowering or hoisting gear
CN203286145U (en) Cable fixing device
CN104318859B (en) A kind of electric power steel pipe tower signboard fixing device and method
CN209389555U (en) A kind of temporary grounding bar fixing device
CN205400233U (en) Install cross arm on wire pole
CN204143774U (en) Electric power steel pipe tower signboard fixing device
CN203967279U (en) Corner pole circuit interior angle side joint device for connecting earth
CN208352856U (en) Power distribution live-wire on-load drainage thread hanging rod
CN202949167U (en) Tool for mounting insulators
CN202026037U (en) Clamping device for replacing multifunctional suspended insulator string cross-arm side armour clamp
CN205828795U (en) A kind of universal RJ45 network mouth connector fixing device
CN211666400U (en) Novel pole cross arm
CN205724648U (en) A kind of charged for replacement 35kV strain insulator string specific purpose tool
CN202687854U (en) Portable hoister
CN203078542U (en) Anti-dropping device of mine car tail rope
CN106437279A (en) Double-cross arm structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170426

Termination date: 20181021

CF01 Termination of patent right due to non-payment of annual fee