CN206130314U - Unsettled oil gas pipeline supports reinforcing apparatus - Google Patents

Unsettled oil gas pipeline supports reinforcing apparatus Download PDF

Info

Publication number
CN206130314U
CN206130314U CN201621168734.1U CN201621168734U CN206130314U CN 206130314 U CN206130314 U CN 206130314U CN 201621168734 U CN201621168734 U CN 201621168734U CN 206130314 U CN206130314 U CN 206130314U
Authority
CN
China
Prior art keywords
pier
conduit saddle
pipeline
pipe thread
tube stay
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621168734.1U
Other languages
Chinese (zh)
Inventor
伍颖
金鹏威
杨旭
周永培
王妮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201621168734.1U priority Critical patent/CN206130314U/en
Application granted granted Critical
Publication of CN206130314U publication Critical patent/CN206130314U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses an unsettled oil gas pipeline supports reinforcing apparatus, including reinforced concrete support mound, tube stay, conduit saddle and pipe thread, the reinforced concrete support mound comprises pier cap and pier shaft, and the cant chisei is connected with reinforced concrete support mound pier cap for the tube stay, and the conduit saddle is in the same place with the tube stay welding, contains the one deck rubber pad between conduit saddle, pipe thread and the pipeline, and the pipe thread makes up into a bolted connection for the fixture with the conduit saddle and fixes the pipeline. The utility model discloses simple structure, simple to operate, the engineering of being convenient for actual operation easily realizes, to unsettled oil gas pipeline and be in the geological conditions not good, easily influenced by natural disasters to lead to the unsettled pipeline of oil gas pipeline to play strengthening effect to reach the mesh of protection pipeline safety operation.

Description

A kind of hanging oil and gas pipes bracing reinforcement device
Technical field
This utility model is related to a kind of bracing reinforcement device, especially a kind of hanging oil and gas pipes bracing reinforcement device.
Background technology
As China's long-distance oil & gas pipeline engineering is greatly developed and is built, many locations will unavoidably be passed through and be susceptible to The massif of natural disaster, easily slides so as to cause pipeline hanging in the natural disasters such as heavy showers, the earthquake effect lower surface soil body, But do not have not under the circumstances when oil and gas pipes are built originally, therefore do not carry out corresponding reinforcement protection and arrange Apply;Simultaneously in the bad area of some geological conditions, buried pipeline is easy to be affected hanging again by disaster.For these situations Corresponding bracing reinforcement mode is taken to be very necessary to pipeline.
Utility model content
The purpose of this utility model is to provide a kind of bracing reinforcement device, can be with better simply structure to hanging oil gas Pipeline is realized effectively supporting and reinforcing.
To achieve these goals, this utility model is adopted the following technical scheme that:
Described a kind of hanging oil and gas pipes bracing reinforcement device, it is characterised in that:Including reinforced concrete support pier, pipe Support, conduit saddle and pipe thread, reinforced concrete support pier are made up of pier cap and pier shaft, and tube stay peg is connected with pier cap, conduit saddle and Tube stay welds together, and one layer of rubber blanket is included between conduit saddle, pipe thread and pipeline, and pipe thread is combined into a fixture bolt with conduit saddle Pipeline is fixed by connection.
Described a kind of hanging oil and gas pipes bracing reinforcement device, reinforced concrete support pier pier cap upper bottom surface length are about 3 Times pipe diameter length 3d, wide about pipeline pipe diameter length d;Pier cap bottom surface is the pros that the length of side is about pipe diameter d Shape;Pier cap is about 1.2d apart from maximum in parallel bottom surface up and down, and minimum range is about 0.75d.
Described a kind of hanging oil and gas pipes bracing reinforcement device, reinforced concrete support pier pier shaft are cylindrical shape, Pier shaft diameter is approximately equal to pipe diameter length d.
Described a kind of hanging oil and gas pipes bracing reinforcement device, tube stay material are 10mm thickness Q345C steel, and conduit saddle material is 16mm thickness Q345C steel, pipe thread material are 10mm thickness Q345C steel, and the rubber blanket between conduit saddle, pipe thread and pipeline is that chip vulcanizes rubber Glue.
Described a kind of hanging oil and gas pipes bracing reinforcement device, two pieces of conduit saddle bottom supporting steel plate are respectively welded at two ends Edge.
Compared with prior art, this utility model has the advantage that:
Stabilized structure, pipeline can be efficiently transferred to power on support pier by conduit saddle and tube stay, hence for hanging Oil and gas pipes can play effective bracing reinforcement effect.
Rubber blanket between conduit saddle, pipe thread and pipeline can play a protective role to the external anti-corrosion layer of pipeline and in operation Pipeline plays cushioning effect.
Steel yield stress that bracing means outside support pier is used is higher, heat resistance is good, tube stay peg and reinforcing bar Concrete support pier connection more firm stable, improves the service life of the device.
Simple structure, reasonable in design, construction work difficulty is little.
Description of the drawings
Fig. 1 is a kind of hanging oil and gas pipes bracing reinforcement device schematic perspective view described in the utility model.
Fig. 2 is a kind of hanging oil and gas pipes bracing reinforcement device upper pipe fixing device details described in the utility model Figure.
Fig. 3 is pier cap dimensional drawing in Fig. 1.
Fig. 4 is conduit saddle detail view in Fig. 1.
In figure, 1. reinforced concrete support pier, 2. tube stay, 3. conduit saddle, 4. pipe thread, 5. pier cap, 6. pier shaft, 7. peg, 8. Rubber blanket, 9. bolt.
Specific embodiment
Below in conjunction with the accompanying drawings embodiment of the present utility model is illustrated, so that advantage of the present utility model and special title It is easier to be readily appreciated by one skilled in the art.
Prop up with reference to a kind of Fig. 1, Fig. 2 hanging oil and gas pipes bracing reinforcement device of the present utility model, including armored concrete Support pier 1, tube stay 2, conduit saddle 3 and pipe thread 4, reinforced concrete support pier 1 are made up of pier cap 5 and pier shaft 6, tube stay 2 with peg 7 with Pier cap 5 connects, and conduit saddle 3 is welded together with tube stay 2, includes one layer of rubber blanket 8 between conduit saddle 3, pipe thread 4 and pipeline, pipe thread 4 with Conduit saddle 3 is combined into a fixture bolt 9 and connects to be fixed pipeline.
Described 5 upper bottom surface length of reinforced concrete support pier pier cap is about pipe diameter three times 3d, wide about pipeline pipeline Diameter length d;5 bottom surface of pier cap is the square that the length of side is about pipe diameter d;Pier cap about 5 parallel bottom surface apart from maximum About 1.2 times pipe diameter 1.2d, minimum range are about 0.75 times of pipe diameter 0.75d.
Described reinforced concrete support pier pier shaft 6 is cylindrical shape, and pier shaft diameter is approximately equal to pipe diameter length d.
Described a kind of hanging oil and gas pipes bracing reinforcement device, 2 material of tube stay be 10mm thickness Q345C steel, 3 material of conduit saddle For 16mm thickness Q345C steel, 4 material of pipe thread is 10mm thickness Q345C steel, and the rubber blanket 8 between conduit saddle 3, pipe thread 4 and pipeline is chip Vulcanite.
Edges at two ends is respectively welded at reference to two pieces of 3 bottom of Fig. 4 conduit saddles supporting steel plate.
Tube stay 2 and pier cap 5 are with being connected using live primary concreting construction at the top of peg 7.
Pipeline lays step:First pipeline is steadily placed on conduit saddle 3, the instrument of pipe thread 4 is then buckled respectively by buckle The bolt 9 at two ends is fastened.
The above, specific embodiment only of the present utility model is not intended to limit the power of this utility model technology Sharp scope, all interest fields covered with identical technological means or claim content and implement, all without departing from this reality With new category.

Claims (5)

1. a kind of hanging oil and gas pipes bracing reinforcement device, it is characterised in that:Including reinforced concrete support pier, tube stay, conduit saddle And pipe thread, reinforced concrete support pier is made up of pier cap and pier shaft, and tube stay peg is connected with pier cap, and conduit saddle is welded with tube stay Together, one layer of rubber blanket is included between conduit saddle, pipe thread and pipeline, pipe thread is combined into a fixture with conduit saddle and is connected with managing Road is fixed.
2. a kind of hanging oil and gas pipes bracing reinforcement device according to claim 1, its spy's title is:Armored concrete Support pier pier cap upper bottom surface length is about 3 times of pipe diameter length 3d, wide about pipe diameter length d;Pier cap bottom surface be the length of side about For the square of pipe diameter d;Pier cap is about 1.2d apart from maximum in parallel bottom surface up and down, and minimum range is about 0.75d.
3. a kind of hanging oil and gas pipes bracing reinforcement device according to claim 1, its spy's title is:Armored concrete Pier pier shaft is supportted for cylindrical shape, pier shaft diameter is approximately equal to pipe diameter length d.
4. a kind of hanging oil and gas pipes bracing reinforcement device according to claim 1, its spy's title is:Tube stay material is 10mm thickness Q345C steel, conduit saddle material be 16mm thickness Q345C steel, pipe thread material be 10mm thickness Q345C steel, conduit saddle, pipe thread and pipeline Between rubber blanket be chip vulcanite.
5. a kind of hanging oil and gas pipes bracing reinforcement device according to claim 1, it is characterised in that two pieces of conduit saddle bottom Supporting steel plate is respectively welded at edges at two ends.
CN201621168734.1U 2016-11-02 2016-11-02 Unsettled oil gas pipeline supports reinforcing apparatus Expired - Fee Related CN206130314U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621168734.1U CN206130314U (en) 2016-11-02 2016-11-02 Unsettled oil gas pipeline supports reinforcing apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621168734.1U CN206130314U (en) 2016-11-02 2016-11-02 Unsettled oil gas pipeline supports reinforcing apparatus

Publications (1)

Publication Number Publication Date
CN206130314U true CN206130314U (en) 2017-04-26

Family

ID=58576148

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621168734.1U Expired - Fee Related CN206130314U (en) 2016-11-02 2016-11-02 Unsettled oil gas pipeline supports reinforcing apparatus

Country Status (1)

Country Link
CN (1) CN206130314U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108317341A (en) * 2018-04-17 2018-07-24 河南创辉水利水电工程有限公司 A kind of mountain area hydropower station pressure pipeline rock-fall proof structural damage
CN110355870A (en) * 2019-07-16 2019-10-22 湖北东方化工有限公司 One kind being based on pipe support maintenance process process

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108317341A (en) * 2018-04-17 2018-07-24 河南创辉水利水电工程有限公司 A kind of mountain area hydropower station pressure pipeline rock-fall proof structural damage
CN110355870A (en) * 2019-07-16 2019-10-22 湖北东方化工有限公司 One kind being based on pipe support maintenance process process
CN110355870B (en) * 2019-07-16 2021-06-01 湖北东方化工有限公司 Maintenance process flow based on pipe frame

Similar Documents

Publication Publication Date Title
CN107152285A (en) For shield launching and the servicing unit of reception
CN204098918U (en) Dimensional parameters multiple degrees of freedom is adjustable uses shield launching bracket repeatedly
CN102134860A (en) Self counter force balance loading test method of engineering pile bearing capacity
CN206130314U (en) Unsettled oil gas pipeline supports reinforcing apparatus
CN208074267U (en) A kind of hanging bracing means of Urban Underground pipe gallery excavation pit gut line
CN206145311U (en) Detachable water conservancy pipeline connecting piece of damping
CN208534495U (en) One kind being used for tunnel double-lining reinforcing bar interlamellar spacing and protective layer positioning device
CN105421473A (en) Double-wall opening-sealed steel sleeve box cofferdam and construction method
CN205240271U (en) Pipeline rack is used in civil engineering construction
CN206052759U (en) A kind of steel-pipe pile attachment means under water
CN103938556B (en) Concrete T-shaped cross section beam bridge Space Double K word supports horizontal intensifier
CN203514337U (en) Large-scale steel-pipe-inserting-type foundation
CN105525942A (en) Escape pipeline
CN204753977U (en) Cement concrete pillar
CN203530963U (en) Counter weight method cage floating prevention device
CN207739280U (en) Communication pipeline member and the communication well for using the communication pipeline member
CN207406344U (en) A kind of shield machine air pushing connecting bridge supporting apparatus
CN206417797U (en) Large diameter pipeline counterpart apparatus
CN206752283U (en) Long-span bridges
CN206740524U (en) A kind of X-shaped Steel Tube Joint tension experimental provision
CN202451983U (en) Multi-pipe support laid along bottom of piping trench
CN213337137U (en) Internal and external pressure inspection equipment for cement pipe
CN206538791U (en) The fixing device of assembled covering plate
CN108756949A (en) One kind being used for tunnel double-lining reinforcing bar interlamellar spacing and protective layer positioning device
CN205857260U (en) A kind of Road Bridge Pile Foundation bracing means

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170426