CN206110482U - Steel construction fixed bolster - Google Patents

Steel construction fixed bolster Download PDF

Info

Publication number
CN206110482U
CN206110482U CN201620900659.7U CN201620900659U CN206110482U CN 206110482 U CN206110482 U CN 206110482U CN 201620900659 U CN201620900659 U CN 201620900659U CN 206110482 U CN206110482 U CN 206110482U
Authority
CN
China
Prior art keywords
connecting portion
steel construction
crane span
span structure
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620900659.7U
Other languages
Chinese (zh)
Inventor
刘勇
倪晓东
韩锋
朱雯清
张明磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Group Co Ltd
Original Assignee
China Railway Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Group Co Ltd filed Critical China Railway Construction Group Co Ltd
Priority to CN201620900659.7U priority Critical patent/CN206110482U/en
Application granted granted Critical
Publication of CN206110482U publication Critical patent/CN206110482U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Butt Welding And Welding Of Specific Article (AREA)

Abstract

The utility model discloses a steel construction fixed bolster, including " second " style of calligraphy crane span structure support, " second " style of calligraphy crane span structure support clamps on the girder steel. The utility model discloses simple structure, convenient to use are applicable to the installation of electronic product on the steel construction, member to need not welded fastening on the girder steel, reduce steel construction fatigue damage, shorten construction period greatly, effectively solved the difficult problem that traditional welding construction side method leads to steel construction fatigue damage, gained good economic benefits and social.

Description

A kind of steel construction fixed support
Technical field
This utility model is related to building structure technology field, it particularly relates to a kind of steel construction fixed support.
Background technology
With continuous progressive and the needs of the times of society, make building structure using steel construction more and more, in steel construction Upper installation electronic product, component, traditional fixed installation construction method are adopted and welding for steel structure, are usually brought not to steel construction With the damage of degree.Simultaneously because adopting welding procedure technology, welding job amount is increased, produce discomfort glare, and discharge Substantial amounts of flue gas, does not meet the theory of current energy-conserving and environment-protective, green construction yet.Traditional construction method complex process, construction effect Rate is low, and construction and installation quality is wayward.
For the problem in correlation technique, effective solution is not yet proposed at present.
Utility model content
For the above-mentioned technical problem in correlation technique, the utility model proposes it is a kind of both simple, and the steel construction of practicality Fixed support, can be applied to electronic product, the installation of component on steel construction, and need not be welded and fixed on girder steel, reduce steel Structure fatigue damage.
To realize above-mentioned technical purpose, what the technical solution of the utility model was realized in:
A kind of steel construction fixed support, including " second " font crane span structure support, " second " the font crane span structure support is installed on steel Liang Shang.
Further, described " second " font crane span structure support includes that the first connecting portion being mutually connected vertically successively, second connect Socket part, the 3rd connecting portion 3, the 4th connecting portion and the 5th connecting portion.
Further, the length of the first connecting portion is wire casing height 1/2;Second connecting portion length is more than wire casing width Degree, second connecting portion deduct the surplus of wire casing width, are exactly wire casing left and right adjusting amount, and guarantee which on the same line;5th The length of connecting portion is the 1/2 of time purlin height.
Further, crane span structure fixed bolt hole is provided with the second connecting portion.
Further, bracket fixing bolt hole is provided with the 5th connecting portion.
Further, described " second " font crane span structure support is integrally formed.
Further, described " second " font crane span structure support is fixedly connected with girder steel by tapping screw.
Further, sealing ring is provided with the tapping screw.
Preferably, the color of spraying and steel structure coating solid colour on described " second " font crane span structure support.
The beneficial effects of the utility model:It is this utility model simple structure, easy to use, it is adaptable to electromechanical on steel construction to produce The installation of product, component, and need not be welded and fixed on girder steel, reduce fatigue of steel structures and damage;The construction period is substantially reduced, is had Effect solves the difficult problem that traditional welding construction method causes fatigue of steel structures to be damaged, and achieves good economic benefit and society's effect Benefit.
Description of the drawings
In order to be illustrated more clearly that this utility model embodiment or technical scheme of the prior art, below will be to embodiment Needed for accompanying drawing to be used be briefly described, it should be apparent that, drawings in the following description are only of the present utility model Some embodiments, for those of ordinary skill in the art, on the premise of not paying creative work, can be with according to this A little accompanying drawings obtain other accompanying drawings.
Fig. 1 is the support bracket fastened structural representation of a kind of steel construction according to this utility model embodiment;
Fig. 2 is the support bracket fastened scheme of installation of a kind of steel construction according to this utility model embodiment.
In figure:
1st, first connecting portion;2nd, second connecting portion;3rd, the 3rd connecting portion;4th, the 4th connecting portion;5th, the 5th connecting portion;6、 " second " font crane span structure support;7th, crane span structure fixed bolt hole;8th, tapping screw;9th, wire casing;10th, secondary purlin;11st, bracket fixing bolt Hole.
Specific embodiment
Below in conjunction with the accompanying drawing in this utility model embodiment, the technical scheme in this utility model embodiment is carried out Clearly and completely describe, it is clear that described embodiment is only this utility model a part of embodiment, rather than whole Embodiment.Based on the embodiment in this utility model, the every other embodiment obtained by those of ordinary skill in the art all belongs to In the scope of this utility model protection.
As depicted in figs. 1 and 2, a kind of steel construction fixed support according to this utility model embodiment, including " second " Font crane span structure support 6, " second " the font crane span structure support 6 are installed on girder steel.
First connecting portion 1 that " second " the font crane span structure support 6 includes being mutually connected vertically successively, second connecting portion 2, Three connecting portions 3, the 4th connecting portion 4 and the 5th connecting portion 5.
The length of the first connecting portion 1 is 9 height 1/2 of wire casing;2 length of second connecting portion be more than 9 width of wire casing, second Connecting portion 2 deducts the surplus of 9 width of wire casing, is exactly 9 left and right adjusting amount of wire casing, and guarantees which on the same line;5th connection The length in portion 5 is the 1/2 of time 10 height of purlin.
Crane span structure fixed bolt hole 7 is provided with the second connecting portion 2.
Bracket fixing bolt hole 11 is provided with 5th connecting portion 5.
" second " the font crane span structure support 6 is integrally formed.
" second " the font crane span structure support 1 is fixedly connected with girder steel by tapping screw 8.
Sealing ring is provided with the tapping screw 8.
The color of spraying and steel structure coating solid colour on " second " the font crane span structure support 6.
Above-mentioned technical proposal of the present utility model is understood for convenience, below by way of new to this practicality in specifically used mode The above-mentioned technical proposal of type is described in detail.
When specifically used, according to a kind of steel construction fixed support described in the utility model, support is fixed on girder steel When, support and steel construction time 10 binding site of purlin answers tight clamping fit, and with zinc-plated 8 fixation of tapping screw, tapping screw 8 On install seal gasket additional, set spacing is 1.5~1.8m;The paint color of support should be consistent with steel structure coating color, with true Protect and steel construction Integral decoration effect, support spraying should be carried out in a pre-installation, it is ensured that coating quality.
It is in sum, by means of above-mentioned technical proposal of the present utility model, this utility model simple structure, easy to use, Suitable for the installation of electronic product, component on steel construction, and need not be welded and fixed on girder steel, reduce fatigue of steel structures and damage; The construction period is substantially reduced, the difficult problem that traditional welding construction method causes fatigue of steel structures to be damaged is efficiently solved, is achieved Good economic benefit and social benefit.
Preferred embodiment of the present utility model is the foregoing is only, it is not to limit this utility model, all at this Within the spirit and principle of utility model, any modification, equivalent substitution and improvements made etc. should be included in this utility model Protection domain within.

Claims (4)

1. a kind of steel construction fixed support, it is characterised in that including integrally formed " second " font crane span structure support (6), described " second " font crane span structure support (6) is installed on girder steel;" second " font crane span structure support (6) is including what is be mutually connected vertically successively First connecting portion (1), second connecting portion (2), the 3rd connecting portion (3), the 4th connecting portion (4) and the 5th connecting portion (5);Described Crane span structure fixed bolt hole (7) is provided with two connecting portions (2);Bracket fixing bolt hole is provided with 5th connecting portion (5) (11)。
2. steel construction fixed support according to claim 1, it is characterised in that the length of the first connecting portion (1) is Wire casing (9) height 1/2;Second connecting portion (2) length is more than wire casing (9) width, and second connecting portion (2) deducts wire casing (9) width Surplus, be exactly wire casing (9) left and right adjusting amount, and guarantee which on the same line;The length of the 5th connecting portion (5) is time purlin (10) the 1/2 of height.
3. steel construction fixed support according to claim 1, it is characterised in that " second " font crane span structure support (1) is led to Cross tapping screw (8) to be fixedly connected with girder steel.
4. steel construction fixed support according to claim 3, it is characterised in that be provided with the tapping screw (8) close Seal.
CN201620900659.7U 2016-08-18 2016-08-18 Steel construction fixed bolster Active CN206110482U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620900659.7U CN206110482U (en) 2016-08-18 2016-08-18 Steel construction fixed bolster

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620900659.7U CN206110482U (en) 2016-08-18 2016-08-18 Steel construction fixed bolster

Publications (1)

Publication Number Publication Date
CN206110482U true CN206110482U (en) 2017-04-19

Family

ID=58512495

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620900659.7U Active CN206110482U (en) 2016-08-18 2016-08-18 Steel construction fixed bolster

Country Status (1)

Country Link
CN (1) CN206110482U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109058730A (en) * 2018-07-16 2018-12-21 国网山西长治电力勘测设计有限公司 Fixation fitting for steel-structure factory building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109058730A (en) * 2018-07-16 2018-12-21 国网山西长治电力勘测设计有限公司 Fixation fitting for steel-structure factory building

Similar Documents

Publication Publication Date Title
CN206110482U (en) Steel construction fixed bolster
CN109812026A (en) A kind of high-altitude ceiling decoration aluminium sheet installation method and device
CN204492021U (en) The windproof fixture of standing seam roof slabs
CN204326438U (en) Hanging buckle structure and there is the wooden facing decorative wall of this hanging buckle structure
CN202990329U (en) Connection structure for interior decoration top surface expansion joints
CN204060442U (en) A kind of rail vehicle and outside hanging door weather shield installation assembly thereof
CN203948826U (en) A kind of prefabricated direct-buried thermal insulation pipe being connected by connection pipe fitting
CN107355035A (en) Glass curtain wall hidden frame system
CN202706837U (en) Mullion connecting piece for aluminum alloy door and aluminum alloy window
CN204531414U (en) Building pipe hole to be provided special tool
CN205195221U (en) Lightning -arrest checkpost of taking of T type
CN203623677U (en) Bullet train cab and bullet train
CN207082721U (en) The connecting plate of regulator cubicle
CN205504351U (en) Thermal -insulated type fixed support means
CN202164779U (en) Dry-hanging installation structure for vertical faces of stone materials
CN206344670U (en) A kind of door frame gasket structure
CN204551915U (en) A kind of metal roofing board fastening structure
CN206625627U (en) Novel fireproof type combined padding and drying system
CN201292588Y (en) Closed-top angle connecting structure for aluminium veneer curtain wall
CN206018076U (en) Novel butt welded flange
CN207177020U (en) Glass curtain wall hidden frame system
CN205894498U (en) High strength anticreep, leak protection tile modelled after an antique
CN204137134U (en) A kind of framework beam plug-in type jointing
CN204782658U (en) Decorate tripe
CN203977288U (en) Convenient cap

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant