CN206110160U - Communication tower ground prefabricated basis of formula - Google Patents
Communication tower ground prefabricated basis of formula Download PDFInfo
- Publication number
- CN206110160U CN206110160U CN201620948661.1U CN201620948661U CN206110160U CN 206110160 U CN206110160 U CN 206110160U CN 201620948661 U CN201620948661 U CN 201620948661U CN 206110160 U CN206110160 U CN 206110160U
- Authority
- CN
- China
- Prior art keywords
- strip footing
- communication tower
- steel framework
- tower ground
- strip
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Foundations (AREA)
Abstract
The utility model provides a communication tower ground prefabricated basis of formula, communication tower ground prefabricated basis of formula include a plurality of equidistance parallel distribution's strip footing and a plurality of equidistance parallel distribution's basic steel framework roof beam, basic steel framework roof beam perpendicular with the strip footing, all through the bolt fastening of predetermineeing in the strip footing between every foundation plinth steel framework roof beam and the all strip footings. The utility model provides a problem of the cycle length of the on -the -spot watering of original reinforced concrete to shorten the cycle greatly, also saved the transport volume simultaneously, practiced thrift manual work and cost.
Description
Technical field
This utility model is related to communication equipment field, specifically a kind of communication tower ground type prefabricated foundation.
Background technology
In existing communication tower manufacturing technology, generally using cast-in-situ steel reinforced concrete basis.The foundation construction method construction week
Phase is long, and scene discharge mud, sewage, destruction are afforested and damages road.
Traditional method foundation construction needs to excavate, pours, natural curing 20-28 days etc., and reinforced concrete foundation is easily produced
Raw building waste, it is larger to job site environmental effect.
Utility model content
This utility model is in order to solve problem of the prior art, there is provided a kind of communication tower ground type prefabricated foundation, solves
The problem of the cycle length of original armored concrete concreting in site, and the cycle is substantially reduced, while also saving transport
Amount, has saved artificial and cost.
This utility model provides a kind of communication tower ground type prefabricated foundation, including the bar shaped base of some equidistant parallels distribution
Plinth and the basic steel framework beam of some equidistant parallels distribution, described basic steel framework beam are vertical with strip footing, per pile foundation steel framework
Fixed by the default bolt in strip footing between beam and all of strip footing.
Further improve, described strip footing two ends are fixed with hanger.
The installation method of communication tower ground type prefabricated foundation, comprises the following steps:
1)Bottom of foundation ditch is tamped smooth by excavation pit, foundation ditch digging good utilisation stone;
2)Strip footing is sling by the hanger at strip footing two ends and is positioned over bottom of foundation ditch by loop wheel machine successively, makes some
The equidistant parallel distribution of shape basis;
3)Basic steel framework beam of slinging successively is positioned in basic blocks by the default bolt position of strip footing block, makes basic steel
Grid beam is vertical with strip footing;
4)The horizontal reference of the basic steel framework beam of adjustment and strip footing.
This utility model beneficial effect is:
1st, shorten the cycle of engineering construction, it is ensured that engineering is finished on schedule, to reach the requirement of base station Fast Construction.Simultaneously
Can solve the problems, such as that prefabricated foundation repeats to recycle, using the fabrication and installation mode more energy-conserving and environment-protective of prefabricated foundation,
Developed area and ecological protection are preferably regional, and use range is wider.
2nd, the destruction that capital construction is brought to surrounding is reduced, it is minimum to ecology influence, using light energy-saving material
Factory's intensive manufacture makes, and reducing site operation is affected and mud, sewage discharge by rainy weather, and energy saving saves material
Material and transport amount 30-50%, can be used repeatedly, substantially increase the success rate of capital construction;Factorial praluction,
Standardized designs, live quick assembling is more efficient, environmentally friendly, energy-conservation.
Description of the drawings
Fig. 1 is communication tower ground type prefabricated foundation structural representation.
Specific embodiment
This utility model provides a kind of communication tower ground type prefabricated foundation, and its structure is as shown in figure 1, including some equidistant
The strip footing 1 of parallel distribution and the basic steel framework beam 2 of some equidistant parallels distribution, described basic steel framework beam 2 and bar shaped base
Plinth 1 is vertical, is fixed by the default bolt in strip footing 1 between every pile foundation steel framework beam 2 and all of strip footing 1.
Further improve, described 1 two ends of strip footing are fixed with hanger.
The installation method of communication tower ground type prefabricated foundation, comprises the following steps:
1)Bottom of foundation ditch is tamped smooth by excavation pit, foundation ditch digging good utilisation stone;
2)Strip footing is sling by the hanger at strip footing two ends and is positioned over bottom of foundation ditch by loop wheel machine successively, makes some
The equidistant parallel distribution of shape basis;
3)Basic steel framework beam of slinging successively is positioned in basic blocks by the default bolt position of strip footing block, makes basic steel
Grid beam is vertical with strip footing;
4)The horizontal reference of the basic steel framework beam of adjustment and strip footing.
This utility model concrete application approach is a lot, and the above is only preferred implementation of the present utility model, should
Point out, for those skilled in the art, on the premise of without departing from this utility model principle, can also make
Go out some improvement, these improvement also should be regarded as protection domain of the present utility model.
Claims (2)
1. a kind of communication tower ground type prefabricated foundation, it is characterised in that:Including the strip footing of some equidistant parallels distribution(1)With
The basic steel framework beam of some equidistant parallel distributions(2), described basic steel framework beam(2)With strip footing(1)Vertically, per pile foundation
Steel framework beam(2)With all of strip footing(1)Between pass through strip footing(1)On default bolt fix.
2. communication tower ground type prefabricated foundation according to claim 1, it is characterised in that:Described strip footing(1)Two
End is fixed with hanger.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620948661.1U CN206110160U (en) | 2016-08-26 | 2016-08-26 | Communication tower ground prefabricated basis of formula |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620948661.1U CN206110160U (en) | 2016-08-26 | 2016-08-26 | Communication tower ground prefabricated basis of formula |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206110160U true CN206110160U (en) | 2017-04-19 |
Family
ID=58513626
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620948661.1U Active CN206110160U (en) | 2016-08-26 | 2016-08-26 | Communication tower ground prefabricated basis of formula |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206110160U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106436738A (en) * | 2016-08-26 | 2017-02-22 | 江苏铭远杆塔有限公司 | Ground prefabricated foundation of communication tower and mounting method of ground prefabricated foundation |
-
2016
- 2016-08-26 CN CN201620948661.1U patent/CN206110160U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106436738A (en) * | 2016-08-26 | 2017-02-22 | 江苏铭远杆塔有限公司 | Ground prefabricated foundation of communication tower and mounting method of ground prefabricated foundation |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103334356B (en) | The dark beam slab pavement system of bridge-type prefabricated reinforced concrete and construction method thereof | |
CN103352471B (en) | Container prefabricated house assembling type steel reinforced concrete single-double-column foundation and construction method thereof | |
CN104975605A (en) | Technology for recyclable reinforced concrete support | |
CN106436738A (en) | Ground prefabricated foundation of communication tower and mounting method of ground prefabricated foundation | |
CN112227759B (en) | Repair, reinforcement and migration method for historic building clean water wall | |
CN103334359A (en) | Fabricated precast reinforced concrete pavement slab and pavement construction method | |
CN103334361B (en) | Prefabricated hollow steel bar concrete wear resistant road surface plate and pavement construction method | |
CN204551532U (en) | Assembling cable shaft | |
CN103343503B (en) | Bridge-type prefabricated reinforced concrete trough slab wear resistant road surface structural system and construction method | |
CN103343547B (en) | Container type prefabricated house assembling steel reinforced concrete four patten and construction method | |
CN118257285A (en) | Assembled ecological retaining wall construction structure and construction method | |
CN206110160U (en) | Communication tower ground prefabricated basis of formula | |
CN106193120A (en) | Basement is encorbelmented, and base plate is inverse makees structure and construction method | |
CN103334360B (en) | The dark beam slab wear-resistant pavement system of bridge-type prefabricated reinforced concrete and construction method thereof | |
CN206034475U (en) | Prefabricated basis of communication tower underground | |
CN106436739A (en) | Underground prefabricated foundation of communication tower and mounting method of underground prefabricated foundation | |
CN208533570U (en) | A kind of prefabricated assembled fetal membrane | |
CN204418229U (en) | Poured band of outer wall of basement concrete draw-in groove | |
CN203429655U (en) | Assembly type steel reinforced concrete single-double column foundation for container prefabricated house | |
CN203145040U (en) | Prefabricated slab iron tower foundation convenient to disassemble and transport | |
CN206158255U (en) | Prefabricated assembled communication machinery room | |
CN203429528U (en) | Bridge-type precast-reinforced-concrete-trough-plate wear-resistant pavement structure system | |
CN201883422U (en) | Fabricated steel guide wall for underground continuous wall | |
CN203373631U (en) | Prefabricated reinforced concrete pavement slab | |
CN105401681B (en) | A kind of quick-assembling pitched roof and its method of construction based on assembled composite wall structure system |
Legal Events