CN206092016U - Stride that active fault is anti to glue tunnel preliminary bracing that slide moved - Google Patents
Stride that active fault is anti to glue tunnel preliminary bracing that slide moved Download PDFInfo
- Publication number
- CN206092016U CN206092016U CN201621045690.3U CN201621045690U CN206092016U CN 206092016 U CN206092016 U CN 206092016U CN 201621045690 U CN201621045690 U CN 201621045690U CN 206092016 U CN206092016 U CN 206092016U
- Authority
- CN
- China
- Prior art keywords
- steel
- flange plate
- concrete layer
- thin
- tunnel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn - After Issue
Links
- 239000003292 glue Substances 0.000 title 1
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 89
- 239000010959 steel Substances 0.000 claims abstract description 89
- 239000004567 concrete Substances 0.000 claims abstract description 42
- 238000007906 compression Methods 0.000 claims abstract description 26
- 239000011150 reinforced concrete Substances 0.000 claims abstract description 15
- 239000011435 rock Substances 0.000 claims description 12
- 230000006835 compression Effects 0.000 claims description 4
- 238000000034 method Methods 0.000 claims description 4
- 238000003466 welding Methods 0.000 claims description 4
- 239000007921 spray Substances 0.000 claims description 3
- 230000003014 reinforcing effect Effects 0.000 claims 3
- 230000015572 biosynthetic process Effects 0.000 claims 1
- 238000002347 injection Methods 0.000 claims 1
- 239000007924 injection Substances 0.000 claims 1
- 239000002689 soil Substances 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 15
- 238000005507 spraying Methods 0.000 description 7
- 238000006073 displacement reaction Methods 0.000 description 6
- 238000005452 bending Methods 0.000 description 4
- 239000011381 foam concrete Substances 0.000 description 4
- 238000010521 absorption reaction Methods 0.000 description 3
- 238000009412 basement excavation Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 230000001133 acceleration Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000002131 composite material Substances 0.000 description 1
- 238000005336 cracking Methods 0.000 description 1
- 230000001066 destructive effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
一种跨活动断层抗粘滑错动的隧道初期支护。其混凝土层为高压缩混凝土层,且在高压缩混凝土层的内壁上还喷射形成钢筋混凝土层;钢拱架由多段工字钢连接构成,连接处位于拱肩或拱脚部位的工字钢,其连接结构是:工字钢的端部焊接矩形的连接法兰板一;薄壁钢管的端部开有变形缺口形成长齿,且薄长齿端部焊接连接法兰板二;工字钢上的连接法兰板一与薄壁钢管上的连接法兰板二螺栓连接。其余工字钢的端部焊接矩形的连接法兰板一,相邻段的工字钢直接通过连接法兰板一螺栓连接。该种初期支护可吸收断层粘滑错动能量,减少断层错动对隧道的破坏,有效地提高隧道的抗震能力和抵抗断层粘滑错动破坏的能力;且其增加的施工量小、对施工进度影响小。
A kind of primary support for anti-stick-slip tunnel across active faults. The concrete layer is a high-compression concrete layer, and a reinforced concrete layer is sprayed on the inner wall of the high-compression concrete layer; the steel arch frame is composed of multi-section I-beam connections, and the connection is located at the I-beam at the spandrel or arch foot. Its connection structure is: the end of the I-beam is welded to a rectangular connecting flange plate 1; the end of the thin-walled steel pipe is opened with a deformation gap to form a long tooth, and the end of the thin long tooth is welded to connect the flange plate 2; the I-beam The first connecting flange plate on the upper part is connected with the second connecting flange plate on the thin-walled steel pipe by bolts. The ends of the remaining I-beams are welded to a rectangular connecting flange plate 1, and the adjacent sections of I-beams are directly connected by connecting flange plates 1-bolts. This kind of primary support can absorb the energy of fault stick-slip dislocation, reduce the damage of fault dislocation to the tunnel, and effectively improve the tunnel's seismic capacity and ability to resist fault stick-slip dislocation damage; Little impact on construction progress.
Description
技术领域technical field
本实用新型涉及一种跨越活动断层抗粘滑错动的隧道初期支护。The utility model relates to a tunnel primary support for anti-stick-slip movement across active faults.
背景技术Background technique
暗挖隧道按新奥法原理施工,采用复合式衬砌支护,包括初期支护和二次衬砌。其中,初期支护和围岩共同组成的支护系统是主要承载结构,二次衬砌主要作为安全储备。初期支护包括在围岩上喷射形成的钢筋混凝土层、钢筋混凝土层中纵向排列的马蹄形钢拱架,钢拱架之间纵向连接钢筋。Underground excavation tunnels are constructed according to the principle of the New Austrian Method, using composite lining support, including primary support and secondary lining. Among them, the support system composed of primary support and surrounding rock is the main bearing structure, and the secondary lining is mainly used as a safety reserve. The primary support includes a reinforced concrete layer formed by spraying on the surrounding rock, horseshoe-shaped steel arches arranged longitudinally in the reinforced concrete layer, and longitudinally connected steel bars between the steel arches.
随着城市化进程的加速、隧道工程的大量兴建,将不可避免地遇到隧道结构跨越活动断层的问题。活动断层是指那些在近代或历史时期内新生或有过继承运动和位移,以及在不久的将来可能再生或继续运动和位移的断层。地震的发生与活动断层有直接关系。With the acceleration of urbanization and the construction of a large number of tunnel projects, it is inevitable to encounter the problem of tunnel structures crossing active faults. Active faults refer to those faults that were newly born or had inherited movement and displacement in modern or historical periods, and may regenerate or continue to move and displace in the near future. The occurrence of earthquakes is directly related to active faults.
活动断层错动尤其是突发性大变形的错动即粘滑错动时,穿越断层段地铁隧道支护结构处于复杂的三维空间应力状态,兼备拉压、剪切、扭转和弯曲的破坏作用。带钢拱架的钢筋混凝土层刚性初期支护和刚性的二次衬砌在这种强力破坏作用下,会产生弯曲、拉伸、扭转等三维空间永久性形变,表现出开裂、坍塌等多种复杂的破坏形式,严重影响隧道的安全运营。When active fault dislocation, especially the dislocation of sudden large deformation, i.e. stick-slip dislocation, the support structure of the subway tunnel crossing the fault section is in a complex three-dimensional stress state, and has the destructive effects of tension and compression, shear, torsion and bending . The rigid primary support of the reinforced concrete layer with the steel arch frame and the rigid secondary lining will produce three-dimensional permanent deformations such as bending, stretching, and torsion under the action of such strong damage, showing various complexities such as cracking and collapse. The form of damage seriously affects the safe operation of the tunnel.
活动断层的粘滑错动具有随机性、强破坏性等特点,因此,对于穿越活动断层的隧道结构不能一味采用刚度大、支护强、延展性差的支护手段抑制围岩变形,而应该采用可以有效适应断层错动位移的柔性支护措施。The stick-slip dislocation of active faults has the characteristics of randomness and strong destructiveness. Therefore, for tunnel structures passing through active faults, support methods with high rigidity, strong support, and poor ductility should not be used blindly to suppress the deformation of surrounding rock, but should be adopted. Flexible support measures that can effectively adapt to fault displacement.
申请号为201310491821.5的中国专利申请公开了一种“跨越活动断层的隧道支护结构”,该隧道支护结构在断层跨越段的初期支护和二次衬砌之间增设有一次衬砌和泡沫混凝土层及泡沫混凝土层内表面的第二防水层。增设的一次衬砌能够部分承受来自于断层蠕滑产生的应力;同时,通过泡沫混凝土层提供错动的位移空间并有效吸收能量,从而减少甚至消除隧道受断层错动的影响,并能保持隧道的防水性能。其存在的问题是:由于增加了一次衬砌、泡沫混凝土层、第二防水层共三个混凝土层,因此增加了三次浇筑混凝土,加大了施工量,施工效率降低,严重影响了施工进度。The Chinese patent application with the application number 201310491821.5 discloses a "tunnel support structure across active faults". The tunnel support structure has a primary lining and a foam concrete layer between the primary support and the secondary lining of the fault spanning section. And the second waterproof layer on the inner surface of the foam concrete layer. The added primary lining can partly bear the stress caused by fault creep; at the same time, the foam concrete layer provides displacement space for displacement and effectively absorbs energy, thereby reducing or even eliminating the influence of fault displacement on the tunnel and maintaining the tunnel’s Water resistance. The existing problems are: due to the addition of three concrete layers including the primary lining, the foam concrete layer, and the second waterproof layer, three times of pouring concrete are added, which increases the amount of construction, reduces construction efficiency, and seriously affects the construction progress.
实用新型内容Utility model content
本实用新型的发明目的是提供一种隧道跨越活动断层抗粘滑错动的隧道初期支护。该隧道初期支护可吸收断层粘滑错动能量,减少断层错动对隧道的破坏,有效地提高隧道的抗震能力和抵抗断层粘滑错动破坏的能力;且其增加的施工量小、对施工进度影响小。The purpose of the invention of the utility model is to provide a tunnel primary support for anti-stick-slip movement across active faults. The initial support of the tunnel can absorb the energy of fault stick-slip dislocation, reduce the damage of fault dislocation to the tunnel, and effectively improve the tunnel's earthquake resistance and ability to resist fault stick-slip dislocation damage; Little impact on construction progress.
本实用新型实现其发明目的所采用的技术方案是,一种跨活动断层抗粘滑错动的隧道初期支护,包括在围岩上喷射形成的马蹄形的混凝土层、混凝土层中纵向排列的马蹄形的钢拱架,钢拱架之间通过纵向连接钢筋(2)焊接连接,其特征在于:The technical scheme adopted by the utility model to realize the purpose of the invention is a kind of initial support for a tunnel that crosses active faults and resists stick-slip dislocation, including a horseshoe-shaped concrete layer formed by spraying on the surrounding rock, and a horseshoe-shaped concrete layer arranged vertically in the concrete layer. The steel arch frame is welded and connected by longitudinal connecting steel bars (2) between the steel arch frames, and is characterized in that:
所述的混凝土层为高压缩混凝土层,且在高压缩混凝土层的内壁上还喷射形成有钢筋混凝土层;The concrete layer is a high-compression concrete layer, and a reinforced concrete layer is formed by spraying on the inner wall of the high-compression concrete layer;
所述的钢拱架由多段工字钢连接构成,其连接结构是:The steel arch frame is composed of multiple sections of I-beam connections, and its connection structure is:
连接处位于拱肩或拱脚部位的工字钢,其连接结构是:工字钢的端部焊接矩形的连接法兰板一;薄壁钢管的端部开有变形缺口形成周向排列的长齿,且薄壁钢管的长齿端部焊接矩形的连接法兰板二;工字钢上的连接法兰板一与薄壁钢管上的连接法兰板二螺栓连接。The I-beam whose connection is located at the spandrel or arch foot, its connection structure is: the end of the I-beam is welded to a rectangular connecting flange plate 1; the end of the thin-walled steel pipe has a deformation gap to form a circumferentially arranged long Teeth, and the end of the long teeth of the thin-walled steel pipe is welded to the second rectangular connecting flange plate; the first connecting flange plate on the I-beam is connected with the second connecting flange plate on the thin-walled steel pipe by bolts.
其余的工字钢的连接结构是:工字钢的端部焊接矩形的连接法兰板一,相邻段的工字钢直接通过连接法兰板一螺栓连接。The connection structure of the remaining I-beams is: the end of the I-beam is welded to a rectangular connecting flange plate 1, and the adjacent sections of I-beams are directly connected by connecting flange plates 1-bolts.
与现有技术相比,本实用新型的隧道初期支护的有益效果是:Compared with the prior art, the beneficial effect of the tunnel initial support of the utility model is:
一、初期支护的内层为钢筋混凝土结构,外层为包括柔性连接结构的钢拱架高压缩混凝土层。当隧道结构承受正常使用荷载时,留有变形缺口的薄壁钢管不发生屈服,可保证整个衬砌的强度,满足正常使用状态下结构安全。1. The inner layer of the primary support is a reinforced concrete structure, and the outer layer is a steel arch high-compression concrete layer including a flexible connection structure. When the tunnel structure bears normal loads, the thin-walled steel pipes with deformation gaps do not yield, which can ensure the strength of the entire lining and meet the structural safety under normal use conditions.
二、当活动断层发生粘滑错动时,支护结构荷载增加,荷载主要增加在钢拱架拱肩、拱脚等弯矩较大部位,这些部位埋设的薄壁钢管上的长齿沿隧道的周向(薄壁钢管的轴向)发生压缩,从而主动增大钢拱架及整个混凝土结构的变形,可以减少支护结构的应力增量,并且可使衬砌受力更均匀,可以大幅减少衬砌在断层发生错动时衬砌的永久裂缝和破坏。总之,本实用新型含有薄壁柔性钢管的钢拱架与高压缩混凝土层构成柔性支护层,形成“外柔内刚”的衬砌构造,达到吸能抗震的作用。2. When the stick-slip dislocation occurs on the active fault, the load of the supporting structure increases, and the load mainly increases at the parts with large bending moments such as the spandrel and arch foot of the steel arch frame. The long teeth on the thin-walled steel pipes buried in these parts along the tunnel The circumferential direction of the thin-walled steel pipe (the axial direction of the thin-walled steel pipe) is compressed, thereby actively increasing the deformation of the steel arch and the entire concrete structure, which can reduce the stress increment of the supporting structure, and can make the lining force more uniform, which can greatly reduce Permanent cracks and failure of the lining when the fault occurs. In a word, the utility model contains a steel arch frame with thin-walled flexible steel pipes and a high-compression concrete layer to form a flexible support layer, forming a lining structure of "soft outside and rigid inside", achieving the effect of energy absorption and earthquake resistance.
三、本实用新型仅需在钢拱架中弯矩作用大的连接部位增加带柔性薄壁钢管结构;并将原有的钢筋混凝土层改为高压缩混凝土层,再增加一层钢筋混凝土层,从施工量而言,仅是增加了一层高压缩混凝土层,其总的施工量远远低于增设三个混凝土层,进行三次浇筑混凝土的施工量,其增加的施工量小、对施工进度影响小。3. The utility model only needs to add a flexible thin-walled steel pipe structure in the connection part of the steel arch frame where the bending moment is large; and change the original reinforced concrete layer into a high-compression concrete layer, and then add a layer of reinforced concrete layer, In terms of construction volume, only one layer of high-compression concrete layer is added, and the total construction volume is far lower than the construction volume of adding three concrete layers and pouring concrete three times. The increased construction volume is small and affects the construction progress. Small impact.
进一步,本实用新型的薄壁钢管还与锥形钢套筒的小口套合,锥形钢套筒将薄壁钢管的长齿罩住;且锥形钢套筒的大口的口沿与连接法兰板二焊接。Further, the thin-walled steel pipe of the present utility model is also fitted with the small mouth of the tapered steel sleeve, and the tapered steel sleeve covers the long teeth of the thin-walled steel pipe; The second welding of the blue plate.
这样,锥形套筒将薄壁钢管的长齿罩住,既可以防止活动断层水平错动时薄壁钢管发生隧道径向剪切移动,导致钢拱架发生剪切破坏,同时又不妨碍薄壁钢管的长齿发生沿隧道周向的压缩变形,达到吸能抗震的作用。In this way, the tapered sleeve covers the long teeth of the thin-walled steel pipe, which can prevent the radial shear movement of the thin-walled steel pipe during the horizontal displacement of the active fault, resulting in shear failure of the steel arch, and at the same time does not hinder the thin-walled steel pipe. The long teeth of the wall steel pipe undergo compressive deformation along the tunnel circumference to achieve the function of energy absorption and earthquake resistance.
更进一步,本实用新型的高压缩混凝土层的厚度为18-30cm,钢筋混凝土层的厚度为18-30cm;所述的连接法兰板一和连接法兰板二均为24cm×20cm×1.5cm的钢制法兰板;所述的纵向连接钢筋为直径2.2cm的螺纹钢;所述的薄壁钢管的直径为15cm,长度为30cm-50cm,壁厚为2.0cm;长齿的长度为8cm-16cm。Furthermore, the thickness of the high-compression concrete layer of the present invention is 18-30cm, and the thickness of the reinforced concrete layer is 18-30cm; the first connecting flange plate and the second connecting flange plate are 24cm×20cm×1.5cm The steel flange plate; the longitudinal connecting steel bar is a threaded steel bar with a diameter of 2.2cm; the diameter of the thin-walled steel pipe is 15cm, the length is 30cm-50cm, and the wall thickness is 2.0cm; the length of the long teeth is 8cm -16cm.
相邻钢拱架的纵向间距为长1.0m,相邻纵向连接钢筋间的环向间距为1.0m。The longitudinal spacing of adjacent steel arches is 1.0m long, and the circumferential spacing between adjacent longitudinal connecting steel bars is 1.0m.
选取的这些参数,既能够保证隧道结构具有足够的强度,满足正常使用状态下结构安全。同时又能够形成“外柔内刚”的衬砌构造,达到吸能抗震的作用,有效减少衬砌在断层发生错动时衬砌的永久裂缝和破坏。These selected parameters can not only ensure that the tunnel structure has sufficient strength, but also meet the structural safety under normal use conditions. At the same time, it can form a lining structure of "soft on the outside and rigid on the inside" to achieve the effect of energy absorption and earthquake resistance, and effectively reduce the permanent cracks and damage of the lining when the fault occurs.
本实用新型的初期支护的修建方法是:The construction method of the primary support of the present utility model is:
a、将所述的钢拱架架于开挖的围岩壁上,并在相邻的钢拱架之间焊接纵向连接钢筋;a, the steel arches are framed on the surrounding rock wall of the excavation, and the longitudinal connecting steel bars are welded between adjacent steel arches;
b、向开挖的围岩壁喷射高压缩混凝土,在围岩壁上形成所述的高压缩混凝土层,且高压缩混凝土层将所述的钢拱架完全覆盖;b. spraying high-compression concrete to the excavated surrounding rock wall to form the high-compression concrete layer on the surrounding rock wall, and the high-compression concrete layer completely covers the steel arch;
c、待高压缩混凝土层凝固后,在高压缩混凝土层的内壁上绑扎钢筋、再喷射混凝土,形成所述的钢筋混凝土层,即完成隧道初期支护的建造。c. After the high-compression concrete layer is solidified, tie steel bars on the inner wall of the high-compression concrete layer, and then spray concrete to form the reinforced concrete layer, that is, complete the construction of the initial support of the tunnel.
下面结合附图和具体实施方式对本实用新型做进一步详细描述。The utility model is further described in detail below in conjunction with the accompanying drawings and specific embodiments.
附图说明Description of drawings
图1为本实用新型实施例的纵向断面结构示意图。Fig. 1 is a schematic diagram of a longitudinal section structure of an embodiment of the utility model.
图2为图1的A-A剖视图。Fig. 2 is a sectional view along line A-A of Fig. 1 .
图3为图2的C部的局部放大图。FIG. 3 is a partially enlarged view of part C in FIG. 2 .
具体实施方式detailed description
实施例Example
图1-3示出,本实用新型的一种具体实施方式是,一种跨活动断层抗粘滑错动的隧道初期支护,一种跨活动断层抗粘滑错动的隧道初期支护,包括在围岩上喷射形成的马蹄形的混凝土层、混凝土层中纵向排列的马蹄形的钢拱架,钢拱架之间通过纵向连接钢筋2焊接连接,其特征在于:Figures 1-3 show that a specific embodiment of the present invention is an initial support for a tunnel that crosses active faults and resists stick-slip dislocation, a kind of tunnel initial support that crosses active faults and resists stick-slip dislocation, It includes a horseshoe-shaped concrete layer formed by spraying on the surrounding rock, and horseshoe-shaped steel arches arranged longitudinally in the concrete layer. The steel arches are connected by welding longitudinally connecting steel bars 2, which are characterized in that:
所述的混凝土层为高压缩混凝土层3,且在高压缩混凝土层3的内壁上还喷射形成有钢筋混凝土层4;The concrete layer is a high-compression concrete layer 3, and a reinforced concrete layer 4 is formed by spraying on the inner wall of the high-compression concrete layer 3;
所述的钢拱架由多段工字钢11连接构成,其连接结构是:The steel arch frame is composed of multiple sections of I-beams 11 connected, and its connection structure is:
图2、图3示出,连接处位于拱肩或拱脚部位的工字钢11,其连接结构是:工字钢11的端部焊接矩形的连接法兰板一12a;薄壁钢管14的端部开有变形缺口形成周向排列的长齿14a,且薄壁钢管14的长齿14a端部焊接矩形的连接法兰板二12b;工字钢11上的连接法兰板一12a与薄壁钢管14上的连接法兰板二12b螺栓连接。Fig. 2, Fig. 3 show, the I-beam 11 that the junction is positioned at spandrel or arch foot position, its connection structure is: the end of I-beam 11 is welded rectangular connection flange plate-12a; Thin-walled steel pipe 14 There are deformation gaps at the end to form long teeth 14a arranged in the circumferential direction, and the end of the long teeth 14a of the thin-walled steel pipe 14 is welded to a rectangular connecting flange plate 2 12b; The connecting flange plate 2 12b on the wall steel pipe 14 is bolted.
其余的工字钢11的连接结构是:工字钢11的端部焊接矩形的连接法兰板一12a,相邻段的工字钢11直接通过连接法兰板一12a螺栓连接。The connection structure of the rest of the I-beams 11 is: the end of the I-beams 11 is welded to a rectangular connecting flange plate-12a, and the I-beams 11 of adjacent sections are directly connected by bolts of the connecting flange plates-12a.
图2、图3示出,本例的薄壁钢管14还与锥形钢套筒15的小口套合,锥形钢套筒15将薄壁钢管14的长齿14a罩住;且锥形钢套筒15的大口的口沿与连接法兰板二12b焊接。Figure 2 and Figure 3 show that the thin-walled steel pipe 14 of this example is also fitted with the small opening of the tapered steel sleeve 15, and the tapered steel sleeve 15 covers the long teeth 14a of the thin-walled steel pipe 14; The mouth edge of the big mouth of sleeve 15 is welded with connecting flange plate two 12b.
本例的高压缩混凝土层3的厚度为18-30cm,钢筋混凝土层4的厚度为18-30cm;所述的连接法兰板一12a和连接法兰板二12b均为24cm×20cm×1.5cm的钢制法兰板;所述的纵向连接钢筋2为直径2.2cm的螺纹钢;所述的薄壁钢管14的直径为15cm,长度为30cm-50cm,壁厚为2.0cm;长齿14a的长度为8cm-16cm。The thickness of the high-compression concrete layer 3 of this example is 18-30cm, and the thickness of the reinforced concrete layer 4 is 18-30cm; Described connection flange plate one 12a and connection flange plate two 12b are 24cm * 20cm * 1.5cm steel flange plate; the longitudinal connecting steel bar 2 is screw steel with a diameter of 2.2cm; the diameter of the thin-walled steel pipe 14 is 15cm, the length is 30cm-50cm, and the wall thickness is 2.0cm; the long teeth 14a The length is 8cm-16cm.
相邻钢拱架的纵向间距为长1.0m,相邻纵向连接钢筋2间的环向间距为1.0m。The longitudinal distance between adjacent steel arches is 1.0m long, and the circumferential distance between adjacent longitudinal connecting steel bars 2 is 1.0m.
本例的跨活动断层抗粘滑错动的隧道初期支护的建造方法如下:In this example, the construction method of the primary support for the anti-stick-slip dislocation of the tunnel across the active fault is as follows:
a、将所述的钢拱架架于开挖的围岩壁上,并在相邻的钢拱架之间焊接纵向连接钢筋2;a, the steel arches are framed on the surrounding rock wall of the excavation, and the longitudinal connecting steel bars 2 are welded between adjacent steel arches;
b、向开挖的围岩壁喷射高压缩混凝土,在围岩壁上形成所述的高压缩混凝土层3,且高压缩混凝土层3将所述的钢拱架完全覆盖;b. Spraying high-compression concrete to the excavated surrounding rock wall to form the high-compression concrete layer 3 on the surrounding rock wall, and the high-compression concrete layer 3 completely covers the steel arch;
c、待高压缩混凝土层3凝固后,在高压缩混凝土层3的内壁上绑扎钢筋、再喷射混凝土,形成所述的钢筋混凝土层4,即完成隧道初期支护的建造。c. After the high-compression concrete layer 3 is solidified, tie steel bars on the inner wall of the high-compression concrete layer 3 and then spray concrete to form the reinforced concrete layer 4, which is to complete the construction of the initial support of the tunnel.
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621045690.3U CN206092016U (en) | 2016-09-09 | 2016-09-09 | Stride that active fault is anti to glue tunnel preliminary bracing that slide moved |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621045690.3U CN206092016U (en) | 2016-09-09 | 2016-09-09 | Stride that active fault is anti to glue tunnel preliminary bracing that slide moved |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206092016U true CN206092016U (en) | 2017-04-12 |
Family
ID=58476278
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621045690.3U Withdrawn - After Issue CN206092016U (en) | 2016-09-09 | 2016-09-09 | Stride that active fault is anti to glue tunnel preliminary bracing that slide moved |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206092016U (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106194215A (en) * | 2016-09-09 | 2016-12-07 | 西南交通大学 | A kind of Tunnel dynamic across the anti-stick slide of active fault and method of construction thereof |
CN107575242A (en) * | 2017-09-25 | 2018-01-12 | 许生安 | A kind of tunnel structure of high-strength anti-seismic |
CN107780951A (en) * | 2017-11-01 | 2018-03-09 | 中交第公路勘察设计研究院有限公司 | High ground stress soft rock stress large deformation preliminary bracing system |
CN108119166A (en) * | 2017-12-15 | 2018-06-05 | 西南交通大学 | Across the large-scale activity fracture belt tunnel prefbricated tunnel lining structure in meizoseismal area and tunnel |
CN111764930A (en) * | 2020-06-05 | 2020-10-13 | 中南大学 | A kind of tunnel support structure with honeycomb energy absorbing device and construction method thereof |
-
2016
- 2016-09-09 CN CN201621045690.3U patent/CN206092016U/en not_active Withdrawn - After Issue
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106194215A (en) * | 2016-09-09 | 2016-12-07 | 西南交通大学 | A kind of Tunnel dynamic across the anti-stick slide of active fault and method of construction thereof |
CN107575242A (en) * | 2017-09-25 | 2018-01-12 | 许生安 | A kind of tunnel structure of high-strength anti-seismic |
CN109162728A (en) * | 2017-09-25 | 2019-01-08 | 许生安 | A kind of tunnel structure of high-strength anti-seismic |
CN109162728B (en) * | 2017-09-25 | 2020-01-10 | 济宁市鸿翔公路勘察设计研究院有限公司 | High-strength anti-seismic tunnel structure |
CN107780951A (en) * | 2017-11-01 | 2018-03-09 | 中交第公路勘察设计研究院有限公司 | High ground stress soft rock stress large deformation preliminary bracing system |
CN107780951B (en) * | 2017-11-01 | 2024-03-01 | 中交第一公路勘察设计研究院有限公司 | High-ground-stress soft rock large-deformation primary support system |
CN108119166A (en) * | 2017-12-15 | 2018-06-05 | 西南交通大学 | Across the large-scale activity fracture belt tunnel prefbricated tunnel lining structure in meizoseismal area and tunnel |
CN111764930A (en) * | 2020-06-05 | 2020-10-13 | 中南大学 | A kind of tunnel support structure with honeycomb energy absorbing device and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206092016U (en) | Stride that active fault is anti to glue tunnel preliminary bracing that slide moved | |
CN105113389B (en) | Prefabricated steel-concrete composite structure pier column member | |
AU2017415961B2 (en) | Prefabricated dual-steel-tube concrete shear wall, and assembly method therefor | |
CN108412128A (en) | A kind of connection structure of steel core concrete column | |
CN107190635B (en) | Dumbbell-shaped concrete-filled steel tubular composite pier and its connection structure and method with bearing platform | |
CN105484152B (en) | A kind of bridge pier of additional mild steel damper and cushion cap attachment structure | |
CN106194215B (en) | A kind of Tunnel and its method of construction moved across the anti-stick slide of active fault | |
CN106013518A (en) | Assembly type concrete column partially and externally wrapped by H-shaped steel and energy dissipation steel plate shear wall structure | |
CN111593926A (en) | H-beam partially filled concrete composite column-reinforced concrete beam joint and its design method | |
CN106836490A (en) | A kind of prestressing force assembled high-performance concrete-filled steel square tubular column concrete girder connection and its construction method | |
CN108532760A (en) | The double girder steel connection structures of half perforation coupled column-perforation and its construction method | |
CN108867341A (en) | A kind of GFRP pipe-concrete-shaped steel combination foot joint and its construction method | |
CN106368348A (en) | Overlapped combined shear wall with double-phase stress characteristic | |
CN106968332A (en) | A kind of prestressing force assembled high-performance concrete-filled circular steel tube column concrete girder connection and its construction method | |
CN206486819U (en) | A kind of stable support body system for ensureing continuous beam cantilever casting construction | |
CN101492918B (en) | A Beam-column Joint Used in Foundation Pit Engineering of Upside-Down Method | |
CN104652704B (en) | Connected installation and calculation methods for inner pipes and outer pipes of pipe-in-pipe concrete-filled steel tube tension members | |
CN206625404U (en) | A kind of concrete filled steel tube organ timbering shear wall with type steel support | |
CN114165269A (en) | Composite support system and construction technology based on steel-concrete composite support and spray canal | |
CN110847057A (en) | A flexible connection structure for continuous box girder cantilever casting | |
CN205088688U (en) | Shaped steel and prestressed reinforced concrete combination structure support | |
CN214401388U (en) | FRP cable arch structure after optimizing | |
CN206829416U (en) | A kind of prefabricated assembled double steel pipe concrete shear force wall | |
CN206360399U (en) | The existing reinforced concrete coupling beam bracing means of one species " doubly-linked beam " | |
CN202360108U (en) | Compound supporting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
AV01 | Patent right actively abandoned | ||
AV01 | Patent right actively abandoned |
Granted publication date: 20170412 Effective date of abandoning: 20180817 |