CN206072746U - A kind of charger of GIS electrical equipment air chamber - Google Patents

A kind of charger of GIS electrical equipment air chamber Download PDF

Info

Publication number
CN206072746U
CN206072746U CN201621098002.XU CN201621098002U CN206072746U CN 206072746 U CN206072746 U CN 206072746U CN 201621098002 U CN201621098002 U CN 201621098002U CN 206072746 U CN206072746 U CN 206072746U
Authority
CN
China
Prior art keywords
ball valve
gas
electrical equipment
gis
port
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621098002.XU
Other languages
Chinese (zh)
Inventor
庄建煌
林荔晟
康建生
周静
黄少炜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Putian Power Supply Co of State Grid Fujian Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Putian Power Supply Co of State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Fujian Electric Power Co Ltd, Putian Power Supply Co of State Grid Fujian Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201621098002.XU priority Critical patent/CN206072746U/en
Application granted granted Critical
Publication of CN206072746U publication Critical patent/CN206072746U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Abstract

The utility model discloses a kind of charger of GIS electrical equipment air chamber, including SF6Gas cylinder, air relief valve, aerating pipe, also including first gas retracting device, four-way connection, pressure gauge, the first ball valve, the second ball valve, the 3rd ball valve and the 4th ball valve, SF6The gas outlet of gas cylinder passes sequentially through the first port that air relief valve, the first ball valve, aerating pipe, the second ball valve connect four-way connection, and the second port of four-way connection connects GIS electrical equipment air chambers by the 3rd ball valve;3rd port of four-way connection connects first gas retracting device by the 4th ball valve;Pressure gauge is arranged on the 4th port of four-way connection.This utility model avoids the air in aerating pipe from entering in GIS air chambers, solves SF in GIS air chambers6The excessive problem of gas moisture content.

Description

A kind of charger of GIS electrical equipment air chamber
Technical field
This utility model is related to a kind of aerating device, more particularly to a kind of charger of GIS electrical equipment air chamber.
Background technology
In recent years, with SF6Gas is used widely as the GIS electrical equipments of dielectric, and current GIS switchs SF6Gas The inflation method of body is to adopt SF6Gas cylinder is to the direct inflation of GIS device, and SF every time6Can all bring into during gas inflated a certain amount of Air, and in air, contain a certain amount of moisture, cause SF in GIS device air chamber6Gas water content is excessive, and works as moisture When excessive, harm will be produced.
Utility model content
This utility model provides a kind of charger of GIS electrical equipment air chamber, which overcomes the deficiency described in background technology Part.
This utility model solves the technical scheme adopted by its technical problem:A kind of charger of GIS electrical equipment air chamber, Including SF6Gas cylinder, air relief valve, aerating pipe, also including first gas retracting device, four-way connection, pressure gauge, the first ball valve, Second ball valve, the 3rd ball valve and the 4th ball valve, SF6The gas outlet of gas cylinder pass sequentially through air relief valve, the first ball valve, aerating pipe, Second ball valve connects the first port of four-way connection, and the second port of four-way connection connects GIS electrical equipment air chambers by the 3rd ball valve; 3rd port of four-way connection connects first gas retracting device by the 4th ball valve;Pressure gauge is arranged on the 4th of four-way connection On port.
Further, also including some snap joints, between first ball valve and the aerating pipe, second ball Snap joint is connected between valve and the aerating pipe, between the 3rd ball valve and GIS electrical equipment air chambers.
Further, pressure gauge is installed on the air relief valve.
Further, the first gas retracting device is gas reclaiming bag.
Further, the first gas retracting device passes sequentially through first gas recovery tube, the 5th ball valve and quickly connects Head connection the 4th ball valve.
Compared to prior art, this utility model has the advantages that:
1st, due to also including first gas retracting device, four-way connection, pressure gauge, the first ball valve, the second ball valve, the 3rd ball Valve and the 4th ball valve so that during inflation, the air in aerating pipe can be by SF6Gas is discharged to first gas retracting device In, it is to avoid the air in aerating pipe is entered in GIS air chambers, solves SF in GIS air chambers6Gas moisture content is excessive to ask Topic;The characteristics of this utility model also has simple to operate, safe and reliable.
2nd, as first ball valve, the second ball valve, the 3rd ball valve and the 4th ball valve are respectively adopted snap joint connection phase Answer pipeline so that the characteristics of this utility model also has convenient dismounting, raising work efficiency.
This utility model is described in further detail below in conjunction with drawings and Examples;But one kind of the present utility model The charger of GIS electrical equipment air chambers is not limited to embodiment.
Description of the drawings
Fig. 1 is decomposing schematic representation of the present utility model.
Specific embodiment
Embodiment, a kind of shown in Figure 1, charger of GIS electrical equipment air chamber of the present utility model, including SF6Gas Bottle 10, air relief valve 8, aerating pipe 13, also including first gas retracting device 11, four-way connection 5, pressure gauge 6, the first ball valve 41st, the second ball valve 42, the 3rd ball valve 43 and the 4th ball valve 44.Four-way connection 5 has four ports, is defined as first end successively Mouth, second port, the 3rd port and the 4th port.SF6The gas outlet of gas cylinder 10 passes sequentially through air relief valve 8, the first ball valve 41, fills Feed channel 13, the second ball valve 42 connect the first port of four-way connection 5, and the second port of four-way connection 5 passes through the 3rd ball valve 43 Connection GIS electrical equipment air chamber 1;3rd port of four-way connection 5 connects first gas retracting device 11 by the 4th ball valve 44;Pressure Table 6 is arranged on the 4th port of four-way connection 5.Pressure gauge 9 is also installed on the air relief valve 8.
Also include that second gas retracting device (not embodying in figure) and the gas cylinder filled with air (are not embodied in figure, below letter Claim air gas cylinder), with when inflation is completed to GIS electrical equipment air chamber 1, by the SF6Gas cylinder 10 is replaced by air gas cylinder, by first Gas concentration unit 11 is replaced by second gas retracting device.The first gas retracting device 11 and the second gas are reclaimed Device is gas reclaiming bag.
In the present embodiment, also including some snap joints, between first ball valve 41 and the aerating pipe 13, described One is connected between second ball valve 42 and the aerating pipe 13, between the 3rd ball valve 43 and GIS electrical equipment air chamber 1 Snap joint, that is, the first ball valve 41 connects one end of aerating pipe 13 by snap joint, and the second ball valve 42 is by quickly connecing The other end of head connection aerating pipe 13, the 3rd ball valve 43 connect the air inlet of GIS electrical equipment air chamber 1 by snap joint.It is described Snap joint includes male 7 and female 3, and the two is by realizing quick connection to inserting.Described each ball valve is respectively stainless steel Matter.
In the present embodiment, the first gas retracting device 11 passes sequentially through first gas recovery tube 12, the 5th ball valve 45 Connect the 4th ball valve 44 with snap joint.The second gas retracting device be connected with turn second gas recovery tube, The female (or male) of six ball valves and snap joint, therefore, during replacing, the 5th ball valve 45 need to be closed only, first gas are returned Female (or male) dismounting of receiving apparatus 11, first gas recovery tube 12, the 5th ball valve 45 and its snap joint for being connected Get off, then make second gas retracting device pass sequentially through second gas recovery tube, the 6th ball valve and snap joint connection described the Four ball valves 44, not only easy accessibility, can also utilize the 5th ball valve, the 6th ball valve to ensure the sealing of gas, it is to avoid the When one gas concentration unit 11 and second gas retracting device are disassembled, the gas effusion reclaimed by which.
A kind of charger of GIS electrical equipment air chamber of the present utility model, its course of work are as follows:
The 3rd ball valve 43 is closed, the first ball valve 41, the second ball valve 42, the 4th ball valve 44 and the 5th ball valve 45 is opened, is opened Air relief valve 8 and SF6Gas cylinder 10, makes SF6Gas cylinder 10 was deflated after some seconds, closed SF6Gas cylinder 10, the sky in such aerating pipe 13 Gas is just by SF6Gas is discharged in first gas retracting device 11;
During inflation, the 4th ball valve 44 is closed, open the 3rd ball valve 43 and SF6Gas cylinder 10, makes SF6Gas passes sequentially through decompression Valve 8, the first ball valve 41, aerating pipe 13, the second ball valve 42, four-way connection 5, the 3rd ball valve 43 are entered in GIS electrical equipment air chamber 1. When air bound authorized pressure is pointed to Deng gauge hand, close SF6Gas cylinder, air relief valve 8, the first ball valve 41, the second ball valve the 42, the 3rd Ball valve 43, the 4th ball valve 44 and the 5th ball valve 45, complete the inflation to GIS electrical equipment air chamber 1;
When completing inflation, by the SF6Gas cylinder 10 is replaced by air gas cylinder, and first gas retracting device 11 is replaced by Two gas concentration units (are changed in the lump together with the female of the snap joint of first gas recovery tube 12, the 5th ball valve and its connection For the female of the snap joint of the second gas recovery tube, the 6th ball valve and its connection), and the 3rd ball valve 43 is remained turned-off, Air gas cylinder, air relief valve 8, the first ball valve 41, the second ball valve 42, the 4th ball valve 44 and the 6th ball valve are opened, air is released some After second, air gas cylinder, so, remaining SF in aerating pipe 13 are closed6Gas is by efficient recovery to second gas retracting device In.
Above-described embodiment is only used for the charger for further illustrating a kind of GIS electrical equipment air chamber of the present utility model, but this Utility model is not limited to embodiment, every any letter made to above example according to technical spirit of the present utility model Single modification, equivalent variations and modification, each fall within the protection domain of technical solutions of the utility model.

Claims (5)

1. a kind of charger of GIS electrical equipment air chamber, including SF6Gas cylinder, air relief valve, aerating pipe, it is characterised in that:Also include First gas retracting device, four-way connection, pressure gauge, the first ball valve, the second ball valve, the 3rd ball valve and the 4th ball valve, SF6Gas cylinder Gas outlet pass sequentially through air relief valve, the first ball valve, aerating pipe, the second ball valve connect four-way connection first port, four-way The second port of joint connects GIS electrical equipment air chambers by the 3rd ball valve;3rd port of four-way connection is connected by the 4th ball valve First gas retracting device;Pressure gauge is arranged on the 4th port of four-way connection.
2. the charger of GIS electrical equipment air chamber according to claim 1, it is characterised in that:Also include some snap joints, Between first ball valve and the aerating pipe, between second ball valve and the aerating pipe, the 3rd ball valve with Snap joint is connected between GIS electrical equipment air chambers.
3. the charger of GIS electrical equipment air chamber according to claim 1, it is characterised in that:It is provided with the air relief valve Pressure gauge.
4. the charger of GIS electrical equipment air chamber according to claim 1, it is characterised in that:The first gas reclaim dress It is set to gas reclaiming bag.
5. the charger of GIS electrical equipment air chamber according to claim 1, it is characterised in that:The first gas reclaim dress Put and pass sequentially through first gas recovery tube, the 5th ball valve and snap joint connection the 4th ball valve.
CN201621098002.XU 2016-09-30 2016-09-30 A kind of charger of GIS electrical equipment air chamber Active CN206072746U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621098002.XU CN206072746U (en) 2016-09-30 2016-09-30 A kind of charger of GIS electrical equipment air chamber

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621098002.XU CN206072746U (en) 2016-09-30 2016-09-30 A kind of charger of GIS electrical equipment air chamber

Publications (1)

Publication Number Publication Date
CN206072746U true CN206072746U (en) 2017-04-05

Family

ID=58441429

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621098002.XU Active CN206072746U (en) 2016-09-30 2016-09-30 A kind of charger of GIS electrical equipment air chamber

Country Status (1)

Country Link
CN (1) CN206072746U (en)

Similar Documents

Publication Publication Date Title
CN106287200A (en) The aerating device of a kind of GIS electrical equipment air chamber and inflation method
CN103486440B (en) Connecting device, vacuum pumping method and inflation method are reclaimed in rapid vacuumizing and inflation
CN202793693U (en) Housing detection gas recovery device
CN206072746U (en) A kind of charger of GIS electrical equipment air chamber
CN204142451U (en) A kind of gas cylinder tightness test device
CN204510363U (en) A kind of gaseous prepressing water supplying equipment
CN202301229U (en) Inflating device of portable energy storage
CN105202358A (en) SF6 air inflation device of electrical equipment
CN204986038U (en) Inflatable cable channel sealing device that can repeatedly use repeatedly
CN205261237U (en) Safety guard suitable for chemical plant pipeline transports
CN210613277U (en) Gaseous recovery unit of tail gas of subcritical extraction system
CN210603769U (en) Ammonia leakage test device
CN103244819A (en) SF6 gas filling device
CN102563342A (en) Gas charging device
CN207439735U (en) Transformer oil taking apparatus
CN203835862U (en) Air cylinder piston rod locking device
CN202647014U (en) Multifunctional inflation conversion joint
CN202793927U (en) Bursting test machine
CN205687537U (en) A kind of air pressure gun air blowing oil pump
CN202083528U (en) High-voltage breaker high-voltage air seepage detection apparatus
CN202788934U (en) Underground coal mine downward hole drainage device
CN204938998U (en) Water-purifying machine
CN206221867U (en) Pneumatic Rescue Kits are combined device
CN205027524U (en) Open and close valve pressure measurement
CN203500769U (en) Scavenging port plugging device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant