CN206057094U - The slow test loading system of beam slab after the completion of a kind of erection for high-altitude - Google Patents

The slow test loading system of beam slab after the completion of a kind of erection for high-altitude Download PDF

Info

Publication number
CN206057094U
CN206057094U CN201621090238.9U CN201621090238U CN206057094U CN 206057094 U CN206057094 U CN 206057094U CN 201621090238 U CN201621090238 U CN 201621090238U CN 206057094 U CN206057094 U CN 206057094U
Authority
CN
China
Prior art keywords
loading system
beam slab
completion
floor stringer
altitude
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621090238.9U
Other languages
Chinese (zh)
Inventor
申雁鹏
韩之江
刘志华
韩锋
毛敏
郭文龙
吕立宁
陈栋栋
赵文溥
郭学兵
王磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Province Transport Science Research Institute
Shanxi Jiaoke Highway Survey and Design Institute
Original Assignee
Shanxi Province Transport Science Research Institute
Shanxi Jiaoke Highway Survey and Design Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Province Transport Science Research Institute, Shanxi Jiaoke Highway Survey and Design Institute filed Critical Shanxi Province Transport Science Research Institute
Priority to CN201621090238.9U priority Critical patent/CN206057094U/en
Application granted granted Critical
Publication of CN206057094U publication Critical patent/CN206057094U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

This utility model belongs to technical field of bridge engineering, it particularly relates to it is a kind of for high-altitude set up after the completion of beam slab slow test loading system.The loading system includes cross-brace, jack and floor stringer;Cross-brace has two, is not erected at the both sides of the lumps of wood of trial test beam slab span centre;Jack is stably located on the lumps of wood, which is provided with proving ring;Floor stringer is erected in two cross-braces, and its top both-side ends is each configured with suspension ring, and its underpart central authorities are provided with power distribution beam;Suspension ring are provided with the fixed track cable for passing perpendicularly through floor stringer, and the fixation track cable connects weight.High-altitude described in the utility model sets up beam slab slow test loading system and solves that traditional load mode is time-consuming, laborious, the unsafe problem of loading procedure compared with prior art, do not limited by high-altitude Site Detection condition simultaneously, drastically increased work efficiency.

Description

The slow test loading system of beam slab after the completion of a kind of erection for high-altitude
Technical field
This utility model belongs to technical field of bridge engineering, it particularly relates to a kind of erection for high-altitude completes the back rest The slow test loading system of plate.
Background technology
Due to the impact of the factors such as construction technology and duration, simple structure, easily Mid and minor spans armored concrete of constructing Or Prestressed Concrete Bridges are still occupied an leading position in highway in China bridge construction, version is based on many beam types of multispan. In process of construction, be the quality for determining single-beam construction, typically slow test will be carried out to prefabricated single-beam.Single-beam static(al) is tried Test is in single-beam specified location, the static displacement of detection single-spar construction, static(al) strain, crack, sedimentation by static load action Deng the pilot project of static parameter, then according to related specifications and the index of code, judge bridge structure bearing capacity and Service behaviour under load action.Recessive disease (the prestressed stretch-draw that cannot be obtained in often routinely being detected Power is not enough, modulus of elasticity of concrete is low etc.), it is the important means control effectively by structure in-situ precast quality.
Static loading is carried out to beam slab at prefabricated scene, generally weight (entire bundle is lifted by hoisting facilities such as straddle truck, cranes Reinforcing bar, steel strand wires, sandbag, small-sized cover plate etc.) implement loading.But it is to finding in the long term investigation of job site, ineffective due to supervising and guiding, The reasons such as sloppy management, beam slab high-altitude are set up after finishing, and are just found there is hidden danger of quality, must be carried out static loading to which.At this In the case of kind, static loading is implemented by hoisting facilities and lifting weight and cannot be realized, or realize that difficulty is larger, in loading procedure Middle beam body is easily toppled, and there is very big personal security hidden danger.
The content of the invention
To solve above-mentioned technical problem, this utility model provides a kind of static(al) examination of beam slab after the completion of setting up for high-altitude Test loading system.
The slow test loading system of beam slab, the loading after the completion of a kind of erection for high-altitude described in the utility model System includes cross-brace 2, jack 3 and floor stringer 5;Cross-brace 2 has two, is erected at 1 span centre of trial test beam slab respectively The lumps of wood 10 both sides;Jack 3 is stably located on the lumps of wood 10, which is provided with proving ring 4;Floor stringer 5 is erected at two laterally Support on 2, its top both-side ends is each configured with suspension ring 8, and its underpart central authorities are provided with power distribution beam 9;Suspension ring 8 are provided with vertically to be worn The fixed track cable 6 of floor stringer 5 is crossed, the fixation track cable 6 connects weight 7.
After the completion of a kind of erection for high-altitude described in the utility model, the slow test loading system of beam slab, described horizontal 2 are supported in vertical direction flexible, which is higher by 4 height 2~3cm of sum of jack 3 and proving ring, for supporting floor stringer 5.
After the completion of a kind of erection for high-altitude described in the utility model, the slow test loading system of beam slab, described very heavy Top 3 adopts hydraulic type, rated load weight be more than 1.2 times of maximum top lift.Maximum top lift according to the across footpath of single-beam, cut The multifactor determination such as face form and loading efficiency, should be demarcated using before.The proving ring 4 should be true according to maximum top lift It is fixed, 10% to the maximum range that scope is maximum range is effectively measured, should be demarcated using before.
The slow test loading system of beam slab, the auxiliary after the completion of a kind of erection for high-altitude described in the utility model Beam 5 is welded by Q345 shaped steel, and which adopts welding by both sides with suspension ring 8, and weld length is 10 times of bar diameters.
The slow test loading system of beam slab, the load-bearing after the completion of a kind of erection for high-altitude described in the utility model Rope 6 is made up of steel wire, to undertake balance weight.
The slow test loading system of beam slab, the suspension ring after the completion of a kind of erection for high-altitude described in the utility model 8 byFinish rolling deformed bar is made, for lifting by crane floor stringer 5 and fixed track cable 6.
The slow test loading system of beam slab, the power point after the completion of a kind of erection for high-altitude described in the utility model It is made up of rectangular steel plates with beam 9, rectangular steel plates are made using Q345 steel plates, steel plate thickness is more than or equal to 5.0mm, for jacking Power is entered to evenly distribute, and prevents 5 local compression of floor stringer from causing bending.
During operation, jack is stable on the lumps of wood of beam slab span centre loading position, while laying proving ring, supporting is horizontal Support and adjust its height and be slightly higher than proving ring about 2~3cm;Set up floor stringer, it is desirable to distribution beam center and proving ring Center overlaps, it is to avoid produce wobbler action power;Track cable is passed through from suspension ring, lower end increases counterweight according to design load, Now slow test loading system combination is finished.
High-altitude described in the utility model sets up beam slab slow test loading system and solves tradition compared with prior art Load mode is time-consuming, laborious, the unsafe problem of loading procedure, while do not limited by high-altitude Site Detection condition, greatly Improve work efficiency.
Description of the drawings
Fig. 1:This utility model schematic diagram;Fig. 2:Floor stringer top view;Fig. 3:Floor stringer cross-sectional view;Fig. 4:Suspension ring full-page proof Figure;Trial test beam slab -1, cross-brace -2, jack -3, proving ring -4, floor stringer -5, track cable -6, counterweight -7, suspension ring -8, Distribution beam -9, the lumps of wood -10.
Specific embodiment
With reference to static(al) examination of the specific embodiment to beam slab after the completion of the erection for high-altitude described in the utility model Test loading system to be described further, but protection domain of the present utility model is not limited to this.
Embodiment 1
The slow test loading system of beam slab after the completion of a kind of erection for high-altitude, the loading system include cross-brace 2nd, jack 3 and floor stringer 5;Cross-brace 2 has two, is erected at the both sides of the lumps of wood 10 of 1 span centre of trial test beam slab respectively;Thousand Jin top 3 is stably located on the lumps of wood 10, which is provided with proving ring 4;Floor stringer 5 is erected in two cross-braces 2, its top both sides End is each configured with suspension ring 8, and its underpart central authorities are provided with power distribution beam 9;Suspension ring 8 are provided with and pass perpendicularly through the fixation of floor stringer 5 and hold Weight rope 6, the fixation track cable 6 connect weight 7.In vertical direction flexible, which is higher by jack 3 and surveys the cross-brace 2 4 height sum 2cm of power ring, for supporting floor stringer 5.The jack 3 adopts hydraulic type, and rated load weight need to be more than maximum 1.2 times of top lift.Maximum top lift according to multifactor determinations such as the across footpath of single-beam, section form and loading efficiencies, using front Should be demarcated.The proving ring 4 should be determined according to maximum top lift, effectively measure 10% to the maximum that scope is maximum range Range, should be demarcated using before.The floor stringer 5 is welded by Q345 shaped steel, and which adopts welding by both sides with suspension ring 8, welding Length is 10 times of bar diameters.The track cable 6 is made up of steel wire, to undertake balance weight.The suspension ring 8 byFinish rolling Spiral is made, for lifting by crane floor stringer 5 and fixed track cable 6.The power distribution beam 9 is made up of rectangular steel plates, rectangle steel Plate is made using Q345 steel plates, steel plate thickness 5.0mm, for entering to evenly distribute to top lift, prevents 5 local compression of floor stringer from leading Cause bending.
Embodiment 2
The slow test loading system of beam slab after the completion of a kind of erection for high-altitude, the loading system include cross-brace 2nd, jack 3 and floor stringer 5;Cross-brace 2 has two, is erected at the both sides of the lumps of wood 10 of 1 span centre of trial test beam slab respectively;Thousand Jin top 3 is stably located on the lumps of wood 10, which is provided with proving ring 4;Floor stringer 5 is erected in two cross-braces 2, its top both sides End is each configured with suspension ring 8, and its underpart central authorities are provided with power distribution beam 9;Suspension ring 8 are provided with and pass perpendicularly through the fixation of floor stringer 5 and hold Weight rope 6, the fixation track cable 6 connect weight 7.In vertical direction flexible, which is higher by jack 3 and surveys the cross-brace 2 4 height sum 3cm of power ring, for supporting floor stringer 5.The jack 3 adopts hydraulic type, and rated load weight need to be more than maximum 1.2 times of top lift.Maximum top lift according to multifactor determinations such as the across footpath of single-beam, section form and loading efficiencies, using front Should be demarcated.The proving ring 4 should be determined according to maximum top lift, effectively measure 10% to the maximum that scope is maximum range Range, should be demarcated using before.The floor stringer 5 is welded by Q345 shaped steel, and which adopts welding by both sides with suspension ring 8, welding Length is 10 times of bar diameters.The track cable 6 is made up of steel wire, to undertake balance weight.The suspension ring 8 byFinish rolling Spiral is made, for lifting by crane floor stringer 5 and fixed track cable 6.The power distribution beam 9 is made up of rectangular steel plates, rectangle steel Plate is made using Q345 steel plates, steel plate thickness 5.5mm, for entering to evenly distribute to top lift, prevents 5 local compression of floor stringer from leading Cause bending.
During operation, jack is stable on the lumps of wood of beam slab span centre loading position, while laying proving ring, supporting is horizontal Support and adjust its height and be slightly higher than proving ring about 2~3cm;Set up floor stringer, it is desirable to distribution beam center and proving ring Center overlaps, it is to avoid produce wobbler action power;Track cable is passed through from suspension ring, lower end increases counterweight according to design load, Now slow test loading system combination is finished.
High-altitude described in the utility model sets up beam slab slow test loading system and solves tradition compared with prior art Load mode is time-consuming, laborious, the unsafe problem of loading procedure, while do not limited by high-altitude Site Detection condition, greatly Improve work efficiency.

Claims (7)

1. it is a kind of for high-altitude set up after the completion of beam slab slow test loading system, it is characterised in that the loading system bag Include cross-brace (2), jack (3) and floor stringer (5);Cross-brace (2) has two, is erected at trial test beam slab (1) respectively The both sides of the lumps of wood (10) of span centre;Jack (3) is stably located on the lumps of wood (10), which is provided with proving ring (4);Floor stringer (5) It is erected on two cross-braces (2), its top both-side ends is each configured with suspension ring (8), its underpart central authorities are provided with power distribution Beam (9);Suspension ring (8) are provided with the fixed track cable (6) for passing perpendicularly through floor stringer (5), the fixation track cable (6) connection weight (7).
2. it is according to claim 1 it is a kind of for high-altitude set up after the completion of beam slab slow test loading system, its feature Be, the cross-brace (2) in vertical direction flexible, its be higher by jack (3) and proving ring (4) height sum 2~ 3cm, for supporting floor stringer (5).
3. it is according to claim 1 it is a kind of for high-altitude set up after the completion of beam slab slow test loading system, its feature It is that the jack (3) adopts hydraulic type, rated load weight be more than 1.2 times of maximum top lift.
4. it is according to claim 1 it is a kind of for high-altitude set up after the completion of beam slab slow test loading system, its feature It is that the floor stringer (5) is welded by Q345 shaped steel, which adopts welding by both sides with suspension ring (8), weld length is 10 times of reinforcing bars Diameter.
5. it is according to claim 1 it is a kind of for high-altitude set up after the completion of beam slab slow test loading system, its feature It is that the track cable (6) is made up of steel wire, to undertake balance weight.
6. it is according to claim 1 it is a kind of for high-altitude set up after the completion of beam slab slow test loading system, its feature Be, the suspension ring (8) byFinish rolling deformed bar is made, for lifting by crane floor stringer (5) and fixed track cable (6).
7. it is according to claim 1 it is a kind of for high-altitude set up after the completion of beam slab slow test loading system, its feature It is that the power distribution beam (9) is made up of rectangular steel plates, and rectangular steel plates are made using Q345 steel plates, and steel plate thickness is more than or equal to 5.0mm, for entering to evenly distribute to top lift, prevents floor stringer (5) local compression from causing bending.
CN201621090238.9U 2016-09-29 2016-09-29 The slow test loading system of beam slab after the completion of a kind of erection for high-altitude Expired - Fee Related CN206057094U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621090238.9U CN206057094U (en) 2016-09-29 2016-09-29 The slow test loading system of beam slab after the completion of a kind of erection for high-altitude

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621090238.9U CN206057094U (en) 2016-09-29 2016-09-29 The slow test loading system of beam slab after the completion of a kind of erection for high-altitude

Publications (1)

Publication Number Publication Date
CN206057094U true CN206057094U (en) 2017-03-29

Family

ID=58366291

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621090238.9U Expired - Fee Related CN206057094U (en) 2016-09-29 2016-09-29 The slow test loading system of beam slab after the completion of a kind of erection for high-altitude

Country Status (1)

Country Link
CN (1) CN206057094U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110230263A (en) * 2019-06-03 2019-09-13 中铁大桥局集团有限公司 A kind of device of auxiliary plug pin shaft
CN112556951A (en) * 2020-11-27 2021-03-26 苏交科集团检测认证有限公司 Test device and test method for rapid load test of prefabricated T-shaped beam

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110230263A (en) * 2019-06-03 2019-09-13 中铁大桥局集团有限公司 A kind of device of auxiliary plug pin shaft
CN112556951A (en) * 2020-11-27 2021-03-26 苏交科集团检测认证有限公司 Test device and test method for rapid load test of prefabricated T-shaped beam

Similar Documents

Publication Publication Date Title
CN102162774B (en) Steel-structure distribution-girder-type double-track whole opening box girder static load test device and construction method thereof
CN103291076A (en) Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame
CN106836498A (en) A kind of super-span Stadium roof system steel truss lifting construction engineering method
CN206328678U (en) Steel box-girder chooses arm and steel guard rail installs dual-purpose type Mobile operating platform
CN102797226A (en) Integral erection construction method of 60m steel box girder
CN201882763U (en) Special carrying pole type beam of double-machine lifting crane
CN111717798A (en) Multi-machine cooperative hoisting system and process for box girder of over-built railway cutting highway bridge
CN103061360A (en) Stress application system for large-tonnage static load tests
CN206057094U (en) The slow test loading system of beam slab after the completion of a kind of erection for high-altitude
CN104963295A (en) Support frame for non-ground internal-force balanced cast-in-place beam and construction method thereof
CN103132702A (en) Longspan pipe truss pulling bar lifting and overhead rotating emplacing construction method
CN204126297U (en) A kind of temporary support of steel truss roof
CN207293909U (en) A kind of precast beam reinforced bar skeleton hanging apparatus
CN104278628B (en) A kind of light hanging basket being applicable to bridge machinery and maintenance activity
CN102877657A (en) Large-span H-shaped plane composite structure beam string upper-air cable replacement construction method
CN201943006U (en) Main tower zone movable bracket for assisting non-variable amplitude girder erecting crane to erect steel box girders
CN214828306U (en) A auxiliary device for hoisting box girder steel reinforcement framework
CN201144134Y (en) Double herringbone hoisting derrick mast
CN103754791A (en) Method for lifting water-tower 1000m<3> water tank by utilizing prestressed strands
CN204040442U (en) A kind of integral lifting elevator hoistways operating platform
CN210505201U (en) Equipment for hoisting reinforcing steel bars in batches
CN204401454U (en) A kind of light hanging basket being applicable to bridge machinery and maintenance activity
CN201952736U (en) Auxiliary pier movable bracket for assisting invariable-amplitude beam erecting crane in erecting steel box girder
CN111877186A (en) Balanced cast-in-place construction method for beam section bracket of side pier of continuous beam
CN202073303U (en) Overhanging type main beam of unloading platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170329

Termination date: 20180929

CF01 Termination of patent right due to non-payment of annual fee