CN206052687U CN201621087709.0U CN201621087709U CN206052687U CN 206052687 U CN206052687 U CN 206052687U CN 201621087709 U CN201621087709 U CN 201621087709U CN 206052687 U CN206052687 U CN 206052687U
Authority
CN
China
Prior art keywords
pile body
pile
main shaft
top board
novel building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621087709.0U
Other languages
Chinese (zh)
Inventor
郭光军
李岩峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shijiazhuang Jiantong Construction Engineering Co Ltd
Original Assignee
Shijiazhuang Jiantong Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shijiazhuang Jiantong Construction Engineering Co Ltd filed Critical Shijiazhuang Jiantong Construction Engineering Co Ltd
Priority to CN201621087709.0U priority Critical patent/CN206052687U/en
Application granted granted Critical
Publication of CN206052687U publication Critical patent/CN206052687U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a kind of novel building stake, which includes pile body and pile top, pile body is hollow structure, the hollow intracavity of pile body is provided with main shaft, the lower end of main shaft is connected with addendum cone, addendum cone, main shaft is coaxially disposed with pile body, the hollow intracavity of pile body is provided with least two gripper shoes, circumferentially uniform intervals are provided with least two top boards for the lower end of pile body, the pilot hole outwards ejected for top board is provided with stake body sidewall, one end positioned at hollow intracavity of top board acts on the taper-face contact with addendum cone by being enclosed within the elastic force of spring on top board, upper end of the upper end of main shaft higher than pile body, the upper end of pile body is provided with pile cover, the internal diameter and external diameter of pile cover is identical with the internal diameter of pile body and external diameter, pile cover is covered in the upper end of pile body, and linked together with pile body by iron hoop in junction.Novel building stake of the present utility model improves the stability of strutting system of pile body, can effectively prevent pile body from moving further downward, have preferable support performance to the weight on pile body.

Description

A kind of novel building stake
Technical field
This utility model is related to building implement technical field, more particularly to a kind of novel building stake.
Background technology
Building stake is a kind of building appliance, is mainly used in squeezing into the basis dress that its upper building support is carried out in soil Put, therefore be widely used in building engineering field;The stake of existing building includes pile body and pile top, and pile top is arranged on the bottom of pile body End;During use, by hitting pile body, using pile top, in soil, operation is operated downwards.But find in use, stake The weight of body upper end can apply a lasting static pressure to building stake itself, can find that some building stakes can quilt after the time is longer Continue to push mobile certain depth, in turn result in the weight to its top and do not reach setting bearing height, or even can make to cause to prop up Support unstable, the situation that weight is glanced off.
The content of the invention
For this purpose, the technical problems to be solved in the utility model is existing building stake can move down in use for some time The drawbacks of, and then provide that a kind of support strength is good, supporting & stablizing, and effectively can prevent from building the novel building stake that stake is moved down.
For achieving the above object, this utility model is employed the following technical solutions:
A kind of novel building stake, which includes pile body and pile top, and the pile body is hollow structure, the hollow intracavity of the pile body Main shaft is provided with, the lower end of the main shaft is connected with the addendum cone of taper type, and the addendum cone, the main shaft are coaxially set with the pile body Put, the hollow intracavity of the pile body is provided with least two for the gripper shoe that positions to the main shaft support, the pile body Circumferentially uniform intervals are provided with least two top boards for lower end, are provided with what is outwards ejected for the top board on the stake body sidewall Pilot hole, one end positioned at the hollow intracavity of the top board by be enclosed within the elastic force of spring on the top board act on it is described The taper-face contact of addendum cone, the upper end of the main shaft are higher than the upper end of the pile body, and the upper end of the pile body is provided with pile cover, described The internal diameter and external diameter of pile cover is identical with the internal diameter and external diameter of the pile body, and the pile cover is covered in the upper end of the pile body, and Junction is linked together with the pile body by iron hoop.
Preferably, the bottom of the middle cavity of the pile body is provided with the guide pad for guiding the top board outwards to make, The guide pad is fixedly connected on the medial wall of the pile body.
Preferably, the top board is arranged obliquely.
Preferably, the top board and the angle of the pile body axis are 50-65 degree.
Preferably, the top board is circumferentially arranged three or four.
Preferably, the main shaft upper end is provided with end cap.
The beneficial effects of the utility model:
Novel building pilework of the present utility model is simple, easy to operate, not only increases the stability of strutting system of pile body, together When also can effectively prevent pile body from moving further downward, therefore still be able to after a long time use ensure that pile body is maintained initially Depth, there is preferable support performance to the weight on pile body.
Description of the drawings
In order that content of the present utility model is more likely to be clearly understood, below in conjunction with the accompanying drawings, this utility model is made Further details of explanation, wherein:
Fig. 1 is the structural representation of novel building stake of the present utility model(The figure is half sectional view, in order to show each portion Part, eliminates cutting line);
Fig. 2 is the structural representation when top board of novel building stake of the present utility model is ejected;
Fig. 3 is the structural representation of novel building stake lower end of the present utility model.
In figure, reference is expressed as:
1- pile bodies;2- pile tops;Cavity in 3-;4- main shafts;5- addendum cones;6- gripper shoes;7- top boards;8- pilot holes;9- springs; 10- pile covers;11- iron hoops;12- guide pads;13- ends cap.
Specific embodiment
Referring to Fig. 1-3, a kind of novel building stake, which includes pile body 1 and pile top 2, and the pile body 1 is hollow structure, described It is provided with main shaft 4 in the middle cavity 3 of pile body 1, the lower end of the main shaft 4 is connected with the addendum cone 5 of taper type, it is the addendum cone 5, described Main shaft 4 is coaxially disposed with the pile body 1, is provided with three for supporting fixed to the main shaft 4 in the middle cavity 3 of the pile body 1 The gripper shoe 6 of position, three gripper shoes arranged for interval about 6, circumferentially uniform intervals are provided with four for the lower end of the pile body 1 Individual top board 7, is provided with the pilot hole 8 for the outside ejection of the top board 7 on 1 side wall of the pile body, the top board 7 positioned at described One end in middle cavity 3 is by being enclosed within the elastic force effect of spring 9 on the top board 7 and the taper-face contact of the addendum cone 5, the master Upper end of the upper end of axle 4 higher than the pile body 1, the upper end of the pile body 1 are provided with pile cover 10, the internal diameter of the pile cover 10 and outer Footpath is identical with the internal diameter and external diameter of the pile body 1, and the pile cover 10 is covered in the upper end of the pile body 1, and is passed through in junction Iron hoop 11 is linked together with the pile body 1, and the iron hoop 11 is detachable connection.During installation, first pile cover is installed, so Backward lower impact pile cover drives pile body to move downward in insertion soil, after pile body drops to desired depth, removes pile cover, then The upper end of impact main shaft, moves downward main shaft, and main shaft drives top board to stretch out by the addendum cone of its bottom during moving downward Outside pile body, referring to Fig. 2, four top boards are ejected to four direction, on the one hand improve the stability of strutting system of pile body, on the other hand then Can effectively prevent pile body from moving further downward, therefore still be able to after a long time use ensure that pile body maintains initial depth Degree, has preferable support performance to the weight on pile body.
In the present embodiment, the bottom of the middle cavity 3 of the pile body 1 is provided with for guiding what the top board 7 was outwards made Guide pad 12, the guide pad 12 are fixedly connected on the medial wall of the pile body 1.Arrange the guide pad 12 to be conducive to Push rod is outwards ejected according to predetermined direction, and then bears excessive power at the pilot hole of reduction pile body lower end, prevents from damaging pile body Side wall.
In order to improve supporting & stablizing type, prevent pile body from surprisingly declining, and it is easy to the smooth ejection of top board 7, the top board 7 is oblique Down-set, the top board 7 is 50-65 degree with the angle of 1 axis of the pile body.
Main shaft body is damaged when applying pressure in order to avoid the upper end to main shaft, the upper end of the main shaft 4 is provided with end Cap 13.
Above-mentioned specific embodiment is simply explained in detail to the technical solution of the utility model, and this utility model is not Only be limited only to above-described embodiment, it will be understood by those skilled in the art that it is every according to above-mentioned principle and spirit in this practicality Improvement, replacement on novel foundation, all should be within protection domain of the present utility model.

Claims (6)

1. a kind of novel building stake, it is characterised in that:Including pile body and pile top, the pile body is hollow structure, the pile body Hollow intracavity is provided with main shaft, and the lower end of the main shaft is connected with the addendum cone of taper type, the addendum cone, the main shaft and the stake Body is coaxially disposed, and the hollow intracavity of the pile body is provided with least two for the gripper shoe that positions to the main shaft support, institute Circumferentially uniform intervals are provided with least two top boards to state the lower end of pile body, be provided with the stake body sidewall for the top board to The pilot hole of outer ejection, one end positioned at the hollow intracavity of the top board are made by being enclosed within the elastic force of spring on the top board With the taper-face contact with the addendum cone, the upper end of the main shaft is higher than the upper end of the pile body, and the upper end of the pile body is provided with Pile cover, the internal diameter and external diameter of the pile cover are identical with the internal diameter and external diameter of the pile body, and the pile cover is covered in the pile body Upper end, and linked together with the pile body by iron hoop in junction.
2. novel building stake according to claim 1, it is characterised in that:The bottom of the middle cavity of the pile body is provided with use In the guide pad for guiding the top board outwards to make, the guide pad is fixedly connected on the medial wall of the pile body.
3. novel building stake according to claim 1 and 2, it is characterised in that:The top board is arranged obliquely.
4. novel building stake according to claim 3, it is characterised in that:The top board with the angle of the pile body axis is 50-65 degree.
5. novel building stake according to claim 1, it is characterised in that:The top board is circumferentially arranged three or four It is individual.
6. novel building stake according to claim 1, it is characterised in that:The main shaft upper end is provided with end cap.
CN201621087709.0U 2016-09-28 2016-09-28 A kind of novel building stake Expired - Fee Related CN206052687U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621087709.0U CN206052687U (en) 2016-09-28 2016-09-28 A kind of novel building stake

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621087709.0U CN206052687U (en) 2016-09-28 2016-09-28 A kind of novel building stake

Publications (1)

Publication Number Publication Date
CN206052687U true CN206052687U (en) 2017-03-29

Family

ID=58366066

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621087709.0U Expired - Fee Related CN206052687U (en) 2016-09-28 2016-09-28 A kind of novel building stake

Country Status (1)

Country Link
CN (1) CN206052687U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107190734A (en) * 2017-06-22 2017-09-22 成都赋阳技术开发有限公司 The roadbed supporting pile for repairing construction is built for road and bridge
CN107237320A (en) * 2017-08-15 2017-10-10 张家港市兴鸿达基础有限公司 The pile foundation that a kind of antidetonation is strengthened
CN107386280A (en) * 2017-08-15 2017-11-24 张家港市兴鸿达基础有限公司 A kind of pile foundation of the spacing reinforcement in bottom
CN107476298A (en) * 2017-09-22 2017-12-15 国家电网公司 A kind of overhead transmission line concrete precast pipe pile implantation pile sinking platform and method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107190734A (en) * 2017-06-22 2017-09-22 成都赋阳技术开发有限公司 The roadbed supporting pile for repairing construction is built for road and bridge
CN107237320A (en) * 2017-08-15 2017-10-10 张家港市兴鸿达基础有限公司 The pile foundation that a kind of antidetonation is strengthened
CN107386280A (en) * 2017-08-15 2017-11-24 张家港市兴鸿达基础有限公司 A kind of pile foundation of the spacing reinforcement in bottom
CN107476298A (en) * 2017-09-22 2017-12-15 国家电网公司 A kind of overhead transmission line concrete precast pipe pile implantation pile sinking platform and method

Similar Documents

Publication Publication Date Title
CN206052687U (en) A kind of novel building stake
CN205329680U (en) Antitorque pile foundation structure of resistance to plucking
CN204609737U (en) A kind of anti-skidding by ladder
CN203121974U (en) Novel sock support
CN102943615B (en) Horizontal-buckling support insulating ladder
CN206728566U (en) A kind of seedling of alfalfa transplantation device
CN205709597U (en) A kind of weight boom hoisting
CN207934023U (en) A kind of adjustable building stake
CN203096444U (en) Bottom structure of washing machine
CN204125958U (en) Foundation pile syndeton
CN206974055U (en) A kind of efficiently rose dryer
CN207472647U (en) A kind of detection of agricultural products oscillator
CN205617821U (en) Building wall strutting arrangement
CN204069928U (en) A kind of seedling bed that spacingly can prevent turning on one's side
CN203852272U (en) Soap holder
CN204090643U (en) Agricultural planting pillar
CN204185866U (en) The board-like connecting structure of passive protection net column column cap
CN208668489U (en) One kind entangling stake transmission rod
CN202467129U (en) Construction operation table
CN213548762U (en) Tree supporting device for environmental ecological protection
CN211336876U (en) Shoe storage device convenient to adjust
CN202500032U (en) Supporting device of automatic clothes hanger
CN207656664U (en) A kind of traction battery transport device
CN205928579U (en) Drive shaft rack
CN204590057U (en) A kind of heat-insulation and heat-preservation building lot structure