CN206048415U - A kind of two-way hot glue press - Google Patents
A kind of two-way hot glue press Download PDFInfo
- Publication number
- CN206048415U CN206048415U CN201620987217.0U CN201620987217U CN206048415U CN 206048415 U CN206048415 U CN 206048415U CN 201620987217 U CN201620987217 U CN 201620987217U CN 206048415 U CN206048415 U CN 206048415U
- Authority
- CN
- China
- Prior art keywords
- briquetting
- pallet
- hot glue
- lower section
- glue press
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model discloses a kind of two-way hot glue press, including water tank, heater, briquetting and control panel, peg is provided with below the gripper shoe, water inlet is connected with the left of the briquetting, outlet is installed on the right side of the briquetting, positioning fixture is provided with the left of the control panel, below the positioning fixture, suction nozzle is provided with, pallet is connected with below the suction nozzle, lower promotion machine below the pallet, is fixed with.The two-way hot glue press is provided with stop screw, the problems such as can preventing briquetting from causing plank to rupture because of excessive compression, suction nozzle is provided with pallet, plank to be extruded can firmly be adsorbed on pallet, the plank up and down caused because of slight displacement is avoided to misplace, gripper shoe is fixedly connected with frame, the gravity for bearing of depression bar can be mitigated when briquetting is moved up and down, extend the service life of machinery, briquetting inner hollow, hot water has not only saved water resource by inner space circulation, and heats also become apparent from.
Description
Technical field
This utility model is related to mechanical equipment technical field, specially a kind of two-way hot glue press.
Background technology
With the continuous improvement of social need, the requirement that people are processed for timber also more and more higher, but existing wood
The such as two-way hot glue press of material process equipment can not meet people's needs, and existing equipment is not provided with stop screw, it is impossible to have
The problems such as effect prevents briquetting from causing plank to rupture because of excessive compression, and be not provided with inhaling on the pallet of existing equipment
Plank to be extruded firmly can not be adsorbed on pallet by mouth, cause the plank up and down caused because of slight displacement to misplace, with
And gripper shoe can not mitigate the gravity for bearing of depression bar when briquetting is moved up and down without being fixedly connected with frame, reduce
The service life of machinery, is not provided with hollow inside the briquetting in some machinery, hot water can not pass through inner space recycle stream
It is logical, water resource is not only wasted, also not substantially, existing equipment has been not provided with promotion machine to heats up and down, can not be
The upper and lower uniform stressed of plank is made during glue laminated, hot pressing is of poor quality.
Utility model content
The purpose of this utility model is to provide a kind of two-way hot glue press, with subtracting for solving to propose in above-mentioned background technology
The service life of machinery is lacked, has wasted water resource, heats are not obvious and can not make on plank during glue laminated yet
Lower uniform stressed, the problems such as hot pressing is of poor quality.
For achieving the above object, this utility model provides following technical scheme:A kind of two-way hot glue press, including water tank,
Heater, briquetting and control panel, are connected with the left of the water tank on the right side of flow pipe, and water tank and are provided with suction hose, described to add
Organic frame is installed below hot device, promotion machine is connected with below the frame, depression bar, the pressure is installed below the promotion machine
It is fixed with below bar above gripper shoe, and gripper shoe and stop screw is installed, below the gripper shoe, is provided with peg, the pressure
Water inlet is connected with the left of block, outlet is installed on the right side of the briquetting, on the left of the control panel, be provided with positioning fixture, institute
State, below the suction nozzle, be connected with pallet, below the pallet, be fixed with lower promotion machine.
Preferably, the gripper shoe is fixedly connected with frame, and the through-hole diameter arranged at stop screw is than spacing spiral shell
The little 5cm of nail diameter.
Preferably, inside the briquetting it is hollow-core construction.
Preferably, the minimum spacing between the positioning fixture is identical with briquetting length.
Preferably, the suction nozzle upper end is in same level with pallet.
Compared with prior art, the beneficial effects of the utility model are:The two-way hot glue press is provided with stop screw, can prevent
The problems such as only briquetting causes plank to rupture because of excessive compression, is provided with suction nozzle on pallet, can will be plank to be extruded firm
Absorption is on pallet, it is to avoid the dislocation of plank up and down caused because of slight displacement, gripper shoe are fixedly connected with frame, can be in pressure
Mitigate the gravity for bearing of depression bar when block is moved up and down, extend the service life of machinery, briquetting inner hollow, hot water are led to
Inner space circulation is crossed, water resource has not only been saved, heats also become apparent from, be provided with promotion machine up and down, can
The upper and lower uniform stressed of plank, hot pressing better quality are made during glue laminated.
Description of the drawings
Fig. 1 is this utility model structural representation.
In figure:1st, water tank, 2, flow pipe, 3, heater, 4, frame, 5, upper promotion machine, 6, depression bar, 7, gripper shoe, 8, enter
The mouth of a river, 9, briquetting, 10, peg, 11, suction hose, 12, stop screw, 13, control panel, 14, outlet, 15, positioning fixture,
16th, suction nozzle, 17, pallet, 18, lower promotion machine.
Specific embodiment
Below in conjunction with the accompanying drawing in this utility model embodiment, the technical scheme in this utility model embodiment is carried out
Clearly and completely describe, it is clear that described embodiment is only this utility model a part of embodiment, rather than whole
Embodiment.Based on the embodiment in this utility model, those of ordinary skill in the art are not under the premise of creative work is made
The every other embodiment for being obtained, belongs to the scope of this utility model protection.
Fig. 1 is referred to, this utility model provides a kind of technical scheme:A kind of two-way hot glue press, including water tank 1, heating
Device 3, briquetting 9 and control panel 13, are connected with the left of water tank 1 on the right side of flow pipe 2, and water tank 1 and are provided with suction hose 11, heater
Organic frame 4 is installed below 3, promotion machine 5 is connected with below frame 4, depression bar 6 is installed below promotion machine 5, it is solid below depression bar 6
Surely there is gripper shoe 7, gripper shoe 7 is fixedly connected with frame 4, and the through-hole diameter arranged at stop screw 12 is more straight than stop screw
The little 5cm in footpath, and stop screw 12 is installed above gripper shoe 7, peg 10 is provided with below gripper shoe 7, is connected with the left of briquetting 9
Water inlet 8, is hollow-core construction inside briquetting 9, is provided with outlet 14, positioning is provided with the left of control panel 13 on the right side of briquetting 9
Fixture 15, the minimum spacing between positioning fixture 15 are identical with 9 length of briquetting, and suction nozzle 16 is provided with below positioning fixture 15, inhale
Pallet 17 is connected with below mouth 16,16 upper end of suction nozzle is in same level with pallet 17, lower promotion machine is fixed with below pallet 17
18。
Operation principle:When using the two-way hot glue press, water tank 1 is filled into water first, then by control panel 13
Heater 3, flow pipe 2 is connected with water inlet 8, and suction hose 11 is connected with outlet 14, and then hot water is along flow pipe 2
Flow into briquetting 9 and then finally enter water tank 1 into suction hose 11 from outlet 14 by water inlet 8 and reheat, compressed wood will be treated
Plate is placed on pallet 17, arranges 15 position of positioning fixture, and suction nozzle 16 adsorbs plank on pallet 17, operational control panel
13, upper promotion machine 5 and lower promotion machine 18 operate, and promote briquetting 9 to move down and move on pallet 17 closure respectively and start glue laminated work, pressure
Hot water in block 9 is transferred heat in middle plank, after glue laminated terminates by 9 shell of briquetting, upper promotion machine 5 and lower promotion machine
18 reversions, take out plank, here it is the operation principle of the two-way hot glue press.
Although being described in detail to this utility model with reference to the foregoing embodiments, for those skilled in the art comes
Say, which still can be modified to the technical scheme described in foregoing embodiments, or which part technical characteristic is entered
Row equivalent, all within spirit of the present utility model and principle, any modification, equivalent substitution and improvements made etc. all should
It is included within protection domain of the present utility model.
Claims (5)
1. a kind of two-way hot glue press, including water tank(1), heater(3), briquetting(9)And control panel(13), its feature exists
In:The water tank(1)Left side is connected with flow pipe(2), and water tank(1)Right side is provided with suction hose(11), the heater(3)
Lower section is installed by organic frame(4), the frame(4)Lower section is connected with promotion machine(5), the promotion machine(5)Lower section is provided with pressure
Bar(6), the depression bar(6)Lower section is fixed with gripper shoe(7), and gripper shoe(7)Top is provided with stop screw(12), described
Fagging(7)Lower section is provided with peg(10), the briquetting(9)Left side is connected with water inlet(8), the briquetting(9)Install on right side
There is outlet(14), the control panel(13)Left side is provided with positioning fixture(15), the positioning fixture(15)Lower section is arranged
There is suction nozzle(16), the suction nozzle(16)Lower section is connected with pallet(17), the pallet(17)Lower section is fixed with lower promotion machine(18).
2. a kind of two-way hot glue press according to claim 1, it is characterised in that:The gripper shoe(7)With frame(4)Gu
It is fixed to connect, and in stop screw(12)The through-hole diameter 5cm less than stop screw diameter that place is arranged.
3. a kind of two-way hot glue press according to claim 1, it is characterised in that:The briquetting(9)Internal is hollow knot
Structure.
4. a kind of two-way hot glue press according to claim 1, it is characterised in that:The positioning fixture(15)Between most
Small Distance and briquetting(9)Length is identical.
5. a kind of two-way hot glue press according to claim 1, it is characterised in that:The suction nozzle(16)Upper end and pallet
(17)In same level.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620987217.0U CN206048415U (en) | 2016-08-30 | 2016-08-30 | A kind of two-way hot glue press |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620987217.0U CN206048415U (en) | 2016-08-30 | 2016-08-30 | A kind of two-way hot glue press |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206048415U true CN206048415U (en) | 2017-03-29 |
Family
ID=58378322
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620987217.0U Expired - Fee Related CN206048415U (en) | 2016-08-30 | 2016-08-30 | A kind of two-way hot glue press |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206048415U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110900748A (en) * | 2019-11-30 | 2020-03-24 | 怀化市祺鑫木业股份有限公司 | Hot-pressing gluing device capable of effectively improving gluing quality of plates |
CN112829359A (en) * | 2019-11-22 | 2021-05-25 | 赵俊儒 | Plate press |
CN113305969A (en) * | 2021-07-15 | 2021-08-27 | 安徽科林新材料科技有限公司 | Controllable hot pressing machine for processing shaving board |
CN114962402A (en) * | 2022-04-17 | 2022-08-30 | 河北汉光重工有限责任公司 | Eddy current induction composite device for aviation tray production |
-
2016
- 2016-08-30 CN CN201620987217.0U patent/CN206048415U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112829359A (en) * | 2019-11-22 | 2021-05-25 | 赵俊儒 | Plate press |
CN110900748A (en) * | 2019-11-30 | 2020-03-24 | 怀化市祺鑫木业股份有限公司 | Hot-pressing gluing device capable of effectively improving gluing quality of plates |
CN113305969A (en) * | 2021-07-15 | 2021-08-27 | 安徽科林新材料科技有限公司 | Controllable hot pressing machine for processing shaving board |
CN114962402A (en) * | 2022-04-17 | 2022-08-30 | 河北汉光重工有限责任公司 | Eddy current induction composite device for aviation tray production |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206048415U (en) | A kind of two-way hot glue press | |
CN206937527U (en) | A kind of energy-saving type plywood hot-pressing machine | |
CN203821612U (en) | Outer wall outer heat-insulation structure provided with reinforcedglass wool board | |
CN107096502A (en) | A kind of active carbon regenerating unit being moved easily | |
CN207974477U (en) | A kind of portable decoration construction ceramic tile immersion device | |
CN204604557U (en) | A kind of steam circulation of still kettle | |
CN103203786A (en) | Poplar modifying process | |
CN204157786U (en) | Leather shoes footwear bag cementing line | |
CN205616759U (en) | Can handle sunshine room of mud | |
CN204007018U (en) | A kind of electromagnetism heat conducting oil type lignum veneer drying-machine | |
CN205398550U (en) | Coal tar dewatering device | |
CN103743212A (en) | Waste heat energy saving automatic humidification and drying line | |
CN203294798U (en) | Molecular sieve filling machine | |
CN202172820U (en) | Energy-saving efficient solar barn | |
CN206445919U (en) | A kind of pre-molding device for waste and old wood plate | |
CN205340508U (en) | Micro -thermal regeneration adsorption type drying machine | |
CN202993756U (en) | Drying chamber with pipeline drying system | |
CN204640937U (en) | A kind of facial tissue preheater of corrugated paper board production line | |
CN214572964U (en) | Continuous preimpregnation device for impregnated paper production | |
CN209190956U (en) | A kind of door-plate core material molding equipment | |
CN205740370U (en) | A kind of active carbon production equipment | |
CN207215674U (en) | A kind of traffic water-proof and anti-corrosive material detection means | |
CN204298310U (en) | A kind of Cortex Eucommiae gelatin extraction technique that is used for is to the quick-fried device of the pretreated vapour of Cortex Eucommiae | |
CN205133458U (en) | Waste heat utilization system of emulsion explosive sensitization process | |
CN201588116U (en) | Heating groove used in groove-type heating ironing machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170329 Termination date: 20170830 |
|
CF01 | Termination of patent right due to non-payment of annual fee |