CN206021347U - Comprehensive wastage reducing and energy saving distribution network big data system - Google Patents

Comprehensive wastage reducing and energy saving distribution network big data system Download PDF

Info

Publication number
CN206021347U
CN206021347U CN201620755433.2U CN201620755433U CN206021347U CN 206021347 U CN206021347 U CN 206021347U CN 201620755433 U CN201620755433 U CN 201620755433U CN 206021347 U CN206021347 U CN 206021347U
Authority
CN
China
Prior art keywords
data
distribution network
comprehensive
energy saving
substation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620755433.2U
Other languages
Chinese (zh)
Inventor
柯峰
柯永达
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Power Grid Co Ltd
Original Assignee
Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Power Grid Co Ltd filed Critical Guangdong Power Grid Co Ltd
Priority to CN201620755433.2U priority Critical patent/CN206021347U/en
Application granted granted Critical
Publication of CN206021347U publication Critical patent/CN206021347U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

This utility model is related to a kind of comprehensive wastage reducing and energy saving distribution network big data system, break the examination point that present power system specifies and only arrive 10kV high-tension distribution chamber of converting and 0.4kV low-voltage distributions room, examination point is extended to each electricity consumer terminal, in user terminal, data acquisition unit is set, the various electricity consumption datas of collection user terminal, including dynamic data and static data, the data for collecting are carried out administration by different levels, the data that user terminal is collected by data concentrator, the data of each manifold are pooled to the substation for being arranged on region (section) administrative center again, region (section) administrative center is pooled to the main website for being arranged on administrative center of branch office again;Adopt comprehensive wastage reducing and energy saving distribution network big data system of said structure accurate and full and accurate basic data to be provided with for distribution system planning design, improve distribution network management level, improve the advantage of power supply reliability, safety and process accident promptness.

Description

Comprehensive wastage reducing and energy saving distribution network big data system
Technical field
This utility model belongs to the distribution network design field of intelligent grid, more particularly to a kind of comprehensive wastage reducing and energy saving Distribution network big data system.
Background technology
System for distribution network of power network design industry, temporarily goes back the intellectuality for such specialty that neither one is suitable for now The system for providing scientific and reasonable really and accurately basic data, only is the manual according to scene of operating management department in system The fragmentary data typing for collecting or retouching system is existing generalized information system (GIS-Geographic Information System).
The existing examination point of power system is that 10kV high-tension distribution chamber of converting (massive quantity power supply and measurement point) or 0.4kV low-voltage distributions room are (high For low enumeration), the circuit following to the examination point and electricity consumption facility are just not examined, and this is a large range of examination leakage Area, the power factor (PF) in the drain region may be relatively low, and harmonic content, line loss etc. may be larger, take no action to make electric energy wave Take very big.
Existing conventional means are the detecting instrument instrument for taking the electric current of mesolow, voltage, power factor (PF) etc., in addition Transformator detection, load detection device;Also the unit and area having did distribution automation system, had installed TTU, DTU, FTU additional It is acquired Deng terminal controller, but restriction and great majority due to monitored examination point is because technological means level owes height So that the factor such as not high, poor reliability of rate of reaching the standard grade causes to meet comprehensive data acquisition, prevent the management level of network from Obtain real raising;For using fiber-optic transfer information communication plan then due to the comprehensive method of investment is too high and enforcement difficulty too Greatly cannot spread.
Content of the invention
The purpose of this utility model is that solving prior art distribution network system does not have targetedly intelligent offer entirely The problem of the accurate basic data in face, and a kind of comprehensive wastage reducing and energy saving distribution network that offer can accurately provide basic data comprehensively is big Data system.
The technical scheme adopted by this utility model is:
A kind of comprehensive wastage reducing and energy saving distribution network big data system, including some data acquisition units, some data concentrator, Substations at different levels, main websites at different levels, transmission network;
The data acquisition unit, including data acquisition unit and data processing unit, the data acquisition unit is used for adopting The data of collection user terminal, the data processing unit draw final conclusion formula number for the data for collecting are carried out with calculating analysis According to, and the data collected by data standalone unit and final conclusion formula data are uploaded to the data belonging to which by the transmission network Manifold;
The data concentrator is used for the data for collecting the data acquisition unit for establishing communication passage, and handle collects To data be uploaded to the substation belonging to which by the transmission network;
Affiliated substation, for being collected to the data of the data concentrator of its subordinate and being uploaded to which by transmission network Affiliated main website;
The main website, for receiving the data that its subordinate substation at different levels uploads, to each data concentrator of its subordinate and The data of substations at different levels carry out monitor in real time, can consult mutually various data between the main websites at different levels.
Further improve, the data of the data acquisition unit collection include dynamic data and static data.
Further improve, the data of the data acquisition unit collection include voltage, electric current, power factor (PF), active power, nothing Work(power, harmonic voltage and power consumption.
Further improve, the data of the data acquisition unit collection also include artificially operate a switch power off time record and failure jump Power off time record and voltage pulsation record that lock is caused.
Further improve, in the substation and main website, be equipped with warning system, when data are not in data judgement principle model Warning is sent when within enclosing immediately.
Further improve, the transmission network is wireless-transmission network.
The beneficial effects of the utility model are:
This utility model arranges data acquisition unit in user terminal, collects basic data, sets can Intelligent electric power engineering Meter systems have basic data support, make the receipts money of power engineering design simple and clear, efficiently, reliable accurate;Comprehensively can slap Hold distribution network operation conditions (containing multinomial truthful data) reliable and effective whole to propose to relevant administration section or owner etc. Change scheme (such as:Reactive-load compensation is improving power factor (PF), configuration and eliminate or reduce harmonic wave facility, Reasonable adjustment circuit section, energetically Using effective wastage reducing and energy saving measure of high-tech energy-conserving product and enforcement etc.), to reach reasonable effectively wastage reducing and energy saving Purpose.
The dynamic of data acquisition unit collection and static data pass to higher level substation and main website by transmission network, can make system Interior operating management department is had at fingertips to the static and dynamic data of all circuits of distribution network systems and equipment, and analysis and judgment has root to have According to, there is provided the efficiency of management;
As first hand basic data can be collected, judge existing line on good grounds in system and device layout can be made Whether reasonable, if to need revised planning, adjustment wiring, transformation reconstruction etc.;
This utility model is provided with warning system, once occurring not conforming to the data system for passing judgment on rule immediately in distribution network Report to the police, can largely eliminate safe hidden trouble, improve distribution quality and improve maintenance efficiency;
It is distribution system planning that a kind of comprehensive wastage reducing and energy saving distribution network big data system that this utility model is provided has Design provides accurate and full and accurate basic data, improves distribution network management level, improves power supply reliability, safety, comprehensively Reduce the advantage of line loss and process accident promptness.
Description of the drawings
The network structure of a kind of comprehensive wastage reducing and energy saving distribution network big data system that Fig. 1 is provided for this utility model Schematic diagram.
Specific embodiment
The utility model is described in further detail with specific embodiment below in conjunction with the accompanying drawings.
Embodiment, a kind of comprehensive wastage reducing and energy saving distribution network big data system, as shown in figure 1, including some data acquisitions Device, some data concentrator, substations at different levels, main websites at different levels, transmission network;
The data acquisition unit, including data acquisition unit and data processing unit, the data acquisition unit is used for adopting The data of collection user terminal, the data processing unit draw final conclusion formula number for the data for collecting are carried out with calculating analysis According to, and the data collected by data standalone unit and final conclusion formula data are uploaded to the data belonging to which by the transmission network Manifold;The data of the data acquisition unit collection include voltage, electric current, power factor (PF), active power, reactive power, harmonic wave Power off time record and voltage that the static datas such as voltage and power consumption, power off time of artificially operating a switch record and fault trip are caused The dynamic datas such as fluctuation record;For the determination of each acquisition terminal, investigation can be carried out through scene and do a special design again, visually Practical situation determines that also part terminal is merged into a collection point by visual feelings.
The data concentrator is used for the data for collecting the data acquisition unit for establishing communication passage, and handle collects To data be uploaded to the substation belonging to which by the transmission network.
Affiliated substation, for being collected to the data of the data concentrator of its subordinate and being uploaded to which by transmission network Affiliated main website;Power supply preferably arranges data substation with 110kV transformer stations.
The main website, for receiving the data that its subordinate substation at different levels uploads, to each data concentrator of its subordinate and The data of substations at different levels carry out monitor in real time, can consult mutually various data between the main websites at different levels;The conduct of city branch office The administrative center of distribution big data, preferably sets up management main website, and the data of each section data concentrator and substation can be supervised at any time Control.
Warning system is equipped with the data acquisition unit, substation and main website, when data are not in data judgement principle model Warning is sent when within enclosing immediately.
As end point position is more, field condition is complicated, in addition this big data system to gather, measuring, calculating, point Based on analysis, judge, and remote manipulation is not made, harshness is not required for the transmission speed of information, so the technology mould of data transfer Formula is preferably preferred using being wirelessly transferred.For acquisition terminal preferably configures nothing according to 1-2 kilometers distance between the data concentrator of section Line transmission equipment;For data substation of the section data concentrator with 110kV transformer stations is preferably configured wirelessly according to 3-8 kilometers distance Transmission equipment;For the management main website of data substation to city branch office of 110kV transformer stations is preferably according to 5-15 kilometers distance configuration nothing Line transmission equipment.
When specifically used, break the examination point that present power system specifies and only arrive 10kV high-tension distribution chamber of converting (massive quantity power supply and measurement point) And 0.4kV low-voltage distributions room (high for low enumeration), examination point is put into each electricity consumer terminal.To each electricity consumer terminal (containing thousand Family ten thousand families and each enterprises and institutions, refer to qualified terminal certainly) voltage, electric current, power factor (PF), active, idle, humorous The data such as ripple, line loss, power consumption directly carry out intelligentized survey calculation metering, and are classified and carry out data transmission managing.Category In cell, a data concentrator can be set at Property Management of residence center;Belong to enterprises and institutions, one can be selected suitably Position sets a data concentrator, and in section, administrative center arranges substation, and in section, the data re-transmission of each manifold is to section Administrative center, is acquired to the track data of section and manages, and sets up main website in the branch office of prefectures and cities.The data of each manifold Branch office or district management center that each districts and cities office divide are transferred to again can, each branch office or district management center can be mutual as needed Data are mutually consulted, and power supply general bureau is also dependent on the data for needing to consult each basis;Each branch office can be being related to charging fee Continuous data is transmitted to the toll administration center of boil on the nape opposite the mouth.
Above-mentioned data acquisition necessarily forms a big data system, and the data volume of the big data system is with a city As a example by 110kV transformer stations, its 10kV outlet typically has 15-20 to return or so, averagely has that 20-30 10kV is high (to be contained with room for each time Switching station), each height with room averagely by 3 0.4kV low with room, each low with room averagely have 0.4kV outlets 10-15 return, per return 0.4kV outlets are be connected to electric terminal 10-50.Each electric terminal key data to be gathered is calculated by 10, Then having 3,600,000 or so static state and dynamic data needs to be acquired.If considered with branch office as management unit, if one point 15, Ju You 110kV transformer stations, then 3,600,000 * 15=5400, ten thousand data volumes.
Data of the above intellectuality substantial amounts of distribution network of collection define an Intelligentized internet-of-thing, can burst, Piecemeal collects and transmits, and can also concentrate and collect, and must accomplish to facilitate consultation, is easy to analyze, is easy to pass judgment on, is easy to propose rectification scheme Big data system.
A kind of comprehensive wastage reducing and energy saving distribution network that this utility model offer can be seen that by above specific embodiment Big data system provides accurate and full and accurate basic data with for distribution system planning design, improves distribution network management water Flat, improve power supply reliability, safety, the advantage for reducing line loss and process accident promptness.

Claims (6)

1. a kind of comprehensive wastage reducing and energy saving distribution network big data system, it is characterised in that including some data acquisition units, some numbers According to manifold, substations at different levels, main websites at different levels, transmission network;
The data acquisition unit, including data acquisition unit and data processing unit, the data acquisition unit is used for gathering to be used The data of family terminal, the data processing unit draw final conclusion formula data for the data for collecting are carried out with calculating analysis, and The data and final conclusion formula data collected by data standalone unit are uploaded to the tidal data recovering belonging to which by the transmission network Device;The data concentrator is used for collecting the data of the data acquisition unit for establishing communication passage, and being pooled to Data are uploaded to the substation belonging to which by the transmission network;
Affiliated substation, for being collected to the data of the data concentrator of its subordinate and being uploaded to belonging to which by transmission network Main website;
The main website, for receiving the data that its subordinate substation at different levels uploads, to each data concentrator of its subordinate and at different levels The data of substation carry out monitor in real time, can consult mutually various data between the main websites at different levels.
2. a kind of comprehensive wastage reducing and energy saving distribution network big data system according to claim 1, it is characterised in that the number The data gathered according to harvester include dynamic data and static data.
3. a kind of comprehensive wastage reducing and energy saving distribution network big data system according to claim 2, it is characterised in that the number The data gathered according to harvester include voltage, electric current, power factor (PF), active power, reactive power, harmonic voltage and electricity consumption Amount.
4. a kind of comprehensive wastage reducing and energy saving distribution network big data system according to claim 3, it is characterised in that the number The data gathered according to harvester also include the power off time record and electricity that power off time is recorded and fault trip is caused of artificially operating a switch Pressure fluctuation record.
5. a kind of comprehensive wastage reducing and energy saving distribution network big data system according to claim 1, it is characterised in that described Warning system is equipped with data acquisition unit, substation and main website, when data not within data judgement spirit when send out immediately Go out to report to the police.
6. a kind of comprehensive wastage reducing and energy saving distribution network big data system according to claim 1, it is characterised in that the biography Defeated network is wireless-transmission network.
CN201620755433.2U 2016-07-15 2016-07-15 Comprehensive wastage reducing and energy saving distribution network big data system Expired - Fee Related CN206021347U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620755433.2U CN206021347U (en) 2016-07-15 2016-07-15 Comprehensive wastage reducing and energy saving distribution network big data system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620755433.2U CN206021347U (en) 2016-07-15 2016-07-15 Comprehensive wastage reducing and energy saving distribution network big data system

Publications (1)

Publication Number Publication Date
CN206021347U true CN206021347U (en) 2017-03-15

Family

ID=58244903

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620755433.2U Expired - Fee Related CN206021347U (en) 2016-07-15 2016-07-15 Comprehensive wastage reducing and energy saving distribution network big data system

Country Status (1)

Country Link
CN (1) CN206021347U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110109906A (en) * 2019-05-08 2019-08-09 上海泰豪迈能能源科技有限公司 Data-storage system and method
CN112271821A (en) * 2020-12-21 2021-01-26 华南理工大学 Loss-reducing and energy-saving intelligent monitoring and analyzing system for power utilization terminal based on cloud computing

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110109906A (en) * 2019-05-08 2019-08-09 上海泰豪迈能能源科技有限公司 Data-storage system and method
CN112271821A (en) * 2020-12-21 2021-01-26 华南理工大学 Loss-reducing and energy-saving intelligent monitoring and analyzing system for power utilization terminal based on cloud computing

Similar Documents

Publication Publication Date Title
CN103135019A (en) Power quality monitoring management system based on electric power wide-area network
CN106199305A (en) Underground coal mine electric power system dry-type transformer insulation health state evaluation method
CN203166626U (en) Intelligent traction substation
CN102116857B (en) Method for checking electric quantity at power grid gate
CN104809665B (en) A kind of power distribution network method for early warning based on improvement Apriori algorithm
CN108418302A (en) A kind of power distribution network platform based on big data analysis
CN103995172B (en) Method for on-line monitoring of load current of GIS bus of substation
CN110907855B (en) Distribution network line fault detection method based on comprehensive distribution box and high-voltage sensor
CN104297616A (en) 10kV distribution line breaking detection method based on multi-system information interaction
CN103632311A (en) Fault examining system and method for power grid operation
CN106022974B (en) Comprehensive wastage reducing and energy saving distribution network big data system
CN106655516A (en) Power supply equipment collection device and remote fault diagnosis system
CN103616616B (en) Fault detection method for large-scale grounding grid
CN104375005A (en) Networked wind power plant harmonic wave monitoring system and method
CN206021347U (en) Comprehensive wastage reducing and energy saving distribution network big data system
CN101964548B (en) Comprehensive intelligent assembly of power transformer
CN105913126A (en) Transformer station intelligent alarm model method for big data and cloud environment
CN213072726U (en) Power distribution network architecture system based on intelligent concentrator
CN203164360U (en) Transformer device insulation online monitoring system
CN109167433A (en) A kind of substation concentrates the classification managing and control system and its method of O&M
CN106645938A (en) Electric energy management system and method for urban rail transit
CN103558432A (en) High-voltage direct connection type electricity stealing detection device
CN111105174A (en) Power distribution network power supply voltage qualification rate layered evaluation method and system
CN110488157A (en) A kind of high-speed railway through track fault section location method
CN203502504U (en) Electric power circuit line loss real time monitoring system based on internet of things

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170315