CN206016432U - A kind of construction enclosure wall - Google Patents
A kind of construction enclosure wall Download PDFInfo
- Publication number
- CN206016432U CN206016432U CN201620761567.5U CN201620761567U CN206016432U CN 206016432 U CN206016432 U CN 206016432U CN 201620761567 U CN201620761567 U CN 201620761567U CN 206016432 U CN206016432 U CN 206016432U
- Authority
- CN
- China
- Prior art keywords
- base
- slide block
- curtain wall
- support bar
- connection
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Power-Operated Mechanisms For Wings (AREA)
Abstract
The utility model discloses a kind of construction enclosure wall, including base and steady pin, one side roof part of the base is provided with curtain wall penel, chute is offered on the curtain wall penel, and chute is slidably connected with the first slide block on curtain wall penel, first slide block is connected with one end of support bar by bearing pin, the other end of the support bar is connected with the push-pull device at fixed in base by bearing pin, run through base in one end of the steady pin, and extend to the bottom of base, the both sides of steady pin are equipped with teeth, and the teeth of both sides are connected with the gear engagement in base, the side of gear is connected with the rotating shaft of the second motor, the push-pull device at fixed includes the first motor.The construction enclosure wall, by being provided with push-pull device at fixed, makes support bar promote curtain wall penel, you can to complete to build automatically, only needs a people complete work, not only increase work efficiency, and reusable after dismantling, very convenient.
Description
Technical field
This utility model is related to technical field of buildings, specially a kind of construction enclosure wall.
Background technology
In architectural engineering, the enclosure wall used by construction site is all temporary, after building builds up, construction site institute
The enclosure wall for using is accomplished by removing, and early stage building enclosing wall is formed by manually brick, not only labor intensive material resources, and can not
Reuse, so the enclosure wall that profile plate is built just is favored by masses, but the profile plate enclosure wall on current market is all
It is to be built by man-made assembly, the strength for depending merely on a people cannot be completed, needs many individuals just complete together, very inconvenient.
Utility model content
The purpose of this utility model is to provide a kind of construction enclosure wall, with solve in above-mentioned background technology propose ask
Topic.
For achieving the above object, this utility model provides following technical scheme:A kind of construction enclosure wall, including base and
Steady pin, one side roof part of the base are provided with curtain wall penel, are offered on chute, and chute and curtain wall penel on the curtain wall penel
First slide block is slidably connected, and first slide block is connected with one end of support bar by bearing pin, and the other end of the support bar leads to
Cross bearing pin to be connected with the push-pull device at fixed in base, base is run through in one end of the steady pin, and extend to the bottom of base, Gu
The both sides of rationed marketing are equipped with teeth, and the teeth of both sides are connected with the gear engagement in base, and the side of gear is electric with second
The rotating shaft connection of machine.
The push-pull device at fixed includes that the first motor, first motor are connected with one end of screw mandrel by the rotating shaft of side,
Leading screw is arranged with the screw mandrel, and the side of the leading screw is connected with the side of the second slide block by push rod, second slide block
Top be connected with one end of support bar by bearing pin, and the second slide block is connected with the slide on base.
Preferably, the quantity of the steady pin is set to two, and is located at the top of base both sides respectively.
Preferably, the side of the curtain wall penel is provided with two grooves, sets on curtain wall penel opposite side and the correspondence position of groove
There is projection, and projection is adapted with groove.
Preferably, the two ends of the screw mandrel are installed with limited block.
Preferably, second slide block and screw mandrel mutually stagger setting, and the both sides up and down of screw mandrel are respectively provided with push rod, and
Two push rods are not contacted with screw mandrel.
Compared with prior art, the beneficial effects of the utility model are:The construction enclosure wall, by being provided with push-and-pull dress
Put, make support bar promote curtain wall penel, you can to complete to build automatically, only need a people complete work, not only increase work
Efficiency, and reusable after dismantling, very convenient, by being provided with two steady pins, for whole device is played necessarily
Fixation, by being provided with groove and projection, multiple curtain wall penels can be connected together, be barricaded as enclosure wall.
Description of the drawings
Fig. 1 is this utility model texture edge schematic diagram;
Fig. 2 is this utility model push-pull device at fixed structural representation;
Fig. 3 is this utility model motor and gear connection structure schematic diagram.
In figure:1 base, 2 curtain wall penels, 3 first slide blocks, 4 support bars, 5 push-pull device at fixed, 51 leading screws, 52 screw mandrels, 53 first electricity
Machine, 54 limited blocks, 55 second slide blocks, 56 push rods, 6 steady pins, 7 teeth, 8 gears, 9 grooves, 10 second motors, 11 bearing pins.
Specific embodiment
Below in conjunction with the accompanying drawing in this utility model embodiment, the technical scheme in this utility model embodiment is carried out
Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of this utility model, rather than whole
Embodiment.Embodiment in based on this utility model, those of ordinary skill in the art are not under the premise of creative work is made
The every other embodiment for being obtained, belongs to the scope of this utility model protection.
Fig. 1-3 are referred to, this utility model provides a kind of technical scheme:A kind of construction enclosure wall, including base 1 and admittedly
Rationed marketing 6, the quantity of steady pin 6 are set to two, and are located at the top of 1 both sides of base respectively, and 1 one side roof part of base is provided with enclosure wall
Plate 2, the side of curtain wall penel 2 are provided with two grooves 9, and 2 opposite side of curtain wall penel is provided with projection with the correspondence position of groove 9, and
Projection is adapted with groove 9, offers chute, and chute is slidably connected with the first slide block 3 on curtain wall penel 2 on curtain wall penel 2,
First slide block 3 is connected with one end of support bar 4 by bearing pin 11, and the other end of support bar 4 is by pushing away in bearing pin 11 and base 1
Drawing device 5 connects, and crosses and is provided with push-pull device at fixed 5, makes support bar 4 promote curtain wall penel 2, you can to complete to build automatically, only needs a people
Work can be completed, not only increase work efficiency, and reusable, very convenient, one end of steady pin 6 after dismantling
Run through base 1, and extend to the bottom of base 1, by being provided with two steady pins, for whole device plays certain fixation
Multiple curtain wall penels 2 by being provided with groove 9 and projection, can be connected together, be barricaded as enclosure wall by effect, and the both sides of steady pin 6 are all provided with
There are teeth 7, and the teeth 7 of both sides are connected with the engagement of gear 8 in base 1, the rotating shaft of the side of gear 8 and the second motor 10
Connection, push-pull device at fixed 5 include that the first motor 53, the first motor 53 are connected with one end of screw mandrel 52 by the rotating shaft of side, screw mandrel
52 two ends are installed with limited block 54, are arranged with leading screw 51 on screw mandrel 52, and the side of leading screw 51 is by push rod 56 and the
The side connection of two slide blocks 55, the second slide block 55 and screw mandrel 52 are mutually staggered setting, and the both sides up and down of screw mandrel 52 are respectively provided with
Push rod 56, and two push rods 56 are not contacted with screw mandrel 52, the one end of the top of the second slide block 55 by bearing pin 11 and support bar 4
Connect, and the second slide block 55 is connected with the slide on base 1.
Operation principle:During use, start the first motor 53, the first motor 53 drives screw mandrel 52 to rotate, and then makes screw mandrel 52
Leading screw 51 is driven to move, leading screw 51 drives push rod 56 while mobile, and then makes the second slide block 55 carry out 4 jack-up of support bar,
So supported curtain wall penel 2, complete to build, then start the second motor 10, make gear 8 drive the teeth 7 of steady pin 6
Move down, you can realize fixing.
While there has been shown and described that embodiment of the present utility model, for the ordinary skill in the art,
Be appreciated that these embodiments can be carried out multiple changes in the case of without departing from principle of the present utility model and spirit, repair
Change, replace and modification, scope of the present utility model is defined by the appended claims and the equivalents thereof.
Claims (2)
1. a kind of construction enclosure wall, including base(1)And steady pin(6), it is characterised in that:The base(1)One side roof part
It is provided with curtain wall penel(2), the curtain wall penel(2)On offer chute, and chute and curtain wall penel(2)On the first slide block(3)Sliding
Dynamic connection, first slide block(3)By bearing pin(11)With support bar(4)One end connection, the support bar(4)The other end
By bearing pin(11)With base(1)Interior push-pull device at fixed(5)Connection, the steady pin(6)One end run through base(1), and
Extend to base(1)Bottom, steady pin(6)Both sides be equipped with teeth(7), and the teeth of both sides(7)With base(1)Interior
Gear(8)Engagement connection, gear(8)Side and the second motor(10)Rotating shaft connection;
The push-pull device at fixed(5)Including the first motor(53), first motor(53)By rotating shaft and the screw mandrel of side(52)
One end connection, the screw mandrel(52)On be arranged with leading screw(51), the leading screw(51)Side pass through push rod(56)With second
Slide block(55)Side connection, second slide block(55)Top pass through bearing pin(11)With support bar(4)One end connection, and
Second slide block(55)With base(1)On slide connection.
2. a kind of construction enclosure wall according to claim 1, it is characterised in that:The steady pin(6)Quantity arrange
For two, and it is located at base respectively(1)The top of both sides.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620761567.5U CN206016432U (en) | 2016-07-16 | 2016-07-16 | A kind of construction enclosure wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620761567.5U CN206016432U (en) | 2016-07-16 | 2016-07-16 | A kind of construction enclosure wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206016432U true CN206016432U (en) | 2017-03-15 |
Family
ID=58244952
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620761567.5U Expired - Fee Related CN206016432U (en) | 2016-07-16 | 2016-07-16 | A kind of construction enclosure wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206016432U (en) |
-
2016
- 2016-07-16 CN CN201620761567.5U patent/CN206016432U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107217602B (en) | A kind of bridge formwork separator | |
CN208913184U (en) | A kind of device for positioning and securing | |
CN110802686A (en) | Cutting equipment for wooden furniture board | |
CN206016432U (en) | A kind of construction enclosure wall | |
CN204523070U (en) | A kind of refinement breaker for limestone crushing equipment | |
CN108483110B (en) | A kind of wallpaper Scissoring device of fitting-up | |
CN207048325U (en) | A kind of aluminum alloy pattern plate provision for disengagement | |
CN208267420U (en) | A kind of easy-to-dismount building template support device | |
CN207026041U (en) | A kind of placement bucket for building building cement slurry | |
CN213104224U (en) | Steel bar cutting equipment for bridge | |
CN211313356U (en) | Building plastic formwork convenient to install | |
CN213513070U (en) | Municipal administration monitoring device | |
CN204035229U (en) | The stretching retracting device of a kind of unidirectional iron wire loop | |
CN207211717U (en) | Rapid forming mold for the house free of demolition of environment-friendly energy-saving | |
CN208056582U (en) | A kind of activity split-type Architectural Equipment operating platform | |
CN207296006U (en) | A kind of prefabricated house roof system of convenient dismounting | |
CN107989343A (en) | A kind of wall automatic scraping great Bai devices | |
CN221362402U (en) | Bending device for building engineering | |
CN219451387U (en) | Wall trowelling device for interior decoration | |
CN110270627A (en) | A kind of perforating steel pipe equipment convenient to use | |
CN219528554U (en) | Stage frame | |
CN221087330U (en) | Drilling machine for cable bridge | |
CN220711088U (en) | Cable erection structure for municipal power engineering | |
CN220583052U (en) | Drying device is used in polymer mortar construction | |
CN219710958U (en) | Supporting template for building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170315 Termination date: 20170716 |