CN206010620U - The alignment device of workpiece is processed on a kind of floor type boring machine - Google Patents
The alignment device of workpiece is processed on a kind of floor type boring machine Download PDFInfo
- Publication number
- CN206010620U CN206010620U CN201621070145.XU CN201621070145U CN206010620U CN 206010620 U CN206010620 U CN 206010620U CN 201621070145 U CN201621070145 U CN 201621070145U CN 206010620 U CN206010620 U CN 206010620U
- Authority
- CN
- China
- Prior art keywords
- workpiece
- boring machine
- floor type
- type boring
- alignment device
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Drilling And Boring (AREA)
Abstract
The alignment device of workpiece is processed on a kind of floor type boring machine, including workbench;It is located at the floor type boring machine of the workbench side;The scriber being connected with the main shaft of the floor type boring machine;Moveable theodolite and at least two rulers;The line being connected with workpiece two ends position of center line is hung down.The technical scheme that this utility model is provided, in calibration of workpieces, the workpiece side bus levelling and work centre line school precision parallel with datum line is up to 0.5mm or so, generally workpiece configurations size is up to several meters or even tens of rice, precision at processing typically can be controlled, within 0.05mm, to be entirely capable of the processing request for meeting workpiece.Relatively conventional technique, the technical scheme that this utility model is provided is faster, efficient, high precision.
Description
Technical field
This utility model is related to machining technology field, more particularly, to the centering for processing workpiece on a kind of floor type boring machine
Device.
Background technology
During the big workpiece such as floor type boring machine processing bucket wheel machine arm support, superstructure, because the reason such as workpiece overlength, ultra-wide, very
Hardly possible is corrected using main shaft.Traditional handicraft is in workpiece boring spindle telescopic extensions in place's to be processed to weld processing technique block:First
Lathe bed is moved first with boring machine guide rail, 4 technique blocks, miller are welded in this side proper range in main shaft calibration of workpieces side then
Skill block is shown in light;Workpiece is rotated by 90 °, and main shaft fills dial gauge gyp's skill block machined surface to requiring;After machining, polishing removes technique
Block.Do so not only can produce destruction to surface of the work, also add welding procedure block, processing technique block, correction main shaft and work
Skill block position, polishing remove technique block operation, bother very much, and long-time takes lathe;And main shaft telescopic extensions relative to
The size of workpiece is very little, beats table school precision out not high.
Utility model content
In order to overcome the defect of prior art, the technical problem that this utility model is solved to be:One kind is provided and can improve machine
Bed utilization rate, the alignment device for improving machining accuracy, being easy to processing workpiece on the floor type boring machine of correction large-scale workpiece.
In order to solve above-mentioned technical problem, this utility model provides the alignment device for processing workpiece on a kind of floor type boring machine,
Including workbench;It is located at the floor type boring machine of the workbench side;The scriber being connected with the main shaft of the floor type boring machine;Removable
Theodolite and at least two rulers;The line being connected with workpiece two ends position of center line is hung down.
The alignment device of workpiece is provided on the floor type boring machine provided as further improved technology scheme, this utility model,
Also have and be located between the workpiece and workbench, for adjusting the cushion block of the levelness of the workpiece.
The technical scheme that this utility model is provided, in calibration of workpieces, workpiece side bus levelling and work centre line school
, up to 0.5mm or so, usual workpiece configurations size is up to several meters or even tens of rice, the precision at processing for the precision parallel with datum line
Typically can control, within 0.05mm, to be entirely capable of the processing request for meeting workpiece.Relatively conventional technique, this utility model are provided
Technical scheme is faster, efficient, high precision.
Description of the drawings
Accompanying drawing is used for providing further understanding to of the present utility model, constitutes the part of the application, of the present utility model
Schematic description and description is used for explaining this utility model, does not constitute to improper restriction of the present utility model.In accompanying drawing
In:
Fig. 1 is the main structure diagram of the alignment device for processing workpiece on embodiment floor type boring machine;
Fig. 2 is the overlooking the structure diagram of the alignment device for processing workpiece on embodiment floor type boring machine;
Fig. 3 is to process main view state diagram of the alignment device of workpiece in calibration of workpieces on embodiment floor type boring machine;
Fig. 4 is the left view structural representation of Fig. 3;
Fig. 5 is to process vertical view state figure of the alignment device of workpiece in calibration of workpieces on embodiment floor type boring machine.
Specific embodiment
Below in conjunction with the accompanying drawings specific embodiment of the present utility model is described in further detail.
The alignment device of workpiece is processed on floor type boring machine as shown in Figures 1 to 5, including workbench 1;It is located at workbench 1
The floor type boring machine 2 of side;The scriber 3 being connected with the main shaft of floor type boring machine 2;Moveable theodolite 4 and at least two rulers 5;With
The line vertical 6 of 7 two ends position of center line connection of workpiece;It is located between workpiece 7 and workbench 1, for adjusting the levelness of workpiece 7
Cushion block 8.
During adjustment, as shown in Figure 2:Scriber 3 is loaded onto on the main shaft of floor type boring machine 2, by stretching for the main shaft of floor type boring machine 2
Datum line is drawn in contracting, scriber 3 on workbench 1(White lead can be applied on the table, make the datum line for marking apparent);Theodolite 4
Be centrally located on 3 drawn datum line of scriber, adjust theodolite 4, make 4 telescope mesh cylinder of theodolite formed face be turned round around axis
Overlap with datum line, datum line is extended to required position using the rotation telescope mesh cylinder of theodolite 4.
As shown in Figures 3 to 5:Workpiece 7 is lifted to workbench 1, is supported with cushion block 8, make the centrage and base of workpiece 7
Directrix is substantially parallel;6 are hung down in 7 two ends position of center line messenger wire of workpiece, online hanging down each between 6 and 1 datum line of workbench places one
Ruler 5, makes ruler 5 vertical with datum line, survey respectively workpiece 7 liang of end lines hang down 6 point between the scale and datum line of rulers apart from A
And B, adjusting workpiece 7, make A=B, then 7 centrage of workpiece is parallel with datum line, now the centrage of workpiece 7 and floor type boring machine 2
Main axis parallel;One end that theodolite 4 is placed in workpiece 7(Side), make ruler 5 keep vertical, and make 5 bottom of ruler or a certain fixation
Scale is maintained an equal level with the side bus of workpiece 7, is observed ruler 5 by theodolite 4, is remembered reading;Several keys are selected in 7 periphery of workpiece
Position, repeats the measurement of above-mentioned theodolite 4 and ruler 5, remembers reading and position respectively;Workpiece is adjusted by modes such as cushioning ferrum
7 height everywhere, until the reading that all position upper warp and woof instrument 4 measure ruler 5 is consistent, then now 7 surrounding side bus level of workpiece,
That is 7 level of workpiece;
The size of detection A and B, finely tunes 7 center of workpiece in the case where holding is highly constant if changing again, until
A=B.So far, the calibration of workpiece 7 is finished.
When drawing datum line on the table, in addition to it can draw the datum line with the main axis parallel of floor type boring machine 2, can also use
Close method draws the datum line vertical with main shaft using the movement of floor type boring machine guide rail, can make forever datum line on workbench 1
Identify long.
The technical scheme that this utility model is provided, in calibration of workpieces 7,7 side bus levelling of workpiece and 7 centrage of workpiece
The school precision parallel with datum line up to 0.5mm or so, because 7 overall dimensions of workpiece are up to several meters of even tens of rice, the essence at processing
Degree typically can be controlled, within 0.05mm, to be entirely capable of the processing request for meeting workpiece 7.Relatively conventional technique, this utility model are carried
For technical scheme is faster, efficient, high precision.
Obviously, this utility model is not limited to above preferred implementation, can also be in this utility model claim and explanation
In the spirit that book is limited, the conversion and improvement of various ways is carried out, same technical problem can be solved, and obtained expected technology
Effect, therefore do not repeat.One of ordinary skill in the art can from this utility model disclosure directly or associate all
Scheme, as long as within the spirit that claim is limited, fall within protection domain of the present utility model.
Claims (2)
1. the alignment device of workpiece is processed on a kind of floor type boring machine, it is characterised in that including workbench(1);It is located at the work
Platform(1)The floor type boring machine of side(2);With the floor type boring machine(2)Main shaft connection scriber(3);Moveable theodolite(4)
At least two rulers(5);With workpiece(7)The line of two ends position of center line connection hangs down(6).
2. the alignment device of workpiece is processed on floor type boring machine according to claim 1, it is characterised in that is also had and is located at institute
State workpiece(7)With workbench(1)Between, for adjusting the workpiece(7)Levelness cushion block(8).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621070145.XU CN206010620U (en) | 2016-09-22 | 2016-09-22 | The alignment device of workpiece is processed on a kind of floor type boring machine |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621070145.XU CN206010620U (en) | 2016-09-22 | 2016-09-22 | The alignment device of workpiece is processed on a kind of floor type boring machine |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206010620U true CN206010620U (en) | 2017-03-15 |
Family
ID=58261101
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621070145.XU Active CN206010620U (en) | 2016-09-22 | 2016-09-22 | The alignment device of workpiece is processed on a kind of floor type boring machine |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206010620U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108971584A (en) * | 2018-08-06 | 2018-12-11 | 华业钢构核电装备有限公司 | A kind of heavy in section steel column end face milling method of branch |
-
2016
- 2016-09-22 CN CN201621070145.XU patent/CN206010620U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108971584A (en) * | 2018-08-06 | 2018-12-11 | 华业钢构核电装备有限公司 | A kind of heavy in section steel column end face milling method of branch |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205228355U (en) | Geometric tolerances test position is used to portable axle | |
CN104385129A (en) | Mounting fixture special for drilling leveling of bottom surface of workpiece | |
CN204546132U (en) | A kind of automobile die part by numerical control processing school benchmark device | |
CN206010620U (en) | The alignment device of workpiece is processed on a kind of floor type boring machine | |
CN210998472U (en) | A pressfitting tool for irregular part | |
CN205967454U (en) | Lathe | |
CN205967887U (en) | Frock is assembled to crane beam | |
CN205733858U (en) | A kind of lathe work platforms of improvement | |
CN104132632A (en) | Workpiece verifying device, workpiece verifying method and workpiece machining method | |
CN107175359B (en) | X-shaped slide block guide rail processing method | |
CN203837616U (en) | Outer correction machine of mechanical processing machine | |
CN109531296A (en) | A kind of deep hole vertical multi-shaft grinding machine | |
CN107378021A (en) | A kind of processing method of endoporus | |
CN209737083U (en) | Marine air compressor machine gear box frock | |
CN209408079U (en) | A kind of deep hole vertical multi-shaft grinding machine | |
CN104117913A (en) | Alignment method for rotary center of multi-grinding-head rotary table | |
CN203831180U (en) | Engraving and milling machine | |
CN107097042B (en) | A kind of processing method of the strip-shaped work suitable for the non-full circle in section | |
CN108748064A (en) | Rapid embarkation bearing calibration of the large-scale diesel engine rack on planer-type milling machine | |
CN109002007B (en) | Quick levelling device of digit control machine tool | |
CN107127513A (en) | A kind of damper tool for welding support lug | |
CN106624620A (en) | Processing method for large suspension bridge splay saddle | |
CN205020962U (en) | Code wheel plane machine tool | |
CN106052535A (en) | Tool for taper detection and realization method thereof | |
CN208575543U (en) | A kind of support leveling unit for processing impeller |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
PE01 | Entry into force of the registration of the contract for pledge of patent right | ||
PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of utility model: Aligning device of processing work piece on floor type boring machine Effective date of registration: 20180503 Granted publication date: 20170315 Pledgee: Xiangtan Jiuhua Economic Construction Investment Co., Ltd. Pledgor: Tidfore Engineering Co., Ltd.|Tidfore Heavy Industry Co., Ltd.|Ocean engineering equipment (Tianjin) Co., Ltd. Registration number: 2018430000029 |