- CN205989148U CN205989148U CN201620859930.7U CN201620859930U CN205989148U CN 205989148 U CN205989148 U CN 205989148U CN 201620859930 U CN201620859930 U CN 201620859930U CN 205989148 U CN205989148 U CN 205989148U
- Authority
- CN
- China
- Prior art keywords
- flange
- supporting construction
- bend pipe
- location structure
- flange location
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Butt Welding And Welding Of Specific Article (AREA)
Abstract
The utility model discloses a kind of bend pipe flange weld tooling, including the first supporting construction, second supporting construction, described first supporting construction is provided with moveable first flange location structure, described second supporting construction is provided with moveable second flange location structure, described first flange location structure, the corresponding location hole in bolt hole position with acting flange to be welded is equipped with second flange location structure, location hole on first flange location structure is aligned with the location hole on second flange location structure, described first flange location structure is parallel with bend pipe one end to be welded end face, described second flange structure is parallel with bend pipe other end end face to be welded.Flange bolt hole during this utility model achieves bend pipe flange welding aligns so that bend pipe flange welding is more accurate, more convenient to operate.
Description
Technical field
This utility model is related to welding tooling field and in particular to a kind of bend pipe flange weld tooling.
Background technology
Using during flange connections road it is desirable to the flange bolt hole of pipe ends aligns.For straight tube, its two ends
Flange bolt hole aligns and is also easier, but for bend pipe, such as, for conventional right-angle elbow pipe, its two ends is in welded flange
When be difficult to accomplish that flange bolt hole aligns, need welding personnel to have skillful solder technology, and welding process be relative complex,
Weld more time-consuming, lead to production efficiency to substantially reduce, therefore need a kind of bend pipe flange weld tooling at present badly.
Utility model content
Technical problem to be solved in the utility model is the bend pipe flange weldering providing a kind of structure to be simple and convenient to operate
Connect frock.
This utility model bend pipe flange weld tooling includes the first supporting construction, the second supporting construction, described first support
Structure is provided with moveable first flange location structure, and described second supporting construction is provided with moveable second flange positioning
Structure, described first flange location structure, second flange location structure are equipped with the bolt hole position pair with acting flange to be welded
The location hole answered, the location hole on first flange location structure is aligned with the location hole on second flange location structure, and described
One flange location structure is parallel with bend pipe one end to be welded end face, described second flange structure and bend pipe other end end face to be welded
Parallel.When carrying out bend pipe flange welding, according to the form of bend pipe, adjust first flange location structure beforehand through moving operation
Adjust second flange location structure in the position in the first supporting construction and by moving operation in the second supporting construction
Position, is respectively mounted flange, due on first flange location structure on first flange location structure, second flange location structure
Location hole align with the location hole on second flange location structure, in first flange location structure, second flange location structure
Bolt hole on upper mounted flange also aligns each other, afterwards by the method for bend pipe one end and installation on first flange location structure
Blue flange hole be aligned, the bend pipe other end is aligned with the flange hole of the flange installed on second flange location structure, is achieved in
Flange bolt hole during bend pipe flange welding aligns so that bend pipe flange welding is more accurate, more convenient to operate.
As the improvement further of above-mentioned bend pipe flange weld tooling, described first supporting construction and/or second supports
Structure includes support frame and is arranged at the guided way on support frame both sides, and the corresponding flange of supporting construction being provided with guided way is fixed
Bit architecture is provided with the slide construction agreeing with described guided way.According to this structure, above-mentioned moving operation is preferably slided behaviour
Make, guided way structure is capable of corresponding flange location structure slide thereon, structure is simple, easy to operate.Excellent
Selection of land, described slide construction is the sliding recess being arranged at companion flange location structure bottom and agreeing with guided way.
As the improvement further of above-mentioned bend pipe flange weld tooling, described first supporting construction and/or second supports
Structure includes support frame, the bearing being fixed on support frame one end and passes through bearing and the silk parallel to support frame setting
Thick stick, the supporting construction corresponding flange location structure being provided with leading screw is fixedly installed on described leading screw, and described leading screw is trapezoidal silk
Thick stick.According to said structure, moving operation is preferably the transmission operation of leading screw, flange can be driven fixed by rotating threaded shaft structure
Bit architecture along guide screw movement, be achieved in the moving operation of corresponding flange location structure, trapezoidal screw has auto-lock function,
Ensure companion flange location structure positional stability.
Further, described leading screw one end is provided with handle.The convenient operator of handle carry out rotation process to leading screw.
Further, described first supporting construction and the second supporting construction are vertically connected.This utility model is particularly suited for
The bend pipe of perpendicular type carries out flange welding.
Further, described first supporting construction is horizontally disposed with, and described second supporting construction is vertically arranged, described first
Support structure bottom is provided with base, and the lower end of described second supporting construction and the first supporting construction, base are sequentially connected.First support
Structure, second support result, base is linked as entirety so that this utility model structure is more stable.
Further, the support frame being provided with the first supporting construction is provided with the reinforcing transverse slat on connection framework both sides.So that
The support frame of the first supporting construction is more firm.
As the improvement further of above-mentioned bend pipe flange weld tooling, described first supporting construction, the second supporting construction
On be equipped with position measurement structure.Thus mustn't be by extra other survey tools, can be directly on this utility model
Accurately determine the shift position of first flange location structure and second flange location structure, finally accurately determine the peace of respective flange
Holding position so that bend pipe carry out operating during flange welding simpler quick.
Further, institute's position measurement structure includes being arranged at the first support along first flange location structure moving direction
In structure first measures steel ruler and is arranged in the second supporting construction second along second flange location structure moving direction
Measurement steel ruler.Steel ruler uses Stability Analysis of Structures, wear-resisting, facilitates operator directly to read flange installation site.
Below by way of accompanying drawing and specific embodiment, the utility model is described in further detail.
Brief description
Fig. 1 is structural representation of the present utility model.
Specific embodiment
Below so that welding object is respectively welded at the flange at perpendicular type bend pipe two ends for perpendicular type bend pipe and needing as a example
The utility model is described in further detail.
This utility model bend pipe flange weld tooling, including the first supporting construction 1, the second supporting construction 2, described first
Support structure 1 is vertically connected with the second supporting construction 2, and described first supporting construction 1 is horizontally disposed with, and described second supporting construction 2 is erected
Straight arrange, described first supporting construction 1 bottom is provided with base 3, the lower end of described second supporting construction 2 and the first supporting construction 1,
Base 3 is sequentially connected.Described first supporting construction 1 is provided with moveable first flange location structure 110, described second support
Structure 2 is provided with moveable second flange location structure 210.Described first supporting construction 1 includes the first square carriage
Frame 130 and the linear type guided way 140 being arranged at the first support frame 130 both sides, first flange location structure 110 be provided with
The slide construction that described guided way 140 agrees with, described slide construction be arranged at companion flange location structure bottom and with guiding
The sliding recess that rail 140 agrees with.Described second supporting construction 2 includes the second square support frame 230, is fixed on the second support
The bearing 240 on framework 230 top and pass through bearing 240 and parallel to the second support frame 230 setting leading screw 220, second
Flange location structure 210 is fixedly installed on described leading screw 220.Described leading screw 220 one end is provided with handle 250.It is provided with first
Support frame frame 130 is provided with the reinforcing transverse slat 120 on connection framework both sides.In described first supporting construction 1, the second supporting construction 2 all
It is provided with position measurement structure.Institute's position measurement structure includes being arranged at along first flange location structure 110 glide direction
In one supporting construction 1 first measures steel ruler 150 and is arranged at the second support along second flange location structure 210 glide direction
The second measurement steel ruler 260 in structure 2.Described leading screw 220 is preferably from the trapezoidal screw with auto-lock function.
Described first flange location structure 110, second flange location structure 210 are all along rectilinear movement, described first flange
Location structure 110 includes first flange location-plate 111 and is arranged on the first flange location hole on first flange location-plate 111
112, second flange location structure 210 includes second flange location-plate 211 and is arranged on second flange location-plate 211
Two flange location holes 212, first flange location hole 112 is aligned with second flange location hole 212, described first flange location structure
110 is parallel with bend pipe one end to be welded end face, and described second flange location structure 210 and bend pipe other end end face to be welded are put down
OK.
The flange that wherein first flange location structure 110 and second flange location structure 210 all can weld as needed
Different size is changed.
Hereinafter again using method of the present utility model is described further:
When bend pipe flange welding is carried out to above-mentioned perpendicular type bend pipe to be welded, according to the size of bend pipe, determine and need
Flange size to be welded, determines first flange location structure 110 and second flange location structure 210 by flange size
Specification, specifically namely determine size and first method of first flange location-plate 111 and second flange location-plate 211
Blue location hole 112 and the size of second flange location hole 212, by reading the reading on the first measurement steel ruler 150, predefine
Position on guided way 140 for the good first flange location structure 110 parallel with bend pipe one end to be welded end face, slide-and-guide rail
First flange location structure 110 on 140 adjusts its position, by reading the reading on the second measurement steel ruler 260, predefines
The position of the good second flange location structure 210 parallel with welding bend pipe other end end face, by rotary handle 250, drives
Leading screw 220 moves, and leading screw 220 linkage second flange location structure 210 thus reaches the mesh of adjustment second flange location structure 210
's.
Position in the first supporting construction 1 for the first flange location structure 110 is adjusted by above-mentioned slide and leads to
Cross leading screw 220 combined operation and adjust position in the second supporting construction 2 for the second flange location structure 210, fixed in first flange
Respectively mounting flange is corresponded to by bolt on bit architecture 210, second flange location structure 220, due to first flange location hole 112
Align with second flange location hole 212, therefore install on first flange location structure 110, second flange location structure 210
Flange on bolt hole also align each other, will install on bend pipe one end to be welded and first flange location structure 110 afterwards
Flange bolt hole be aligned, the bend pipe other end is aligned with the bolt hole of flange of installation on second flange location structure, thus
Achieve the flange bolt hole during bend pipe flange welding to be welded to align so that bend pipe flange welding is more accurate, operation
Convenient.
For other non-right angle bend pipes, this utility model keeps first flange location hole 112 in implementation process
Align with second flange location hole 212, described first flange location structure 110 is parallel with bend pipe one end to be welded end face, described
Second flange location structure 210 is parallel with bend pipe other end end face to be welded, and corresponding first supporting construction 1 and second that changes supports
Angle between structure 2, concrete welding step ibid, will not be described here.
Claims (10)
1. bend pipe flange weld tooling is it is characterised in that include the first supporting construction (1), the second supporting construction (2), and described the
One supporting construction (1) is provided with moveable first flange location structure (110), and described second supporting construction (2) is provided with can
The second flange location structure (210) of movement, on described first flange location structure (110), second flange location structure (210)
Be equipped with the corresponding location hole in bolt hole position with acting flange to be welded, the location hole on first flange location structure (110) with
Location hole on second flange location structure (210) aligns, described first flange location structure (110) and bend pipe one end to be welded
End face is parallel, and described second flange location structure (210) is parallel with bend pipe other end end face to be welded.
2. bend pipe flange weld tooling as claimed in claim 1 is it is characterised in that described first supporting construction (1) and/or
Two supporting constructions (2) include support frame and the guided way (140) being arranged at support frame both sides, are provided with guided way (140)
Supporting construction corresponding flange location structure is provided with the slide construction agreeing with described guided way (140).
3. bend pipe flange weld tooling as claimed in claim 2 is it is characterised in that described slide construction is to be arranged at correspondent method
Blue location structure bottom the sliding recess agreeing with guided way (140).
4. bend pipe flange weld tooling as claimed in claim 1 is it is characterised in that described first supporting construction (1) and/or
Two supporting constructions (2) include support frame, the bearing (240) being fixed on support frame one end and pass through bearing (240) and put down
Row is fixedly installed in the leading screw (220) of support frame setting, the supporting construction corresponding flange location structure being provided with leading screw (220)
On described leading screw (220), described leading screw (220) is trapezoidal screw.
5. bend pipe flange weld tooling as claimed in claim 4 is it is characterised in that described leading screw (220) one end is provided with handle
(250).
6. the bend pipe flange weld tooling as described in claim 2 or 4 is it is characterised in that described first supporting construction (1) and the
Two supporting constructions (2) are vertically connected.
7. bend pipe flange weld tooling as claimed in claim 6 is it is characterised in that described first supporting construction (1) level sets
Put, described second supporting construction (2) is vertically arranged, described first supporting construction (1) bottom is provided with base (3), described second
The lower end of support structure (2) is sequentially connected with the first supporting construction (1), base (3).
8. bend pipe flange weld tooling as claimed in claim 7 is it is characterised in that be provided with the support of the first supporting construction (1)
Framework is provided with the reinforcing transverse slat (120) on connection framework both sides.
9. bend pipe flange weld tooling as claimed in claim 1 it is characterised in that described first supporting construction (1), second
Support structure is equipped with position measurement structure on (2).
10. bend pipe flange weld tooling as claimed in claim 9 is it is characterised in that institute's position measurement structure is included along
One flange location structure (110) moving direction is arranged at the first measurement steel ruler (150) in the first supporting construction (1) and along the
Two flange location structure (210) moving directions are arranged at the second measurement steel ruler (260) in the second supporting construction (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620859930.7U CN205989148U (en) | 2016-08-10 | 2016-08-10 | Bend pipe flange weld tooling |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620859930.7U CN205989148U (en) | 2016-08-10 | 2016-08-10 | Bend pipe flange weld tooling |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205989148U true CN205989148U (en) | 2017-03-01 |
Family
ID=58106830
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620859930.7U Expired - Fee Related CN205989148U (en) | 2016-08-10 | 2016-08-10 | Bend pipe flange weld tooling |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205989148U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107116328A (en) * | 2017-04-25 | 2017-09-01 | 成都乔依赛斯石油科技有限公司 | The fixing device aligned when being easy to bend pipe with flange welding |
CN111037175A (en) * | 2019-12-31 | 2020-04-21 | 燕山大学 | Automatic elbow welding auxiliary device |
-
2016
- 2016-08-10 CN CN201620859930.7U patent/CN205989148U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107116328A (en) * | 2017-04-25 | 2017-09-01 | 成都乔依赛斯石油科技有限公司 | The fixing device aligned when being easy to bend pipe with flange welding |
CN111037175A (en) * | 2019-12-31 | 2020-04-21 | 燕山大学 | Automatic elbow welding auxiliary device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205989148U (en) | Bend pipe flange weld tooling | |
CN103692251B (en) | A kind of Cylinder Parts angle of bend is measured and level and vertical plane boring grab | |
CN101695787B (en) | Crossed column assembling machine | |
CN103157945B (en) | Concrete pump truck cantilever crane installing and welding location device | |
CN103770153A (en) | Machining equipment and method capable of machining side-hung casement hinge holes automatically and accurately | |
CN203426643U (en) | Welding tool for climbing frame of tower crane | |
CN103325595B (en) | Bearing platform for adjusting switch operating mechanism in four directions | |
CN216000334U (en) | Vehicle door hinge mounting equipment | |
CN215091756U (en) | Steel tie rod processing platform | |
CN210755294U (en) | Novel high-precision drilling equipment for extra-high-pressure steel plate | |
CN110722317B (en) | Block assembly tool and method for block type steel pipe ring | |
CN109269382B (en) | Detection device and detection method for top drive double guide rails | |
CN219053227U (en) | Manual laser welding device | |
CN202845832U (en) | Row drilling machine | |
CN207223471U (en) | A kind of numerical control machining center diclinic hole drilling equipment | |
CN201960315U (en) | Rolling wheel for large circumference soldering | |
CN111828052A (en) | Leading little pipe guiding orientation device | |
CN206500796U (en) | A kind of vertical automatic soldering device | |
CN206034428U (en) | SMW worker method stake shaped steel positioning die | |
CN203656493U (en) | Large base cross groove connection device | |
CN217192780U (en) | Plate punching device | |
CN214187870U (en) | Concrete slab drilling equipment is used in building site construction | |
CN212919365U (en) | Marking device of anchor clamps production usefulness | |
CN216264355U (en) | Pipe fitting welding tool for manufacturing metal corrugated oil conservator | |
CN114151008B (en) | Drilling equipment for construction site soil layer |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170301 Termination date: 20170810 |