CN205980348U - Mix water system - Google Patents
Mix water system Download PDFInfo
- Publication number
- CN205980348U CN205980348U CN201620889884.5U CN201620889884U CN205980348U CN 205980348 U CN205980348 U CN 205980348U CN 201620889884 U CN201620889884 U CN 201620889884U CN 205980348 U CN205980348 U CN 205980348U
- Authority
- CN
- China
- Prior art keywords
- water
- branch road
- main line
- tie point
- control unit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Domestic Plumbing Installations (AREA)
Abstract
The utility model discloses a mix water system, this system includes: the water heater, it carries the water in the water heater through the main line, first branch road, its water inlet is connected with the main line, and its delivery port is connected with water container, mix the hydrophone, the second branch road, its water inlet is connected with the main line, and its delivery port is connected with muddy hydrophone, a control unit, it links to each other with first branch road and second branch road respectively, first branch road switches on so that the water in the water heater is carried to water container through first branch road through controlling for it, perhaps switch on through control second branch road so that the water in the water heater passes through the transport of second branch road to mixing the hydrophone, therefore, can carry water container with cold water through the second branch road, prevent that cold water from flowing from mix water system's delivery port, it is amazing to avoid the user to receive cold water when the water, the water comfort level has been improved, and simultaneously, carry out effectual recycle to cold water, water resources are saved, it is more intelligent and humanized, thereby improving user experience.
Description
Technical field
This utility model is related to an electro-technical field, particularly to a kind of turbid water system.
Background technology
In the related, pass through Pipeline transport after water heater heats to cold water to water-water jet, and pass through water-water jet
Control the switch of water temperature, the water yield and water valve.But, correlation technique has the drawback that, the pipeline between water heater and water-water jet
In have cold water, user use warm water during, need manually these cold water are bled off, cause water resource waste, and
Need user constantly water temperature to be tested and reach suitable temperature until outlet water temperature, be that user makes troubles, time-consuming take
God.
Therefore, correlation technique needs to improve.
Utility model content
This utility model is intended at least solve one of technical problem in correlation technique to a certain extent.For this reason, this reality
It is to propose a kind of turbid water system with water-saving function with new purpose.
For reaching above-mentioned purpose, the utility model proposes a kind of turbid water system, including:Water heater, described water heater leads to
Cross main line and convey the water in described water heater;Tie point, the water inlet of described tie point is connected with described main line, institute
The outlet stating tie point is connected with tank;Water-water jet;Second branch road, the water inlet of described second branch road and described master
Pipeline connects, and the outlet of described second branch road is connected with described water-water jet;Control unit, described control unit respectively with described
Tie point is connected with described second branch road, and described control unit passes through to control the conducting of described tie point so that described water heater
Interior water is delivered to described tank by described tie point, or by controlling described second branch road conducting so that described
Water in water heater is delivered to described water-water jet by described second branch road.
According to the utility model proposes turbid water system, control unit pass through control tie point conducting, make water heater
Main line is connected with tie point, so that the water in water heater is transported to tank by tie point, or by controlling
Second branch road conducting, makes the main line of water heater connect with the second branch road, so that the water in water heater passes through the second branch road conveying
To water-water jet, thus, the cold water in main line can be transported to by tank by the second branch road, prevent cold water from turbid water system
Outlet flow out, it is to avoid user when with water be subject to cold water stimulating, improve and use water comfort level, cold water is had meanwhile
The recycling of effect, has saved water resource, and more intelligent and hommization improves Consumer's Experience.
Specifically, described main line is connected with described tie point and described second branch road by three-way valve, wherein, described
The water inlet of three-way valve is connected with described main line, and the first outlet of described three-way valve is connected with described tie point, described
Second outlet of three-way valve is connected with described second branch road.
Further, described turbid water system also includes:It is arranged on the temperature detector in described main line, described temperature
Detector is used for detecting the water temperature in described main line, and wherein, the water temperature that described control unit is used in described main line is little
Control described tie point conducting when preset temperature threshold value, and the water temperature in described main line is more than or equal to described default temperature
Control described second branch road conducting during degree threshold value.
Further, described turbid water system also includes:It is arranged on the Level Detection unit in described tank, described
Level Detection unit is used for detecting the liquid level of described tank, and wherein, described control unit is used in described tank
Liquid level controls described tie point to close when being more than default level threshold.
Further, described turbid water system also includes:It is arranged on the drain assembly of described tank, wherein, described
Control unit is used for controlling described drain assembly to beat when the accumulative ON time of described tie point is more than preset time threshold
Open, so that described tank carries out draining.
Specifically, described control unit can be the main control chip of described water-water jet.
Brief description
Fig. 1 is the block diagram of the turbid water system according to this utility model embodiment;
Fig. 2 a is the operation principle schematic diagram of the three-way valve of the turbid water system according to one embodiment of this utility model;
Fig. 2 b is the operation principle schematic diagram of the three-way valve of the turbid water system according to another embodiment of this utility model;
Fig. 2 c is the operation principle schematic diagram of the three-way valve of the turbid water system according to another embodiment of this utility model;
Fig. 2 d is the block diagram of the turbid water system according to one embodiment of this utility model;
Fig. 3 is the block diagram of the turbid water system according to another embodiment of this utility model;
Fig. 4 is the block diagram of the turbid water system according to another embodiment of this utility model;
Fig. 5 is the flow chart of the control method of the turbid water system according to this utility model embodiment;And
Fig. 6 is the flow chart of the control method of the turbid water system according to one embodiment of this utility model.
Reference:
Water heater 10, tie point 20, water-water jet 30, the second branch road 40 and control unit 50;
Tank 60;Main line 100, three-way valve 101 and temperature detector 102;
Level Detection unit 601 and drain assembly 602.
Specific embodiment
Embodiment of the present utility model is described below in detail, the example of described embodiment is shown in the drawings, wherein ad initio
To the element that same or similar label represents same or similar element or has same or like function eventually.Below by ginseng
The embodiment examining Description of Drawings is exemplary it is intended to be used for explaining this utility model, and it is not intended that to this utility model
Restriction.
Below with reference to the accompanying drawings turbid water system and its control method of the proposition of this utility model embodiment to be described.
Fig. 1 is the block diagram of the turbid water system according to this utility model embodiment.As shown in figure 1, this turbid water system 1
Including:Water heater 10, tie point 20, water-water jet 30, the second branch road 40 and control unit 50.
Wherein, water heater 10 conveys the water in water heater 10 by main line 100;The water inlet b1 of tie point 20 and master
Pipeline 100 connects, and the outlet b2 of tie point 20 is connected with tank 60;The water inlet c1 of the second branch road 40 and main line
100 connections, the outlet c2 of the second branch road 40 is connected with water-water jet 30;Control unit 50 respectively with tie point 20 and second
Road 40 is connected, and control unit 50 is passed through to control tie point 20 to turn on so that the water in water heater 10 is conveyed by tie point 20
To tank 60, or turned on so that the water in water heater 10 is delivered to by the second branch road 40 by controlling the second branch road 40
Water-water jet 30.
Specifically, water heater 10 heats to the water in water heater, yet with water heater 10 and water-water jet 30 it
Between distant, can be stored with main line 100 one section of cold water.In the second branch road 40 side parallel connection tie point 20, in user
During using warm water, control unit 50 can first control tie point 20 to turn on, so that the cold water of storage flows into first in main line 100
Branch road 20, and it is delivered to the water tank of tank 60 such as water closet by tie point 20, wherein, tank 60 is used for
The water that storage tie point 20 flows out, and water is otherwise utilized, and after the cold water in main line 100 is drained, control unit 50 can
The second branch road 40 is controlled to turn on again, so that the hot water in water heater 10 flows into the second branch road 40 by main line 100, and by the
Two branch roads 40 are delivered to water-water jet 30, and by hot water and the outside such as tap water that supplies water is mixed so that turbid water system for water-water jet 30
1 outlet discharges warm water, with for users to use.
Thus, tie point 20 and the working condition of the second branch road 40 are controlled by control unit 50, can prevent from being responsible for
The cold water of road 100 memory storage is discharged from the outlet of turbid water system 1, it is to avoid user is subject to cold water stimulating when with water, improves
With the comfort level of water, cold water is effectively recycled meanwhile, saved water resource, more intelligent and hommization, carry
Rise Consumer's Experience.
According to an embodiment of the present utility model, as shown in Figure 2 a-2d, main line 100 passes through three-way valve 101 and first
Branch road 20 and the second branch road 40 connect, and wherein, the water inlet A of three-way valve 101 is connected with main line 100, and the first of three-way valve 101
Water outlet B is connected with tie point 20, and the second outlet C of three-way valve 101 is connected with the second branch road 40.That is, can be
At the interconnection of main line 100, tie point 20 and the second branch road 40, three-way valve 101 is set, to control water outlet direction.
It should be noted that three-way valve 101 can be electric T-shaped valve, wherein, as shown in Figure 2 d, three-way valve 101 can be
Switching water discharging direction under the control of control unit 50.
Specifically, as shown in Figure 2 a-2d, control unit 50 is passed through to control the working condition of three-way valve 101 to control
Water direction, for example, can adopt following control mode:
One) as shown in Fig. 2 a and 2d, control unit 50 controls the water inlet A of three-way valve 101 and the first water outlet B formed logical
Road, now, tie point 20 turns on, and the second branch road 40 turns off, and that is, the water in main line 100 is according to the direction of Fig. 2 a arrow indication
Flow into tie point 20;
Two) as shown in Fig. 2 b and 2d, control unit 50 controls the water inlet A of three-way valve 101 and the second outlet C-shaped to become logical
Road, now, the second branch road 40 turns on, and tie point 20 turns off, and that is, the water in main line 100 is according to the direction of Fig. 2 b arrow indication
Flow into the second branch road 40;
Three) as illustrated in figures 2 c and 2d, control unit 50 controls three-way valve 101 to close, i.e. the first water outlet B and the second water outlet
Mouthful C all not outflow waters, now, tie point 20 and the second branch road 40 are turned off, and that is, the water in main line 100 may not flow into first
Branch road 20 and the second branch road 40.
According to an embodiment of the present utility model, as shown in Figure 2 d, turbid water system 1 also includes:Temperature detector 102,
Wherein, temperature detector 102 is arranged in main line 100, and temperature detector 102 is used for detecting the water temperature T in main line 100,
Wherein, the water temperature T that control unit 50 is used in main line 100 is less than during preset temperature threshold value T0 and controls tie point 20 to lead
Logical, and control the second branch road 40 to turn on when the water temperature T in main line 100 is more than or equal to preset temperature threshold value T0.
Specifically, as shown in Figure 2 d, temperature detector 102 can be arranged at the water inlet A of three-way valve 101, so,
After the hot water that water heater 10 produces enters main line 100, temperature detector 102 can water in real-time detection main line 100
Warm T, and the water temperature T detecting is sent to control unit 50, control unit 50 judges whether the water temperature T in main line 100 is little
In preset temperature threshold value T0, when the water temperature T that control unit 50 judges in main line 100 is less than preset temperature threshold value T0, control
Unit 50 controls the water inlet A of three-way valve 101 and the first water outlet B to form path and control tie point 20 open-minded, main line
Water in 100 flows into tie point 20 according to the direction of Fig. 2 a arrow indication, so that cold water is delivered to through tie point 20
Tank 60, otherwise utilized;When the water temperature T that control unit 50 judges in main line 100 is more than or equal to preset temperature threshold value T0
When, control unit 50 controls the water inlet A of three-way valve 101 and the second outlet C-shaped to become path to control the second branch road 40 open-minded,
Hot water in water heater 10 flows into the second branch road 40 according to the direction of Fig. 2 b arrow indication, so that hot water is through the second branch road 40
It is delivered to water-water jet 30, further, the outside such as tap water that supplies water is mixed in water-water jet 30 with hot water, and finally exists
The outlet of turbid water system 1 discharges warm water.
It should be noted that the length of pipeline in the second branch road 40 is shorter, the cold water in the second branch road 40 pipeline is to mixed
The influence degree that the water temperature of the outlet of water system 1 produces is less;Conversely, the water temperature of the outlet of turbid water system 1 is produced
Influence degree is bigger.Based on this, when actually used, the pipeline of the second branch road 40 should be as far as possible short, i.e. three-way valve 101 and water-water jet
Pipeline between 30 should be as far as possible short, is produced with the water temperature reducing the outlet to turbid water system 1 for the cold water in the second branch road 40 pipeline
Raw influence degree.Thus, it is possible to first control tie point 20 conducting to make cold water flow directly into tank 60 from water heater 10,
The second branch road 40 conducting is controlled to make hot water flow directly into water-water jet 30 from water heater 10, it is thus possible to prevent cold water from mixed water again
The outlet of system 1 is discharged, it is to avoid user is subject to cold water stimulating when with water, improves and uses water comfort level, cold water is entered meanwhile
Row effectively recycles, and has saved water resource, and more intelligent and hommization improves Consumer's Experience.
According to a specific embodiment of the present utility model, as shown in figure 3, turbid water system 1 also includes:Level Detection unit
601, wherein, Level Detection unit 601 is arranged in tank 60, and Level Detection unit 601 is used for detecting tank 60
Liquid level, wherein, control unit 50 is used for when the liquid level of tank 60 is more than default level threshold controlling tie point 20
Close.
Specifically, the liquid level in Level Detection unit 601 real-time detection tank 60 to be to generate Level Detection signal,
And Level Detection signal is fed back to control unit 50, control unit 50 judges the liquid of tank 60 according to Level Detection signal
Whether position is more than default level threshold, if control unit 50 judges that the liquid level of tank 60 is less than or equal to default liquid level threshold
Value, then control unit 50 can continue to judge the water temperature T in main line 100, and the water temperature T in main line 100 is less than and presets
Control the water inlet A of three-way valve 101 and the first water outlet B to form path during temperature threshold T0, water is delivered to tank
60;If control unit 50 judges that the liquid level of tank 60 is more than default level threshold, control unit 50 controls three-way valve
101 the first water outlet B is closed and controls tie point 20 to close, and to stop for water being delivered to tank 60, now controls
Unit 50 can remind user to discharge the water in tank 60 by alarm set.
According to another specific embodiment of the present utility model, as shown in figure 4, turbid water system 1 also includes:Drain assembly
602, wherein, drain assembly 602 is arranged on tank 60, and wherein, control unit 50 is used for leading in the accumulative of tie point 20
The logical time is more than control drain assembly 602 during preset time threshold and opens, so that tank 60 carries out draining.Wherein, draining
Assembly 602 may include electric draining switch, and electric draining switch can be controlled by control unit 50.
Specifically, water temperature T in judging main line 100 for the control unit 50 is less than during preset temperature threshold value T0 and controls the
One branch road 20 turns on, and carries out timing by timer to the accumulative ON time of tie point 20, to judge tie point 20
Accumulative ON time whether be more than preset time threshold, if control unit 50 judges the accumulative ON time of tie point 20
More than preset time threshold, then more than default level threshold, control unit 50 controls draining to the liquid level in explanation tank 60
Assembly 602 is opened, so that tank 60 carries out draining;If control unit 50 judges the accumulative ON time of tie point 20
Less than preset time threshold, then less than default level threshold, control unit 50 controls draining to the liquid level in explanation tank 60
Assembly 602 is closed, so that tank 60 maintains normal work.
Thus, it is possible to prevent the water in tank 60 from overflowing, it is to avoid the water in tank 60 occurs spilling to make
The trouble becoming, makes turbid water system more perfect.
According to some embodiments of the present utility model, as shown in Figure 2 d, control unit 50 can be the master control core of water-water jet 30
Piece.Say, control unit 50 can be integrated into water-water jet 30, the water outlet direction controlling of three-way valve 101, the switch of drain assembly 602
Control and all can be realized by water-water jet 30.
To sum up, the turbid water system being proposed according to this utility model embodiment, control unit is passed through to control tie point conducting,
The main line of water heater is made to connect with tie point, so that the water in water heater is transported to tank by tie point, and
By controlling the second branch road conducting, the main line of water heater is made to connect with the second branch road, so that the water in water heater passes through second
Branch road is delivered to water-water jet, thus, the cold water in main line can be transported to by tank by the second branch road, prevent cold water from
The outlet of turbid water system flows out, it is to avoid user is subject to cold water stimulating when with water, improves and uses water comfort level, meanwhile, to cold
Water is effectively recycled, and has saved water resource, more intelligent and hommization, improves Consumer's Experience.
Fig. 5 is the flow chart of the control method of the turbid water system according to this utility model embodiment.Turbid water system includes heat
Hydrophone, tie point, the second branch road and water-water jet, water heater conveys the water in water heater, the entering of tie point by main line
The mouth of a river is connected with main line, and the outlet of tie point is connected with tank, and the water inlet of the second branch road is connected with main line,
The outlet of the second branch road is connected with water-water jet.Wherein, as shown in figure 5, this control method comprises the following steps:
S1:Water temperature in detection main line.
S2:If the water temperature in main line is less than preset temperature threshold value, control tie point conducting so that in water heater
Water tank is delivered to by tie point.
S3:If the water temperature in main line is more than or equal to preset temperature threshold value, control the second branch road conducting so that hot water
Water in device is delivered to water-water jet by the second branch road.
Specifically, water heater heats to the water in water heater, and by delivery to main line, when water heater produces
After raw hot water enters main line, can water temperature T in real-time detection main line, and determine whether the water temperature T in main line
Whether it is less than preset temperature threshold value T0, if it is determined that the water temperature T in main line is less than preset temperature threshold value T0, then control first
Road forms path with main line, so that the cold water of storage is delivered to tank through tie point in main line, separately makees him
With;If it is determined that the water temperature T in main line is more than or equal to preset temperature threshold value T0, then the second branch road and main line is controlled to be formed logical
Road so that the hot water in main line is delivered to water-water jet through the second branch road, further, outside supply water such as tap water with
Hot water is mixed in water-water jet, and the final outlet in turbid water system discharges warm water.
As described above, as shown in fig. 6, the control method of turbid water system specifically includes following steps:
S101:Set preset temperature threshold value T0.
S102:Turbid water system starts to discharge water.
S103:Water temperature T in real-time detection main line.
S104:Judge whether the water temperature T in main line is less than preset temperature threshold value T0.
If it is, execution step S105;If it is not, then execution step S106;
S105:Tie point is controlled to turn on so that the water in water heater is delivered to tank by tie point.
S106:The second branch road is controlled to turn on so that the water in water heater is delivered to water-water jet by the second branch road.
S107:Terminate.
It should be noted that the length of pipeline in the second branch road is shorter, the cold water in the second bypass line is to water-water jet
The influence degree that the water temperature in exit produces is less;Conversely, it is bigger to the influence degree of the water temperature generation in water-water jet exit.Base
In this, when actually used, the pipeline of the second branch road should be as far as possible short, to reduce the cold water in the second bypass line to turbid water system
Outlet water temperature produce influence degree.
Thus, it is possible to first control tie point conducting to make cold water flow directly into tank from water heater, then control second
Branch road conducting makes hot water flow directly into water-water jet from water heater, it is thus possible to prevent cold water from flowing out from the outlet of turbid water system,
Avoid user to be subject to cold water stimulating when with water, improve and use water comfort level, cold water is effectively recycled meanwhile,
Save water resource, more intelligent and hommization, improve Consumer's Experience.
According to an embodiment of the present utility model, the control method of turbid water system also includes:The liquid of detection tank
Position;If the liquid level of tank is more than default level threshold, tie point is controlled to close.
Specifically, the liquid level in real-time detection tank to be to generate Level Detection signal, and believed according to Level Detection
The liquid level number judging tank whether more than default level threshold, if it is determined that the liquid level of tank is less than or equal to default liquid
Position threshold value, then can continue to judge the water temperature T in main line, and when the water temperature T in main line is less than preset temperature threshold value T0
Control tie point to form path with main line, water is delivered to tank;If it is determined that the liquid level of tank is more than
Default level threshold, then controlled tie point to close, to stop for water being delivered to tank, now can be carried by alarm set
Water in tank is discharged by awake user.
According to another embodiment of the present utility model, the control method of turbid water system also includes:Record tie point
Accumulative ON time;If the accumulative service time of tie point is more than preset time threshold, tank is controlled to be arranged
Water.
Specifically, the water temperature T in judging main line is less than during preset temperature threshold value T0 and controls tie point conducting, and
Timing is carried out to the accumulative ON time of tie point, whether Preset Time is more than with the accumulative ON time judging tie point
Threshold value, if it is determined that the accumulative ON time of tie point is more than preset time threshold, then the liquid level in explanation tank is big
In default level threshold, tank is controlled to carry out draining;If it is determined that when the accumulative ON time of tie point is less than default
Between threshold value, then the liquid level in explanation tank be less than default level threshold, control tank to maintain normal work.
Thus, it is possible to prevent the water in tank from overflowing, it is to avoid the water in tank occurs spilling to cause
Trouble, makes turbid water system more perfect.
To sum up, in the control method of the turbid water system being proposed according to this utility model embodiment, first detection main line
Water temperature, if the water temperature in main line is less than preset temperature threshold value, controls tie point conducting so that the water in water heater leads to
Cross tie point and be delivered to tank;If the water temperature in main line is more than or equal to preset temperature threshold value, control second
Road turns on so that the water in main line is delivered to water-water jet by the second branch road, thus, can be by main line by the second branch road
Cold water be transported to tank, prevent cold water from flowing out from the outlet of turbid water system, it is to avoid user is subject to cold water when with water
Stimulate, improve and use water comfort level, cold water is effectively recycled meanwhile, saved water resource, more intelligent and
Hommization, improves Consumer's Experience.
In description of the present utility model it is to be understood that term " " center ", " longitudinal ", " horizontal ", " length ", " width
Degree ", " thickness ", " on ", D score, "front", "rear", "left", "right", " vertical ", " level ", " top ", " bottom " " interior ", " outward ", " suitable
The orientation of instruction such as hour hands ", " counterclockwise ", " axial ", " radially ", " circumferential " or position relationship are based on orientation shown in the drawings
Or position relationship, be for only for ease of description this utility model and simplify description, rather than instruction or hint indication device or
Element must have specific orientation, with specific azimuth configuration and operation, therefore it is not intended that to limit of the present utility model
System.
Additionally, term " first ", " second " are only used for describing purpose, and it is not intended that indicating or hint relative importance
Or the implicit quantity indicating indicated technical characteristic.Thus, define " first ", the feature of " second " can express or
Implicitly include at least one this feature.In description of the present utility model, " multiple " are meant that at least two, such as two
Individual, three etc., unless otherwise expressly limited specifically.
In this utility model, unless otherwise clearly defined and limited, term " installation ", " being connected ", " connection ", " Gu
Fixed " etc. term should be interpreted broadly, for example, it may be being fixedly connected or being detachably connected or integral;Can be
It is mechanically connected or electrically connect;Can be to be joined directly together it is also possible to be indirectly connected to by intermediary, can be two
The connection of element internal or the interaction relationship of two elements, limit unless otherwise clear and definite.Common skill for this area
For art personnel, concrete meaning in this utility model for the above-mentioned term can be understood as the case may be.
In this utility model, unless otherwise clearly defined and limited, fisrt feature second feature " on " or D score
Can be the first and second feature directly contacts, or the first and second features pass through intermediary mediate contact.And, first is special
Levy second feature " on ", " top " and " above " but fisrt feature directly over second feature or oblique upper, or only
Represent that fisrt feature level height is higher than second feature.Fisrt feature second feature " under ", " lower section " and " below " permissible
Be fisrt feature immediately below second feature or obliquely downward, or be merely representative of fisrt feature level height and be less than second feature.
In the description of this specification, reference term " embodiment ", " some embodiments ", " example ", " specifically show
The description of example " or " some examples " etc. means specific features, structure, material or the spy describing with reference to this embodiment or example
Point is contained at least one embodiment of the present utility model or example.In this manual, the schematic table to above-mentioned term
State and be necessarily directed to identical embodiment or example.And, the specific features of description, structure, material or feature are permissible
Any one or more embodiments or example combine in an appropriate manner.Additionally, in the case of not conflicting, this area
Technical staff the feature of the different embodiments described in this specification or example and different embodiment or example can be entered
Row combines and combines.
Although of the present utility model embodiment has been shown and described above it is to be understood that above-described embodiment is
Exemplary it is impossible to be interpreted as that those of ordinary skill in the art is in scope of the present utility model to restriction of the present utility model
Interior above-described embodiment can be changed, change, replacing and modification.
Claims (6)
1. a kind of turbid water system is it is characterised in that include:
Water heater, described water heater conveys the water in described water heater by main line;
Tie point, the water inlet of described tie point is connected with described main line, the outlet of described tie point and water storage
Container connects;
Water-water jet;
Second branch road, the water inlet of described second branch road is connected with described main line, the outlet of described second branch road with described
Water-water jet connects;
Control unit, described control unit is connected with described tie point and described second branch road respectively, and described control unit is led to
Cross and control described tie point to turn on so that the water in described water heater is delivered to described tank by described tie point,
Or by controlling described second branch road conducting so that the water in described water heater is delivered to described mixing by described second branch road
Hydrophone.
2. turbid water system according to claim 1 is it is characterised in that described main line passes through three-way valve and described first
Road and described second branch road connect, and wherein, the water inlet of described three-way valve is connected with described main line, and the first of described three-way valve
Outlet is connected with described tie point, and the second outlet of described three-way valve is connected with described second branch road.
3. turbid water system according to claim 1 is it is characterised in that also include:
It is arranged on the temperature detector in described main line, described temperature detector is used for detecting the water temperature in described main line,
Wherein, the water temperature that described control unit is used in described main line controls described tie point to lead when being less than preset temperature threshold value
Logical, and when the water temperature in described main line is more than or equal to described preset temperature threshold value, control described second branch road conducting.
4. turbid water system according to claim 3 is it is characterised in that also include:
It is arranged on the Level Detection unit in described tank, described Level Detection unit is used for detecting described tank
Liquid level, wherein, described control unit is used for controlling described first when the liquid level of described tank is more than default level threshold
Branch road is closed.
5. turbid water system according to claim 3 is it is characterised in that also include:
It is arranged on the drain assembly of described tank, wherein, described control unit is used for leading in the accumulative of described tie point
The logical time controls described drain assembly to open, so that described tank carries out draining when being more than preset time threshold.
6. the turbid water system according to any one of claim 1-5 is it is characterised in that described control unit is described mixed water
The main control chip of device.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620889884.5U CN205980348U (en) | 2016-08-16 | 2016-08-16 | Mix water system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620889884.5U CN205980348U (en) | 2016-08-16 | 2016-08-16 | Mix water system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205980348U true CN205980348U (en) | 2017-02-22 |
Family
ID=58030547
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620889884.5U Active CN205980348U (en) | 2016-08-16 | 2016-08-16 | Mix water system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205980348U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106123353A (en) * | 2016-08-16 | 2016-11-16 | 芜湖美的厨卫电器制造有限公司 | Turbid water system and control method thereof |
CN107339805A (en) * | 2017-08-23 | 2017-11-10 | 湖南埃瓦新能源科技有限公司 | Air energy thermal water installations |
-
2016
- 2016-08-16 CN CN201620889884.5U patent/CN205980348U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106123353A (en) * | 2016-08-16 | 2016-11-16 | 芜湖美的厨卫电器制造有限公司 | Turbid water system and control method thereof |
CN107339805A (en) * | 2017-08-23 | 2017-11-10 | 湖南埃瓦新能源科技有限公司 | Air energy thermal water installations |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104856565B (en) | Instant heating type drinking equipment and its control method | |
CN106766231B (en) | Shower system and its control method without cold water and Recovery of the hot water | |
CN205980348U (en) | Mix water system | |
CN102525315B (en) | Residual water removing device of showering system | |
CN106766230A (en) | Water heater, water heater return water system and its control method and device | |
CN208536122U (en) | A kind of novel heat pump hot-water heating system | |
CN112728759B (en) | Water storage type hot water system and control method | |
CN103994495A (en) | Water storage type energy-saving system and energy-saving method | |
CN101737953A (en) | Water heater pipeline post heating device, water heater and method for heating domestic water | |
CN206755608U (en) | Water-heater system | |
CN106247627B (en) | A kind of high-efficiency water-saving temperature regulating device | |
CN106123353A (en) | Turbid water system and control method thereof | |
CN109512281A (en) | A kind of double gallbladder direct-drinking devices and its double gallbladder high temperature direct drinking method for yielding water | |
CN102287903A (en) | Intelligent dual-mode energy-saving under water heater | |
CN108224544A (en) | A kind of Intelligent preheating bathroom accessory system | |
CN204718102U (en) | Beforehand instant double-mode electric water heater | |
CN207881223U (en) | Water route module, hot-water heating system | |
CN106820989A (en) | Milk maker | |
CN201828029U (en) | Intelligent dual-mode electricity-saving water control system of 'small kitchen mate' water heater | |
CN209879637U (en) | Water outlet pipeline system of water vending machine | |
CN206438555U (en) | Water Sproading reutilization system | |
CN205980003U (en) | Floor heating control device and floor heating system | |
CN208566849U (en) | Hot-water heating system | |
CN218814088U (en) | Water outlet device | |
CN203731545U (en) | Water-storage type energy saving system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |