CN205976091U - Steel construction building thermal insulation wall - Google Patents

Steel construction building thermal insulation wall Download PDF

Info

Publication number
CN205976091U
CN205976091U CN201620819714.XU CN201620819714U CN205976091U CN 205976091 U CN205976091 U CN 205976091U CN 201620819714 U CN201620819714 U CN 201620819714U CN 205976091 U CN205976091 U CN 205976091U
Authority
CN
China
Prior art keywords
steel
warming plate
wall
lateral surface
wall body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620819714.XU
Other languages
Chinese (zh)
Inventor
赵宏宇
孙志光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ochsen (Beijing) new Mstar Technology Ltd
Original Assignee
Beijing Ochsen Energy-Saving Environmental Protection Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Ochsen Energy-Saving Environmental Protection Technology Co Ltd filed Critical Beijing Ochsen Energy-Saving Environmental Protection Technology Co Ltd
Priority to CN201620819714.XU priority Critical patent/CN205976091U/en
Application granted granted Critical
Publication of CN205976091U publication Critical patent/CN205976091U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Building Environments (AREA)

Abstract

The utility model provides a steel construction building thermal insulation wall contains steel column, wall body and first heated board, and first heated board sets up in wall body lateral surface, has the adhesive linkage between first heated board and the wall body, the wall body sets up in the steel column left and right sides, be fixed with the metal mesh on the steel column lateral surface, the metal mesh lateral surface is provided with the second heated board, have the clearance between second heated board and the steel column lateral surface, the watering has the high liquidity bonding agent in the clearance, can there be the efficiency of construction and the durability that improve steel construction building thermal insulation wall, improve the heat preservation efficiency of steel construction wall body simultaneously to possess the advantage that the steel construction structural weight per square meter is light.

Description

A kind of steel building heat-preserving wall
【Technical field】
This utility model is related to a kind of steel building field, particularly a kind of steel building heat-preserving wall and its construction Method.
【Background technology】
Technology using steel structure structure building house is fairly common at present, and steel building has from heavy and light, factory Change manufacture, quick for installation, short construction period, anti-seismic performance are good, gain quick return for investment, the comprehensive advantage such as low in the pollution of the environment, with reinforcing bar Xoncrete structure is compared, with more the feature at " high, big, light " three aspects, in the world, particularly developed country and ground Area, steel construction obtain in building engineering field rationally, be widely applied.
In order to further conform to the relevant criterion of energy saving building, steel house also must carry out insulation construction in exterior wall Install, however, traditional warming plate mounting means is after the formation of steel house, body of wall external pasting fix warming plate with Reach the effect of insulation, but not only speed be slow for such form of construction work, and the warming plate being located at outside steel construction do not allow easy to stick Be attached on steel column, simultaneously in order to reinforce warming plate and steel column, generally using bolt sealed so that also holding in the sealed position of bolt Easily form cold bridge effect, cause the not good problem of heat insulation effect.
Patent No. CN201310457792.0 discloses steel structure concrete internal-external thermal insulation integration module house, It is connected with channel-section steel between steel column, be connected with longitudinal shaped steel between levels channel-section steel and form steel house skeleton.Skeleton side It is connected with heat-insulation layer and sheet material.Casting concrete between relative channel-section steel and between body of wall two-layer heat-insulation layer.Floor with Beam body contact position pours full of empty between space and beam body outer layer heat-insulation layer and channel-section steel between beam body internal layer heat-insulation layer and channel-section steel Between and the channel-section steel relative with two between the consecutive concrete of concrete, integralization structure after house concreting, There is better quality performance and longer service life, heat-insulation layer and body of wall same life-span, and cement need not be carried out in constructing Maintenance and anticorrosion of steel structure antirust treatment.Although such form of construction work strengthens the combination of warming plate and body of wall, phase of constructing When loaded down with trivial details, simultaneously need to carrying out a large amount of concrete castings, decrease the advantage from heavy and light for the steel house.
Patent No. CN201220050765.2 discloses a kind of steel construction heat-preserving wall, including warming plate and steel plate, in insulation The front side of plate, upside, downside, left side and right side are respectively fixed with steel plate, are evenly equipped with bolt mounting holes on steel plate and warming plate. This utility model structure is simple, easy to use, by being respectively fixed with the front side of warming plate, upside, downside, left side and right side Steel plate, not only increases intensity, and the damage reducing warming plate also improves fire resistance property.This kind of form of construction work adopts steel plate solid Determine warming plate, improve building cost on the contrary, the weight of steel plate also results in the load increasing of body of wall simultaneously.
Therefore, problem of the prior art is mainly at following 3 points:
1. work progress is loaded down with trivial details;
2. increased the load of body of wall;
3. steel column and the combination of warming plate easily form cold bridge, reduce heat insulation effect.
【Utility model content】
For solving the above problems, this utility model provide a kind of steel building heat-preserving wall, comprise steel column, wall body and First warming plate, the first warming plate is arranged at wall outer body face, has adhesive linkage between the first warming plate and wall body;Wall is originally Body is arranged at the steel column left and right sides;Wire netting is fixed with steel column lateral surface, wire netting lateral surface is provided with the second warming plate;The There is between two warming plates and steel column lateral surface gap, pour in gap and be inoculated with high fluidity bonding agent.
Further, the first insulation plate suqare is less than wall bulk area, and the first insulation plate suqare is wall bulk area 30%~90%.
Further, the second warming plate width is more than steel column lateral surface width.
Further, the first insulation plate suqare is equal to wall bulk area.
Further, gap width is 0.5cm~3cm.
Therefore the beneficial effects of the utility model are, increase wire netting in steel construction lateral surface, and protect and warming plate between Leave gap, in gap, then pour into high fluidity bonding agent, strengthen the fastness between warming plate and steel column, simultaneously letter Change the construction technology of many complexity, possessed the advantage from heavy and light for the steel building again, meanwhile, such structure has solved to know clearly Steel column locations form the problem of cold bridge.
【Brief description】
Fig. 1 is this utility model first embodiment top view cross section structural representation.
Fig. 2 is combined top view cross section structural representation for wall body with the first warming plate.
Fig. 3 is this utility model second embodiment top view cross section structural representation.
Fig. 4 splices schematic diagram for wall body.
Fig. 5 is the construction method of this utility model building heat preservation body of wall.
Element number explanation
Steel column 11
Wall body 12
First warming plate 13
Adhesive linkage 14
Wire netting 15
Second warming plate 16
Gap 17
【Specific embodiment】
This utility model mainly discloses a kind of steel building heat-preserving wall and its construction method, wherein for steel construction Construction process and energy saving building insulation relevant regulations have been known to those skilled in the technology concerned, therefore with saying hereinafter Bright, no longer to building heat preservation template using and relevant regulations make complete description.
Refer to Fig. 1, provide a kind of steel building heat-preserving wall for this utility model, comprise steel column 11, wall body 12 And first warming plate 13, the first warming plate 13 is arranged at wall body 12 lateral surface, has between the first warming plate 13 and wall body 12 There is adhesive linkage 14, this adhesive linkage 14 can be using inorganic mortar or fire prevention bonding agent, and wall body 12 is in embodiment of the present utility model Middle employing aerated concrete wall body, but aerated blocks can be adopted depending on design requirement during practice of construction;Wall body 12 sets It is placed in steel column 11 left and right sides;Wire netting 15 is fixed with steel column 11 lateral surface, wire netting 15 lateral surface is provided with the second insulation Plate 16, wire netting 15 can be steel wire further;Between second warming plate 16 and steel column 11 lateral surface, there is gap 17, gap 17 width is 0.5cm~3cm, pours and is inoculated with high fluidity bonding agent (not shown), less than the gap of 0.5cm in gap 17 17 pourings being unfavorable for high fluidity bonding agent, can make higher than 3cm that the deadweight of high fluidity bonding agent is excessive, cost increase; After high fluidity bonding agent is solid, the second warming plate 16 can be bonded in the lateral surface of steel column 11, wire netting 15 can add simultaneously The adhesive force of strong high fluidity bonding agent;High fluidity bonding agent is high fluidity mortar or strength cement-based grouting material, and this practicality is new It is adopted as M50 mobility non-shrink mortar, specific performance is as follows in type embodiment:
Please also refer to Fig. 1 and Fig. 2, in the embodiment that this utility model provides, the first warming plate 13 area is little In wall body 12 area, make the first warming plate 13 surrounding and wall body 12 surrounding can form stair-stepping offset, simultaneously the first guarantor Warm plate 13 size can be the 30%~90% of wall body 12 area, and this means, the first warming plate 13 minimum area is not less than The 30% of wall body 12 area, the surrounding of the first warming plate 13 and wall body 12 surrounding respectively have 50mm's respectively in the present embodiment Distance, the 80%~83.33% about of the first warming plate 13 area about wall body 12 area, therefore, when two pieces of wall bodies 12 When being fixed on steel column 11 left and right sides, a sky being more than steel column 11 lateral surface width can be vacated in the position of steel column 11 lateral surface Between, for the present embodiment, about steel column 11 lateral surface width adds 100mm, then fills in this by the second warming plate 16 In space, therefore the width of the second warming plate 16 is more than the width of steel column 11 lateral surface in the present embodiment.
Refer to Fig. 3, this utility model provides in another embodiment, the area of the first warming plate 11 is equal to wall body 12 In steel column 11 lateral surface position, area, therefore when wall body 12 is fixed on steel column 11 left and right sides, occurs that is equal to a steel The space of post 11 lateral surface width, inserts in this space by the second warming plate 16, therefore the second warming plate 16 in the present embodiment Width be equal to steel column 11 lateral surface width.
Furthermore, in the construction of steel building body of wall or secondary structure body of wall, equally can be using as the wall body of Fig. 2 12 structures, refer to Fig. 4, when two wall bodies 12 are spliced, two wall body 12 junction formation space, and also can be in this space In insert the second warming plate 16, meanwhile, make the second warming plate 16 and the stitching portion of wall body 12 have gap 17, then at gap Pour into high flowing bonding agent in 17, complete the construction of whole body of wall;Second warming plate 16 is set in wall body 12 stitching portion and fills Entering the high bonding agent that flows, can effectively reducing the cold bridge effect of stitching portion, improving the heat insulation effect of integral wall body.
In above-described embodiment, the first warming plate 11 can be identical material or different material from the second warming plate 16 Matter, the such as first warming plate 11 and the second warming plate 16 can be the B level insulation material such as extruded sheet, cystosepiment simultaneously, or In order to preferably avoid the conduction of heat of steel column, the second warming plate 16 can be replaced with A level insulation material, such as AEPS is polymerized polyphenyl Plate, foam cement, foamed concrete, rock wool, mineral wool, glass cotton, glass bead and glue powder polyphenyl particle etc..
Additionally, in general, should not there is excessive gap between the first warming plate 11 and the second warming plate 16, only may be used Can because the first warming plate 11 and the second warming plate 16 are different or cut closely sealed relation and there are trickle gap from material, Those trickle gaps can be filled automatically when pouring into high fluidity bonding agent, does not therefore need in the first warming plate 11 and Clog other materials between two warming plates 16 to be engaged.
Refer to Fig. 5, a kind of construction method as aforementioned steel building heat-preserving wall, comprise the steps of:(1) provide It is compounded with the wall body of the first warming plate;(2) wall body is installed on the steel column left and right sides;Fix metal in steel column lateral surface Net;(3) fix the second warming plate in steel column lateral surface, and and steel column lateral surface between, there is gap;(4) pour into height in gap Mobility bonding agent.Because the wall body structure that construction method is formed is identical with previous embodiment, here is not repeated here, but Necessarily illustrate, in construction method of the present utility model, the first warming plate and wall body are prefabricated chunk, meaning That is, first the first warming plate is combined with wall body with bonding agent before wall construction, during Specific construction, will The wall body of compound first warming plate is integrally fixed construction as a plate.Reduce wall body to be fixed with warming plate Complicated technology.
Further, in order to strengthen the steadiness of warming plate and wall body, it is to avoid produce after warming plate is of long duration The problem coming off, during practice of construction, is uniformly arranged by spacing≤600mm in the first warming plate and the second warming plate edge Expansion anchor, strengthens the steadiness between warming plate and wall body.
Steel building heat-preserving wall provided by the utility model and construction method, not only reduce numerous in work progress Trivial construction procedure, makes the durability of heat-insulation layer increase, and realizes and the structure same life-span, improves steel building insulation simultaneously Efficiency and remain the advantage from heavy and light for the steel building, additionally, the body of wall of this kind of structure is due to taking in all seam areas Perfusion high fluidity bonding agent is processed, and forms continuously airtight mortar rigid waterproof layer, improves the waterproof effect of metope.
The foregoing is only this utility model preferably embodiment, be not limited to right model of the present utility model Enclose;Simultaneously above description, for correlative technology field, special personage should understand and implement, therefore other are without departing from this practicality The equivalent change being completed under new disclosed spirit or modification, should be included in claim.

Claims (5)

1. a kind of steel building heat-preserving wall, comprise steel column, wall body and the first warming plate it is characterised in that:
Described first warming plate is arranged at described wall outer body face, has viscous between described first warming plate and described wall body Connect layer;
Described wall body is arranged at the described steel column left and right sides;
It is fixed with wire netting, described wire netting lateral surface is provided with the second warming plate on described steel column lateral surface;
Between described second warming plate and described steel column lateral surface, there is gap, pour in described gap and be inoculated with high fluidity bonding Agent.
2. steel building heat-preserving wall according to claim 1 it is characterised in that:Described first insulation plate suqare is less than Described wall bulk area, described first insulation plate suqare is the 30%~90% of described wall bulk area.
3. steel building heat-preserving wall according to claim 2 is it is characterised in that described second warming plate width is more than Described steel column lateral surface width.
4. steel building heat-preserving wall according to claim 1 it is characterised in that:Described first insulation plate suqare is equal to Described wall bulk area.
5. steel building heat-preserving wall according to claim 1 it is characterised in that:Described gap width be 0.5cm~ 3cm.
CN201620819714.XU 2016-07-29 2016-07-29 Steel construction building thermal insulation wall Active CN205976091U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620819714.XU CN205976091U (en) 2016-07-29 2016-07-29 Steel construction building thermal insulation wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620819714.XU CN205976091U (en) 2016-07-29 2016-07-29 Steel construction building thermal insulation wall

Publications (1)

Publication Number Publication Date
CN205976091U true CN205976091U (en) 2017-02-22

Family

ID=58027305

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620819714.XU Active CN205976091U (en) 2016-07-29 2016-07-29 Steel construction building thermal insulation wall

Country Status (1)

Country Link
CN (1) CN205976091U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106121088A (en) * 2016-07-29 2016-11-16 北京奥克森节能环保科技有限公司 A kind of steel building heat-preserving wall and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106121088A (en) * 2016-07-29 2016-11-16 北京奥克森节能环保科技有限公司 A kind of steel building heat-preserving wall and construction method thereof
CN106121088B (en) * 2016-07-29 2018-10-23 北京奥克森节能环保科技有限公司 A kind of construction method of steel building heat-preserving wall

Similar Documents

Publication Publication Date Title
CN104358337B (en) Light-weight composite floor slab structure for assembling integral prefabricated double thin plates, and construction method
CN206737118U (en) A kind of prefabricated regeneration concrete bean column node of reinforcement
CN206289884U (en) A kind of heat insulation integrated light roof board of fabricated construction
CN204386018U (en) Autoclaved aerated concrete slabs steel sheet arrangement of reinforcement
CN108385884A (en) A kind of bolted and welded connection steel reinforced concrete special-shape column-stealth beam floor assembly system
CN110374254A (en) The plug-in composite wallboard structure of assembled basalt fibre regeneration concrete and production method
CN206070792U (en) A kind of assembled steel lath band combined concrete shear wall
CN215167030U (en) Cast-in-place glass fiber reinforced concrete superimposed sheet of steel bar truss
CN205976091U (en) Steel construction building thermal insulation wall
CN208168032U (en) Assembled built-in heat insulation layer concrete composite wall-light steel frame-floor connecting node
CN207277667U (en) Insulation blocks
CN109008733A (en) Punch forming bathroom chassis and its manufacturing method
CN209144647U (en) A kind of combined planar load-bearing steel plate of high intensity
CN110158762A (en) Prefabricated steel structure frame supports room
CN206477479U (en) A kind of compound heat preservation die plate wall body structure
CN206189694U (en) Assembled room lid
CN107119815B (en) With lead pipe-coarse sand energy-dissipating and shock-absorbing key assembled linear type heat-preserving wall and the practice
CN107460968A (en) Sandwich heat preservation in-line combined wall and the practice with lead pipe coarse sand energy-dissipating and shock-absorbing key
CN106121088B (en) A kind of construction method of steel building heat-preserving wall
CN212295247U (en) Assembled light full precast slab
CN106869360B (en) A kind of Z-shaped combined wall and the practice with sandwich heat preservation and damping key
CN106930433A (en) Large-scale lateral aperture overall assembled wallboard
CN201915557U (en) Reinforced concrete beam slab based on preset cast-in-place construction of thermal-insulation plate at bottom of beam slab
CN107119819B (en) Assembled external thermal insulation L shape combined wall and the practice with energy-dissipating and shock-absorbing key
CN113622542A (en) Assembled outer wall based on light outer wall apron board

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20170509

Address after: 102446 Fangshan District City, the town of Beijing after the town of Industrial Development Zone, No. 1

Patentee after: Ochsen (Beijing) new Mstar Technology Ltd

Address before: 102446 Fangshan District City, the town of Beijing after the town of Industrial Development Zone, No. 1

Patentee before: Beijing Ochsen energy-saving environmental protection technology Co. Ltd.

TR01 Transfer of patent right