CN205936638U - Oversensitive round shield tunnel lining cutting - Google Patents

Oversensitive round shield tunnel lining cutting Download PDF

Info

Publication number
CN205936638U
CN205936638U CN201620723413.7U CN201620723413U CN205936638U CN 205936638 U CN205936638 U CN 205936638U CN 201620723413 U CN201620723413 U CN 201620723413U CN 205936638 U CN205936638 U CN 205936638U
Authority
CN
China
Prior art keywords
lining cutting
oversensitive
shield tunnel
section
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620723413.7U
Other languages
Chinese (zh)
Inventor
夏勇
申志军
王丽庆
王泊松
李建伟
王成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Design Corp
Original Assignee
Third Railway Survey and Design Institute Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Railway Survey and Design Institute Group Corp filed Critical Third Railway Survey and Design Institute Group Corp
Priority to CN201620723413.7U priority Critical patent/CN205936638U/en
Application granted granted Critical
Publication of CN205936638U publication Critical patent/CN205936638U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses an oversensitive round shield tunnel lining cutting, it closes the domain lining cutting of splicing to include to be enclosed by uniform thickness arc section of jurisdiction, the profile is oversensitive circular in the domain lining cutting. Domain lining cutting section is the axial symmetry figure, the symmetry axis be the tunnel central line. The utility model discloses the profile is unanimous in the interior profile that well section of jurisdiction design was adopted and the tunnel of mountain tunnel mine method construction, and the structural cohesion of being convenient for realizes that the shield constructs the nos shaft of construction and starts, receives the requirement, overcome circular shield and constructed the section of jurisdiction too big problem of space fill concrete under the rail of back of assembling, and the atress is reasonable, and each section of jurisdiction combines section position atress in place to carry out the arrangement of reinforcement, the degree of difficulty and quickening construction progress but effective control investment, reduction are under construction. The utility model discloses the design, the construction that are applicable to shield tunnel under major diameter, big buried depth, long distance, the rich water and soil matter formation condition that can be extensive.

Description

A kind of oversensitive O-tube shield tunnel lining cutting
Technical field
This utility model belongs to a kind of shield tunnel liner and in particular to a kind of oversensitive O-tube shield tunnel lining cutting.
Background technology
Shield, since being born, has extensively been applied and has been developed rapidly with its safety, high-quality, quick, environmental protection characteristic. China's shield technique starts from nineteen fifty-three, and northeast Fuxin colliery diameter 2.6m handss dig the Liu Shui tunnel of formula shield-tunneling construction, 60 to 90 years For first Shanghai soft soil shield technique, to middle and late stage nineties Guangzhou compound stratum shield technique.Shield technique is advised greatly in traffic Constantly update in mould practice and innovation, the geological conditions of all kinds of complexity can not only be adapted to, and to " long, big, difficult, fast, Excellent " development, even more from " traffic " to " electric power, water utilities, combustion gas " broad areas extension;Shield technique is so that geological adaptability is wide, machine Tool degree height is the development trend of following underground engineering construction.
At present shield diameter is increasing, and driving distance is more and more longer, all using being circular configuration, its rail of large-diameter shield Lower space arranges concrete, is required using function, rigidity and monolithic stability with the operation meeting tunnel.City tunnel is in order to reduce Occupancy on the underground space and reduce on structures impact and reduce investment, once attempts non-circular structure, Japan is in the eighties Development and application Rectangular Tunnel, has manufactured shape of a hoof machinery for 1986 and has excavated shield, manufactured ECL shield within 1991;Shanghai track Traffic No. 8 lines double-O-tube shields in 2003 and Guangzhou, Shanghai municipal works nineteen ninety-five rectangular shield etc. successfully use, for special-shaped shield Technology development done deposit work.
Circular configuration advantage is that reasonable stress, construction friction power are little;But low space utilization, implements operation interference under rail Greatly, in-cavity construction environment is poor.General traffic tunnel is taken precautions against natural calamities for satisfaction and is evacuated space under function setting rail, and it is with the obvious advantage;But How mountain ridge railway tunnel, according to circle, is filled by plain concrete under its rail, and digging soil amount is big, backfill quantity of masonry greatly, and investment is high; Though rectangular cross section energy effectively utilizes space, structure stress is unfavorable.
Content of the invention
This utility model is to solve the problems, such as that prior art proposes, and its objective is to provide a kind of oversensitive targe structure tunnel Road lining cutting.
The technical solution of the utility model is:A kind of oversensitive O-tube shield tunnel lining cutting, encloses including by uniform thickness arc section of jurisdiction The domain lining cutting being spliced into, described domain lining cutting Internal periphery is oversensitive round shape.
Described domain lining section is zhou duicheng tuxing, and described axis of symmetry is tunnel center line.
Described domain lining cutting includes the odd loop of spaced series and even loop successively.
Described odd loop, even loop are along tunnel center line mirror image each other.
Described odd loop and even loop all include wedge, No. I adjacent block, No. II block that is connected, No. I conventional bar, No. II general Logical block, No. III conventional bar, No. IV conventional bar, No. V conventional bar.
Described wedge is located at the inclined 40 ° of positions of vault.
It is staggered joint erection between described adjacent odd loop, even loop.
The Internal periphery that in this utility model, Segment design adopts is consistent with the tunnel Internal periphery of mountain tunnel mining method construction, It is easy to structure cohesion, realizes shield-tunneling construction no vertical shaft and originate, receive requirement, overcome space under rail after circular shield pipe sheet assembling The big problem of fill concrete, and reasonable stress, each section of jurisdiction carries out arrangement of reinforcement with reference to place section position stress, can effective control throw Money, reduction difficulty of construction and accelerating construction progress.This utility model can be widely suitable for major diameter, great burying, distance, The design of shield tunnel, construction under the conditions of rich water texture stratum.
Brief description
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the schematic diagram of odd loop in this utility model;
Fig. 3 is the schematic diagram of even loop in this utility model;
Wherein:
1 wedge 2 I adjacent block
4 No. I conventional bar of 3 No. II adjacent blocks
6 No. III conventional bar of 5 No. II conventional bar
8 No. V conventional bar of 7 No. IV conventional bar.
Specific embodiment
Hereinafter, with embodiment, this utility model is described in detail referring to the drawings:
As shown in Fig. 1 ~ 3, a kind of oversensitive O-tube shield tunnel lining cutting, enclose, including by uniform thickness arc section of jurisdiction, the domain being spliced into Lining cutting, described domain lining cutting Internal periphery is oversensitive round shape.
Described domain lining section is zhou duicheng tuxing, and described axis of symmetry is tunnel center line.
Described domain lining cutting includes the odd loop of spaced series and even loop successively.
Described odd loop, even loop are along tunnel center line mirror image each other.
Described odd loop and even loop all include 1, No. I adjacent block of wedge, 3, No. I conventional bar 4, II of 2, No. II adjacent block Number 5, No. III conventional bar of conventional bar, 7, No. V conventional bar 8 of 6, No. IV conventional bar.
Described wedge 1 is located at the inclined 40 ° of positions of vault.
It is staggered joint erection between described adjacent odd loop, even loop.
Pipe-plate lining ring has carried out inspection by different operating mode least favorable situations and has calculated, and specific aim carries out Reinforcement Design, is closed with economical Reason steel using amount ensures structure safety, meets structure safety index requirement.
Shield tunnel outline span is 11.54m, and highly for 10.59m, thickness is 500mm shield duct piece.Pipe sheet assembling Mode is intended using " 7+1 piecemeal " staggered joint erection mode.
Oversensitive round Lining Ring lining cutting centrage etc. is divided 22 parts, is divided into 7+1 block arc plate, i.e. 1, No. I phase of wedge Adjacent block 5, No. III conventional bar of 4, No. II conventional bar of 2, No. II adjacent piece 3, No. I conventional bar, 7, No. V conventional bar 8 of 6, No. IV conventional bar.
Design requirement is pressed in section of jurisdiction number, be transported to scene, assembling, assembled cyclization, and then the company of being concatenated into after shield machine driving Continue into multi-ring.
This utility model lining cutting relies on oversensitive round shield machine assembly molding, is designed with two kinds of structural shapes, series connection is spelled Dress forms tunnel-liner, first carries out piecemeal, typesetting, water proof structure arrangement etc. with odd number Lining Ring, then applies even loop shield lining Build.
The Internal periphery that in this utility model, Segment design adopts is consistent with the tunnel Internal periphery of mountain tunnel mining method construction, It is easy to structure cohesion, realizes shield-tunneling construction no vertical shaft and originate, receive requirement, overcome space under rail after circular shield pipe sheet assembling The big problem of fill concrete amount, and reasonable stress, each section of jurisdiction carries out arrangement of reinforcement with reference to place section position stress, can effective control Investment, reduction difficulty of construction and accelerating construction progress.This utility model can be widely suitable for major diameter, great burying, long away from The design of shield tunnel, construction under the conditions of, rich water texture stratum.

Claims (7)

1. a kind of oversensitive O-tube shield tunnel lining cutting it is characterised in that:Serve as a contrast including being enclosed the domain being spliced into by uniform thickness arc section of jurisdiction Build, described domain lining cutting Internal periphery is oversensitive round shape.
2. a kind of oversensitive O-tube shield tunnel lining cutting according to claim 1 it is characterised in that:Described domain lining section is Zhou duicheng tuxing, described axis of symmetry is tunnel center line.
3. a kind of oversensitive O-tube shield tunnel lining cutting according to claim 2 it is characterised in that:Described domain lining cutting include according to The odd loop of minor tick series connection and even loop.
4. a kind of oversensitive O-tube shield tunnel lining cutting according to claim 3 it is characterised in that:Described odd loop, even loop Along tunnel center line mirror image each other.
5. a kind of oversensitive O-tube shield tunnel lining cutting according to claim 3 it is characterised in that:Described odd loop and even loop All include wedge, No. I adjacent block, No. II connected block, No. I conventional bar, No. II conventional bar, No. III conventional bar, No. IV conventional bar, No. V conventional bar.
6. a kind of oversensitive O-tube shield tunnel lining cutting according to claim 5 it is characterised in that:Described wedge is located at vault Inclined 40 ° of positions.
7. a kind of oversensitive O-tube shield tunnel lining cutting according to claim 3 it is characterised in that:Described adjacent odd loop, It is staggered joint erection between even loop.
CN201620723413.7U 2016-07-11 2016-07-11 Oversensitive round shield tunnel lining cutting Active CN205936638U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620723413.7U CN205936638U (en) 2016-07-11 2016-07-11 Oversensitive round shield tunnel lining cutting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620723413.7U CN205936638U (en) 2016-07-11 2016-07-11 Oversensitive round shield tunnel lining cutting

Publications (1)

Publication Number Publication Date
CN205936638U true CN205936638U (en) 2017-02-08

Family

ID=57928702

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620723413.7U Active CN205936638U (en) 2016-07-11 2016-07-11 Oversensitive round shield tunnel lining cutting

Country Status (1)

Country Link
CN (1) CN205936638U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106640122A (en) * 2016-07-11 2017-05-10 铁道第三勘察设计院集团有限公司 Multi-centered round shield tunnel lining
CN108361045A (en) * 2018-04-23 2018-08-03 同济大学 A kind of duct pieces of shield tunnel being adapted to soft soil layer

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106640122A (en) * 2016-07-11 2017-05-10 铁道第三勘察设计院集团有限公司 Multi-centered round shield tunnel lining
CN108361045A (en) * 2018-04-23 2018-08-03 同济大学 A kind of duct pieces of shield tunnel being adapted to soft soil layer

Similar Documents

Publication Publication Date Title
CN103375170B (en) Underground excavation construction deformation control method for three-hole small clear distance tunnel underpass trunk railway
CN202280462U (en) Pipe segment for building subway station through large-diameter shield tunneling expanded excavation
CN101806217A (en) Tunneling method for three-line parallel small-distance shallow-buried and unsymmetrical-pressure tunnel groups
CN102979531B (en) Reinforce construction method and the structure of large-scale rock slope deep weak structural plane
CN102606168B (en) Construction method for preventing settlement and deformation of shallow-buried-excavation tunnel in excavation
CN106640122A (en) Multi-centered round shield tunnel lining
CN105332710A (en) Construction method suitable for up-down overlapped tunnel with small clear space and long distance under weak geological condition
CN112049650B (en) Method for expanding and excavating existing small shield tunnel by using large shield
CN106014449A (en) Construction method of double-track small-clear distance large-section jointed rock mass subway tunnel
CN102287207B (en) Assembling jacking method in relation to serious collapse of small-section tunnel
CN205895242U (en) Low -angle crossing tunnel structure
CN102182464A (en) Construction structure and construction method of channel structure
CN205936638U (en) Oversensitive round shield tunnel lining cutting
CN109184704A (en) A kind of small-clear-distance tunnel excavation and middle folder rock reinforcement technique
CN104790964A (en) Construction method for shield tunneling machine moving-out on condition of tunnel portal deviation
CN210598976U (en) Shield constructs tail portion slip casting pressure test device
CN108915714A (en) The double TBM installation methods in one hole
CN111594199A (en) Construction method for wall back backfilling of double-shield TBM
Qiu et al. First application of mechanized method using earth pressure balance TBM with large horseshoe-shaped cross section to loess mountain tunnel: A case study of Baicheng tunnel
CN108374674A (en) Six pilot tunnels, 12 step Underground Space Excavation method for protecting support
CN209621322U (en) A kind of guide table structure missed the stop suitable for rock tunnel(ling) machine
CN110700848A (en) Small-curvature-radius shield construction subsection deviation rectifying method
CN204187155U (en) A kind of underground steel and concrete structure pipeline of inner wall belt spiral compound stiffening ring
CN202768001U (en) Arc bridge type integral supporting structure for inclined well bell mouth construction
CN109578017A (en) A kind of quick liner structure of speciality light section hydraulic tunnel and its construction method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 300142 Hebei District, Zhongshan Road, No. 10,

Patentee after: China Railway Design Group Limited

Address before: 300142 Hebei District, Zhongshan Road, No. 10,

Patentee before: China Railway Third Survey and Design Institute Group Ltd.