CN205894436U - Dysmorphism daylighting furred ceiling structure - Google Patents

Dysmorphism daylighting furred ceiling structure Download PDF

Info

Publication number
CN205894436U
CN205894436U CN201620798029.3U CN201620798029U CN205894436U CN 205894436 U CN205894436 U CN 205894436U CN 201620798029 U CN201620798029 U CN 201620798029U CN 205894436 U CN205894436 U CN 205894436U
Authority
CN
China
Prior art keywords
daylighting
arc support
ceiling structure
light
support rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620798029.3U
Other languages
Chinese (zh)
Inventor
王靖钢
曾夏洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Jing Gong Decoration Design Engineering Co Ltd
Original Assignee
Shenzhen Jing Gong Decoration Design Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Jing Gong Decoration Design Engineering Co Ltd filed Critical Shenzhen Jing Gong Decoration Design Engineering Co Ltd
Priority to CN201620798029.3U priority Critical patent/CN205894436U/en
Application granted granted Critical
Publication of CN205894436U publication Critical patent/CN205894436U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Non-Portable Lighting Devices Or Systems Thereof (AREA)

Abstract

The utility model discloses a dysmorphism daylighting furred ceiling structure, including cavity glass, the square tube, a ARC support bar, the 2nd ARC support bar and glass fiber gypsum board, cavity glass folds and locates on the square tube, for reflect sunlight to indoor, a ARC support bar and the 2nd ARC support bar be symmetric connection in the both ends of square tube respectively, form curved daylighting passageway between a ARC support bar and the 2nd ARC support bar and the square tube, and the width of daylighting passageway increases from the direction of square tube earthward in proper order, glass fiber gypsum board is located in the daylighting passageway, and glass fiber gypsum board seals the daylighting passageway, glass fiber gypsum board is used for the sunlight reflection of cavity glass reflection extremely indoorly. The utility model provides a dysmorphism daylighting furred ceiling structure makes the width top -down of this daylighting passageway increase in proper order through in setting up curved daylighting passageway to the realization is under the less condition of sky window area, and it is long -pending to increase lighting surface, ensures this dysmorphism daylighting furred ceiling structure's daylighting effect.

Description

A kind of abnormity daylighting ceiling structure
Technical field
The utility model is related to building decoration field, more particularly, to a kind of abnormity daylighting ceiling structure.
Background technology
At present, in large-scale commercial building agent structure, architect often opens up skylight for daylighting on furred ceiling.And by In the particularity in market, particularly high-end market needs to meet businessman and attracts consumer demand to carry out individual decoration, Therefore in decoration construction, how in the case of the daylighting area reducing skylight, the overall daylighting effect in skylight can be increased again And guarantee its safe and reliable be urgent need to resolve critical problem.
Utility model content
The purpose of this utility model is to provide a kind of entirety that can guarantee furred ceiling in the case of reducing sky window ara Daylighting effect simultaneously guarantees its safe and reliable special-shaped daylighting ceiling structure.
In order to solve above-mentioned technical problem, the utility model provides a kind of abnormity daylighting ceiling structure, and it includes hollow Glass, Fang Tong, the first arc support rod, the second arc support rod and glass fibre plasterboard, described double glazing is located at described On side is logical, in order to reflected sunlight to interior, described first arc support rod and the second arc support rod are respectively symmetrically and are connected to The two ends that described side is led to, described first arc support rod and the second arc support rod and described side form the daylighting of arc between leading to Passage, and the direction that the width of described daylighting passage leads to ground from described side increases successively, described glass fibre plasterboard sets In described daylighting passage, and described glass fibre plasterboard closes the side of described daylighting passage, described glass fibre gypsum Plate reflexes to interior in order to the sunshine reflecting described double glazing.
Wherein, the center of described double glazing is provided with the first shot-light, and the light emission direction of described first shot-light is towards ground Face is arranged.
Wherein, described first arc support rod and described side lead to the one end connecing and are provided with the first light trough, described first lamp It is provided with the second shot-light, described second arc support rod and described side lead to the one end connecing and be provided with one second light trough, institute in groove State and in the second light trough, be provided with the 3rd shot-light, the light emission direction of described second shot-light and the 3rd shot-light is all towards described glass fibre Plasterboard is arranged.
Wherein, described glass fibre plasterboard is provided with least one deformation along along the bearing of trend of described daylighting passage Seam.
Wherein, the area of the position towards ground for the described daylighting passage is more than or equal to described daylighting passage near described The twice of the logical area of position in side.
Wherein, the surface of described glass fibre plasterboard is processed using sub- light.
Wherein, described abnormity daylighting furred ceiling also includes the first bracing piece and the second bracing piece, described first bracing piece and the Two bracing pieces are respectively symmetrically the two ends leading to located at described side, and described first bracing piece and the second bracing piece are all along towards ground Direction is extended, and described first arc support rod is fixedly connected on the position that described first bracing piece leads to, institute adjacent to described side State the second arc support rod and be fixedly connected on the position that described second bracing piece leads to adjacent to described side.
Wherein, described abnormity daylighting ceiling structure also includes the first stone material peg and the second stone being extended towards ground Material peg, described first stone material peg is fixedly connected on one end that described first bracing piece leads to, described second stone away from described side Material peg is fixedly connected on one end that described second bracing piece leads to away from described side.
Wherein, described first stone material peg being extended has some first Zinc-coated angle steels, some described first angle steel The other end is extended to the one end being led to away from described side with described first arc support rod and is connected;Extend on described second stone material peg It is provided with some second Zinc-coated angle steels, the other end of some described second Zinc-coated angle steels extends as described second arc support rod Connect away from one end that described side is led to.
Wherein, described first stone material peg and the second stone material peg also each extend over and be provided with some first hangs muscles and Two hangs muscles, described first hangs muscle and the second hangs muscle are all extended along towards the direction on ground, and described first hangs muscle and second Hangs muscle is equipped with Thistle board on the one end away from described first stone material peg and the second stone material peg.
The special-shaped daylighting ceiling structure that the utility model provides is by being respectively provided with the first arc at described double glazing two ends Shape support bar and the second arc support rod, and make between this first arc support rod, double glazing and the second arc support rod Formed arc daylighting passage, and the area of this daylighting passage from double glazing, direction earthward increases successively, then by glass Glass fibrous plaster reflexes to interior located at daylighting passage side, the sunshine that double glazing is reflected, thus realizing in sky In the case of window ara is less, increase daylighting area it is ensured that the daylighting effect of this special-shaped daylighting ceiling structure.Additionally, employing side The logical design with the first arc support rod and the second arc support rod is it is ensured that the structural strength of this special-shaped daylighting ceiling structure is with just Degree, prevents it from deformation or coming off, is conducive to the safe handling of this special-shaped daylighting ceiling structure.
Brief description
In order to be illustrated more clearly that the technical solution of the utility model, below will be attached to use required in embodiment Figure be briefly described it should be apparent that, drawings in the following description be only some embodiments of the present utility model, for For those of ordinary skill in the art, on the premise of not paying creative work, other can also be obtained according to these accompanying drawings Accompanying drawing.
Fig. 1 is the special-shaped daylighting ceiling structure schematic diagram that the utility model embodiment provides;
Fig. 2 is the right side structure of the special-shaped daylighting ceiling structure that Fig. 1 is defined by the center of the first shot-light;
Fig. 3 is the iii of Fig. 1 to partial enlarged drawing.
Specific embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, to the technical scheme in the utility model embodiment It is clearly and completely described.
See also Fig. 1 to Fig. 3, a kind of abnormity daylighting ceiling structure 100 that the utility model embodiment provides, bag Include double glazing 10, logical 20, first arc support rod 30 in side, the second arc support rod 40 and glass fibre plasterboard 50, described Double glazing 10 is stacked at described side and leads on 20, in order to reflected sunlight to indoor, described first arc support rod 30 and second Arc support rod 40 is respectively symmetrically and is connected to two ends, described first arc support rod 30 and the second curved support that described side leads to 20 Bar 40 and described side lead to the daylighting passage 111 forming arc between 20, and the width of described daylighting passage 111 leads to 20 from described side Direction earthward increases successively, and described glass fibre plasterboard 50 is in described daylighting passage 111, and described glass fibre Plasterboard 50 closes the side of described daylighting passage 111, and described glass fibre plasterboard 50 is in order to will be anti-for described double glazing 10 The sunshine penetrated reflexes to interior.Using described first arc support rod 30 and the second arc support rod 40 and described double glazing Form described daylighting passage 111 between 10, and make the width of described daylighting passage 111 from described double glazing 10 to ground Direction increases successively such that it is able in the case that area in skylight reduces, increase daylighting area it is ensured that the daylighting of described abnormity is hung The daylighting effect of roof construction, is conducive to the daylighting meeting large department stores to require.
In the present embodiment, for the ease of still guaranteeing that in the case of night sunray deficiency the daylighting of described abnormity is hung The daylighting effect of roof construction 100, the center of described double glazing 10 is provided with the first shot-light 11, and described first shot-light 11 Light emission direction is arranged towards ground.Lighted such that it is able to by described daylighting passage towards ground using described first shot-light 11 111 light sending described first shot-light 11 reflect away, thus the daylighting meeting described abnormity daylighting ceiling structure 100 will Ask, and then can the effectively save energy.
In the present embodiment, described first arc support rod 30 and the second arc support rod 40 are the shaft-like knot of circular arc Structure, and described first arc support rod 30 and the second arc support rod 40 are symmetrical arranged the approximate "eight" shape structure of formation, so that The width of the described daylighting passage 111 being formed increases successively.
Further, guarantee described abnormity daylighting ceiling structure in the case of sunray deficiency to further ensure that 100 daylighting effect, described first arc support rod 30 leads to 20 one end being connected with described side and is provided with one first light trough 31, institute State and in the first light trough 31, be provided with the second shot-light 311, described second arc support rod 40 leads to 20 one end being connected with described side and sets It is equipped with one second light trough 41, in described second light trough 41, be provided with the 3rd shot-light 411, described second shot-light 311 and the 3rd shot-light 411 light emission direction is all arranged towards described glass fibre plasterboard 50.Using described second shot-light 311 and the 3rd shot-light 411 Illumination effect it can be ensured that described abnormity daylighting ceiling structure 100 daylighting effect.Additionally, utilizing described first light trough 31 And second light trough 41 occlusion effect, enable to spectators and described second shot-light 311 and the 3rd cannot be watched on visual effect Shot-light 411 so that described abnormity daylighting ceiling structure 100 overall appearance effect more.
In order to make full use of the sunshine that described double glazing 10 reflection carries out coming, to strengthen described abnormity daylighting furred ceiling knot The daylighting effect of structure 100, the area of the position towards ground for the described daylighting passage 111 is more than or equal to described daylighting passage 111 Twice in the area of the position leading to 20 near described side.Preferably, the area of the position towards ground for the described daylighting passage 111 Equal to the twice of the area in the position leading to 20 near described side for the described daylighting passage 111, make full use of sunshine to reach Effect, further enhances the daylighting effect of interior.
Further, described glass fibre plasterboard 50 is provided with along along the bearing of trend of described daylighting passage 111 to A few movement joint 51, to prevent described glass fibre plasterboard 50 to be deformed because temperature change is expanded with heat and contract with cold.Preferably, The width of described movement joint 51 can be 10mm~20mm.The quantity of described movement joint 51 can be one, two, three or more Bar, depending on the area setting adjustment of described glass fibre plasterboard 50.
Further, the surface of described glass fibre plasterboard 50 is processed using sub- light, so that sunshine is via described glass Light is got in more soft after glass fibrous plaster 50 reflection.Additionally, when night sunray is not enough, open described the One shot-light 11, the second shot-light 311 and the 3rd shot-light 411, the surface Asia light using described glass fibre plasterboard 50 is processed, and also can Enough make described second shot-light 311 and the 3rd shot-light 411 launch more soft to indoor light.
Described abnormity daylighting ceiling structure 100 also includes the first bracing piece 61 and the second bracing piece 62, described first reinforcement Bar 61 and the second bracing piece 62 are respectively symmetrically the two ends leading to 20 located at described side, and described first bracing piece 61 and the second bracing piece 62 equal edges are extended towards the direction on ground, and it is adjacent that described first arc support rod 30 is fixedly connected on described first bracing piece 61 Closely described side leads to 20 position, and described second arc support rod 40 is fixedly connected on described second bracing piece 62 and leads to adjacent to described side 20 position.In the present embodiment, described first bracing piece 61 and the second bracing piece 62 can be using sides logical 20, described first reinforcement Bar 61 and the second bracing piece 62 in order to increase the support strength that described side leads to 20, to increase described abnormity daylighting ceiling structure 100 Bulk strength.
Further, described abnormity daylighting ceiling structure 100 also includes the first stone material peg being extended towards ground 63 and the second stone material peg 64, described first stone material peg 63 is fixedly connected on described first bracing piece 61 and leads to 20 away from described side One end, described second stone material peg 64 be fixedly connected on described second bracing piece 62 away from described side lead to 20 one end.Using Described first stone material peg 63 and the second stone material peg 64 can further enhance described first bracing piece 61 and the second bracing piece 62 support strength.
Additionally, be extended on described first stone material peg 63 thering is some first Zinc-coated angle steels 65, some described first platings The other end of zinc angle steel 65 extends to the one end leading to 20 away from described side with described first arc support rod 30 and is connected;Described second Being extended on stone material peg 64 has some second Zinc-coated angle steels 66, and the other end of some described second Zinc-coated angle steels 66 extends to The one end leading to 20 away from described side with described second arc support rod 40 is connected.Using in described first stone material peg 63 and second The design of described first Zinc-coated angle steel 65 and the second Zinc-coated angle steel 66 is respectively provided with stone material peg 64, and makes described first plating Zinc angle steel 65 and the second Zinc-coated angle steel 66 are respectively connecting to described first arc support rod 30 and the second arc support rod 40, thus Can further ensure that described abnormity is adopted using the rigidity of described first Zinc-coated angle steel 65 and the second Zinc-coated angle steel 66 and intensity The intensity of light ceiling structure 100 and rigidity, and then prevent it from the situation coming off and deforming occurring, improve its safety in utilization.
Further, described first stone material peg 63 and the second stone material peg 64 also each extend over and be provided with some first Hangs muscle 67 and the second hangs muscle 68, described first hangs muscle 67 and the equal edge of the second hangs muscle 68 are extended towards the direction on ground, and institute State and be equipped with the first hangs muscle 67 and the second hangs muscle 68 one end away from described first stone material peg 63 and the second stone material peg 64 Thistle board 69.Specifically, described Thistle board 69 is additionally provided with LED lamp band (sign), to increase described abnormity The exterior decorative effect of daylighting ceiling structure 100.
The special-shaped daylighting ceiling structure 100 that the utility model provides is by being respectively provided with the at described double glazing 10 two ends One arc support rod 30 and the second arc support rod 40, and make this first arc support rod 30, double glazing 10 and the second arc Form the daylighting passage 111 of arc between shape support bar 40, and the area of this daylighting passage 111 is from double glazing 10 earthward Direction increases successively, then by glass fibre plasterboard 50 located at daylighting passage 111 side, double glazing 10 is reflected too Sunlight reflexes to interior, thus realizing, in the case of sky window ara is less, increasing daylighting area it is ensured that this special-shaped daylighting furred ceiling The daylighting effect of structure.Additionally, employing side lead to 20 and first arc support rod 30 and the second arc support rod 40 design it is ensured that The structural strength of this special-shaped daylighting ceiling structure 100 and rigidity, prevent it from deformation or coming off, are conducive to this special-shaped daylighting to hang The safe handling of roof construction.
The above is preferred embodiment of the present utility model it is noted that ordinary skill for the art For personnel, on the premise of without departing from the utility model principle, some improvements and modifications can also be made, these improve and moisten Decorations are also considered as protection domain of the present utility model.

Claims (10)

1. a kind of abnormity daylighting ceiling structure it is characterised in that it include double glazing, Fang Tong, the first arc support rod, second Arc support rod and glass fibre plasterboard, described double glazing is stacked at described side and leads to, in order to reflected sunlight to interior, Described first arc support rod and the second arc support rod are respectively symmetrically and are connected to the two ends that described side is led to, and described first arc props up Strut and the second arc support rod and described side form the daylighting passage of arc between leading to, and the width of described daylighting passage is from institute The direction that ground is led in the side of stating increases successively, and described glass fibre plasterboard is in described daylighting passage, and described glass fibers Dimension plasterboard closes the side of described daylighting passage, and described glass fibre plasterboard is in order to the sun reflecting described double glazing Light reflexes to interior.
2. abnormity daylighting ceiling structure according to claim 1 is it is characterised in that the center of described double glazing is arranged There is the first shot-light, the light emission direction of described first shot-light is arranged towards ground.
3. according to claim 1 abnormity daylighting ceiling structure it is characterised in that described first arc support rod with described The concave end that Fang Tonglian connects is provided with one first light trough, is provided with the second shot-light, described second arc in described first light trough Support bar and described side lead to the concave end connecing and are provided with one second light trough, are provided with the 3rd shot-light in described second light trough, The light emission direction of described second shot-light and the 3rd shot-light is all arranged towards described glass fibre plasterboard.
4. abnormity daylighting ceiling structure according to claim 1 is it is characterised in that along institute on described glass fibre plasterboard At least one movement joint is provided with the bearing of trend stating daylighting passage.
5. according to claim 1 abnormity daylighting ceiling structure it is characterised in that described daylighting passage towards ground position The area put is more than or equal to the twice of the area in the position leading near described side for the described daylighting passage.
6. abnormity daylighting ceiling structure according to claim 1 is it is characterised in that the surface of described glass fibre plasterboard Processed using sub- light.
7. abnormity daylighting ceiling structure according to claim 1 is it is characterised in that described abnormity daylighting ceiling structure also wraps Include the first bracing piece and the second bracing piece, described first bracing piece and the second bracing piece are respectively symmetrically two leading to located at described side Hold, and described first bracing piece and the second bracing piece are all extended along towards the direction on ground, described first arc support rod It is fixedly connected on the position that described first bracing piece leads to adjacent to described side, described second arc support rod is fixedly connected on described the The position that two bracing pieces lead to adjacent to described side.
8. abnormity daylighting ceiling structure according to claim 7 is it is characterised in that described abnormity daylighting ceiling structure also wraps Include the first stone material peg being extended towards ground and the second stone material peg, described first stone material peg is fixedly connected on described One end that first bracing piece leads to away from described side, described second stone material peg is fixedly connected on described second bracing piece away from described The logical one end in side.
9. abnormity daylighting ceiling structure according to claim 8 sets it is characterised in that extending on described first stone material peg It is equipped with some first Zinc-coated angle steels, the other end of some described first angle steel extends to described first arc support rod away from institute One end that the side of stating leads to connects;Being extended on described second stone material peg has some second Zinc-coated angle steels, some described second platings The other end of zinc angle steel extends one end connection led to as described second arc support rod away from described side.
10. abnormity daylighting ceiling structure according to claim 9 is it is characterised in that described first stone material peg and second Also each extend on stone material peg and be provided with some first hangs muscles and the second hangs muscle, described first hangs muscle and the second hangs muscle are all along court Direction earthward is extended, and described first hangs muscle and the second hangs muscle are away from described first stone material peg and the second stone hanging It is equipped with Thistle board on one end of bar.
CN201620798029.3U 2016-07-26 2016-07-26 Dysmorphism daylighting furred ceiling structure Expired - Fee Related CN205894436U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620798029.3U CN205894436U (en) 2016-07-26 2016-07-26 Dysmorphism daylighting furred ceiling structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620798029.3U CN205894436U (en) 2016-07-26 2016-07-26 Dysmorphism daylighting furred ceiling structure

Publications (1)

Publication Number Publication Date
CN205894436U true CN205894436U (en) 2017-01-18

Family

ID=57784690

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620798029.3U Expired - Fee Related CN205894436U (en) 2016-07-26 2016-07-26 Dysmorphism daylighting furred ceiling structure

Country Status (1)

Country Link
CN (1) CN205894436U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111795365A (en) * 2020-08-17 2020-10-20 阿海普建筑设计咨询(北京)有限公司 Light reflecting unit and lighting structure
CN111910818A (en) * 2020-07-20 2020-11-10 上海蓝天房屋装饰工程有限公司 Method for installing large suspended ceiling of departure hall of airport

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111910818A (en) * 2020-07-20 2020-11-10 上海蓝天房屋装饰工程有限公司 Method for installing large suspended ceiling of departure hall of airport
CN111910818B (en) * 2020-07-20 2022-09-13 上海蓝天房屋装饰工程有限公司 Method for installing large suspended ceiling of departure hall of airport
CN111795365A (en) * 2020-08-17 2020-10-20 阿海普建筑设计咨询(北京)有限公司 Light reflecting unit and lighting structure

Similar Documents

Publication Publication Date Title
CN205894436U (en) Dysmorphism daylighting furred ceiling structure
CN103629602B (en) A kind of combination type lamp bar
CN108797862A (en) A kind of double glass solar energy photoelectric curtain walls
CN208650373U (en) A kind of luminous furred ceiling of tower-like moulding that decorating skylight
CN111101627B (en) Heat preservation type energy-saving building curtain wall
CN204665022U (en) A kind of composite and multi-purpose lighting
CN205530864U (en) Metal clad sheet curtain mounting structure
CN205316152U (en) High light efficiency LED panel light
CN209429343U (en) A kind of plate-jointing structure of concealed frame glass curtain wall
CN208011637U (en) The reflective light bar mounting structure of furred ceiling
CN211037431U (en) Curtain wall system with hidden lamps
CN107343723A (en) The silver mirror of concealed lamp band and the method by silver mirror on wall
CN208733886U (en) A kind of double glass solar energy photoelectric curtain walls
CN202382194U (en) Light trough for a multifunction device zone
CN207878741U (en) Heat-insulating type glass curtain wall system
CN206904792U (en) It is a kind of to decorate special multi-functional suspension lamp
CN214220144U (en) Curtain wall splicing structure with attractive structure
CN209703797U (en) A kind of hardened structure of curtain wall standing-seam
CN106284671B (en) A kind of Full-automatic telescopic cantilever glass sunlight house
CN209353579U (en) It is fixed easily organic bright watt of macromolecule
CN205348495U (en) Building curtain wall
CN205012573U (en) Colored steel joins externally gutter
CN217763211U (en) Ceiling lamp mounting structure applied to inclined roof
CN220058498U (en) Aluminum ceiling convenient to installation
CN213488283U (en) Curtain box part for glass curtain wall

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170118