CN205877547U - Tee bend electric smelting pipe fitting - Google Patents
Tee bend electric smelting pipe fitting Download PDFInfo
- Publication number
- CN205877547U CN205877547U CN201620826169.7U CN201620826169U CN205877547U CN 205877547 U CN205877547 U CN 205877547U CN 201620826169 U CN201620826169 U CN 201620826169U CN 205877547 U CN205877547 U CN 205877547U
- Authority
- CN
- China
- Prior art keywords
- pipe
- linkage section
- main
- wall
- arm
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000003723 Smelting Methods 0.000 title abstract 3
- 238000003466 welding Methods 0.000 claims abstract description 17
- 238000002844 melting Methods 0.000 claims description 17
- 230000008018 melting Effects 0.000 claims description 17
- 230000005619 thermoelectricity Effects 0.000 claims 1
- 238000004519 manufacturing process Methods 0.000 abstract description 2
- 230000008878 coupling Effects 0.000 abstract 10
- 238000010168 coupling process Methods 0.000 abstract 10
- 238000005859 coupling reaction Methods 0.000 abstract 10
- 238000010438 heat treatment Methods 0.000 abstract 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000000155 melt Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
Landscapes
- Resistance Heating (AREA)
Abstract
The utility model discloses a tee bend electric smelting pipe fitting, including pipe fitting, branch pipe, pipe fitting include first union coupling section and second union coupling section to and the pipe section of accepting, the pipe fitting's of first union coupling section inner wall, the pipe fitting's of second union coupling section the inner wall and the inner wall of branch pipe twine has respectively arranged the heating resistor silk, still is provided with welding wiring plug core in the pipe diameter main part of first union coupling section and second union coupling section respectively, pipe fitting's outer wall still is provided with the stem stem that holds welding wiring plug core, it observes the nail all to be provided with the welding degree on the pipe wall of first union coupling section, second union coupling section and branch pipe, the boss is accepted to the pipe that the pipe diameter main part inner wall of the pipe section of accepting still was provided with the T style of calligraphy, the pipe end portion of first union coupling section, second union coupling section and branch pipe all overlaps and is provided with the pipe cap, and the inner oral area of pipe cap is accepted the boss with the pipe and is contacted. The utility model discloses a tee bend electric smelting pipe fitting, it is convenient to connect, and the cost of manufacture is low, and welding quality is high.
Description
Technical field
This utility model belongs to pipe joint technical field, is specifically related to a kind of threeway electric melting pipe fittings.
Background technology
Existing threeway electric melting pipe fittings, all two ends at main body tube arrange resistive heater, and arm portion is then not provided with electricity
Resistance silk, during welding, needs to weld together plus a straight-through pipe fitting on arm, troublesome poeration again, and cost is high, efficiency of construction
Low.
Utility model content
The purpose of this utility model is: for problems of the prior art, it is provided that a kind of threeway electric melting pipe fittings,
Three connecting section are provided with resistance wire, it is not necessary to increase other pipe fittings, reduce use cost, operate simpler.
To achieve these goals, the technical solution adopted in the utility model is:
A kind of threeway electric melting pipe fittings, including main pipe body, and be perpendicular in main pipe body side main pipe body and with pipe
The arm of part main body connection, main pipe body includes the first pipe linkage section and the second pipe linkage section being positioned at main pipe body two ends, with
And the pipe undertaking section between the first pipe linkage section and the second pipe linkage section, the main pipe body of the first described pipe linkage section
Inwall, the inwall of main pipe body of the second pipe linkage section and the inwall of arm are wound around respectively and are disposed with resistive heater, in arm
Resistive heater be connected between the resistive heater of the first pipe linkage section and the second pipe linkage section, the first pipe linkage section and
The caliber main body of two pipe linkage sections is also respectively provided with the welding connecting plug core connecting resistive heater, outside main pipe body
Wall is additionally provided with the stem stem accommodating welding connecting plug core;On the tube wall of the first pipe linkage section, the second pipe linkage section and arm all
It is provided with welding degree and observes nail;The caliber main body inner wall of described pipe undertaking section is additionally provided with the pipe of T font and accepts boss;
The tube end of described the first pipe linkage section, the second pipe linkage section and arm all overlaps and is provided with pipe cap, and pipe cap is inner
Oral area is accepted boss with pipe and is contacted.
Preferably, the pipe cap contacted with pipe end actinal surface is additionally provided with locating dowel, the first described pipe linkage section,
The pipe port of two pipe linkage sections and arm is provided with the hole, location for accommodating described locating dowel.
Owing to have employed technique scheme, the beneficial effects of the utility model are:
Threeway electric melting pipe fittings of the present utility model, adds thermal resistance by being provided with in the two ends of main pipe body and arm
Silk, it is possible to realize tee T and connect, simple to operate, convenient welding, cost of manufacture is low, connects end at each pipe simultaneously and is provided with pipe
Cap, it is possible to select the port needing to connect as required, thus tee T is used as straight-through, bend pipe.
Accompanying drawing explanation
Fig. 1 is threeway electric melting pipe fittings of the present utility model (omission pipe cap) structural representation.
Fig. 2 is threeway electric melting pipe fittings of the present utility model (omission pipe cap) front view.
Fig. 3 is threeway electric melting pipe fittings of the present utility model (omission pipe cap) side view.
Fig. 4 is threeway electric melting pipe fittings of the present utility model (omission pipe cap) sectional view.
Fig. 5 is threeway electric melting pipe fittings sectional view of the present utility model.
Reference: 11-main pipe body, 111-the first pipe linkage section, 112-pipe undertaking section, 113-the second pipe linkage section,
12-arm, 101-stem stem, 102-welding degree observation nail, 103-pipe undertaking boss, 104-positions hole, 2-resistive heater, 3-
Pipe cap, 301-locating dowel.
Detailed description of the invention
With reference to Fig. 1-5, threeway electric melting pipe fittings of the present utility model, including main pipe body 11, and in main pipe body 11 1
Side is perpendicular to main pipe body 11 arm 12 connected with main pipe body 11, and main pipe body 11 includes being positioned at main pipe body 11 two ends
The first pipe linkage section 111 and the second pipe linkage section 113, and be positioned at the first pipe linkage section 111 and the second pipe linkage section 113 it
Between pipe accept section 112, the described inwall of main pipe body 11 of the first pipe linkage section 111, the pipe fitting of the second pipe linkage section 113
The inwall of main body 11 and the inwall of arm 12 are wound around respectively and are disposed with resistive heater 2, and the resistive heater 2 in arm 12 is connected
Between the first pipe linkage section 111 and the resistive heater 2 of the second pipe linkage section 113, the first pipe linkage section 111 and the second pipe are even
The caliber main body of the section of connecing 113 is also respectively provided with the welding connecting plug core connecting resistive heater 2, outside main pipe body 11
Wall is additionally provided with the stem stem 101 accommodating welding connecting plug core;First pipe linkage section the 111, second pipe linkage section 113 and arm 12
Tube wall on be provided with welding degree observe nail 102;Described pipe is accepted the caliber main body inner wall of section 112 and is additionally provided with T word
Boss 103 accepted by the pipe of type.
The tube end of first pipe linkage section the 111, second pipe linkage section 113 and arm 12 all overlaps and is provided with pipe cap 3, pipe cap 3
Inner oral area is accepted boss 103 with pipe and is contacted.
So that pipe cap 3 can be firmly fixed to the nozzle position of correspondence, on the pipe cap 3 contacted with pipe end actinal surface
Being additionally provided with locating dowel 301, the pipe port at first described pipe linkage section the 111, second pipe linkage section 113 and arm 12 is all provided with
It is equipped with the hole, location 104 for accommodating described locating dowel 301.
Threeway electric melting pipe fittings of the present utility model, before using, the first pipe linkage section 111 and pipe of the second pipe linkage section 113
Part main body 11 is provided with pipe cap 3, arm 12 is also equipped with pipe cap 3, when needs threeway connects, can be by three pipes
Cap 3 all takes out, the position that then pipe fitting connected will be needed to be connected to correspondence.
If have only to straight-through connection, then can take off the pipe cap 3 in arm 12, connect the pipe fitting of needs
After, by being energized to welding connecting plug core so that resistive heater 2 heats, and melts inside pipe wall, it is achieved connects, is simultaneously connected with
In addition to needing the pipe fitting connected, also pipe cap 3 is connected in arm 12 so that whole threeway electric melting pipe fittings can be made simultaneously
Use for straight pipe, and do not have leakage in arm 12 part.
Same principle, threeway electric melting pipe fittings of the present utility model is also used as union elbow and uses.
Claims (2)
1. a threeway electric melting pipe fittings, including main pipe body (11), and is perpendicular to main pipe body in main pipe body (11) side
(11) arm (12) and with main pipe body (11) connected, it is characterised in that main pipe body (11) includes being positioned at main pipe body
(11) the first pipe linkage section (111) at two ends and the second pipe linkage section (113), and it is positioned at the first pipe linkage section (111) and
Section (112) accepted by pipe between two pipe linkage sections (113), the main pipe body (11) of the first described pipe linkage section (111) interior
Wall, the inwall of main pipe body (11) of the second pipe linkage section (113) and the inwall of arm (12) are wound around respectively to be disposed with and add thermoelectricity
Resistance silk (2), the resistive heater (2) in arm (12) is connected on the first pipe linkage section (111) and the second pipe linkage section (113)
Between resistive heater (2), the caliber main body of the first pipe linkage section (111) and the second pipe linkage section (113) is also respectively provided with
Having the welding connecting plug core of connection resistive heater (2), the outer wall of main pipe body (11) is additionally provided with receiving welding wiring and inserts
The stem stem (101) of head core;It is provided with on the tube wall of the first pipe linkage section (111), the second pipe linkage section (113) and arm (12)
Welding degree observes nail (102);The caliber main body inner wall of described pipe undertaking section (112) is additionally provided with the pipe of T font and accepts convex
Platform (103);
The tube end of described the first pipe linkage section (111), the second pipe linkage section (113) and arm (12) all overlaps and is provided with pipe cap
(3), the inner oral area of pipe cap (3) contacts with pipe undertaking boss (103).
Threeway electric melting pipe fittings the most according to claim 1, it is characterised in that on the pipe cap (3) contacted with pipe end actinal surface
It is additionally provided with locating dowel (301), at the first described pipe linkage section (111), the second pipe linkage section (113) and the pipe of arm (12)
Port is provided with the hole, location (104) for accommodating described locating dowel (301).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620826169.7U CN205877547U (en) | 2016-08-02 | 2016-08-02 | Tee bend electric smelting pipe fitting |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620826169.7U CN205877547U (en) | 2016-08-02 | 2016-08-02 | Tee bend electric smelting pipe fitting |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205877547U true CN205877547U (en) | 2017-01-11 |
Family
ID=57701205
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620826169.7U Active CN205877547U (en) | 2016-08-02 | 2016-08-02 | Tee bend electric smelting pipe fitting |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205877547U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109210306A (en) * | 2018-08-24 | 2019-01-15 | 洛阳沃虹石化设备有限公司 | Welding double-skin duct electric smelting threeway and its mold and production technology can be prepared simultaneously |
-
2016
- 2016-08-02 CN CN201620826169.7U patent/CN205877547U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109210306A (en) * | 2018-08-24 | 2019-01-15 | 洛阳沃虹石化设备有限公司 | Welding double-skin duct electric smelting threeway and its mold and production technology can be prepared simultaneously |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP1004810A2 (en) | Unions for double-wall tubes and dies for manufacturing the same | |
CN113236879B (en) | Air conditioner pipe fitting, air conditioner pipeline and air conditioner | |
CA2321764A1 (en) | Electrofusion coupler | |
CN115429415A (en) | Cold and hot ablation needle | |
CN205877547U (en) | Tee bend electric smelting pipe fitting | |
CN214618417U (en) | Pipe connecting assembly and stainless steel four-way valve with same | |
CN207094016U (en) | A kind of inner thread elbow | |
CN217082937U (en) | Flexible-connection conical surface composite structure of through type double-liner electric water heater | |
CN208364396U (en) | Exhaust pipe, soldered fitting and compressor | |
CN211599879U (en) | PE electric melting pipe fitting with insert | |
CN107476958A (en) | A kind of compressor air suction structure | |
CN2900065Y (en) | Tungsten electrode argon arc welding straight gun | |
CN208173826U (en) | A kind of splicing sleeve | |
CN203697475U (en) | Indoor central heating plastic pipe guide insertion thermal sealing machine | |
CN208382528U (en) | A kind of air conditioner muffler | |
CN106678473A (en) | Sheet type non-leakage rapid hot melting connecting method and connector | |
CN214743897U (en) | Hot melting sleeve suitable for different pipe diameters | |
CN212480491U (en) | High-strength thermoplastic pipe connecting structure | |
CN214305839U (en) | Inner diameter socket pipe fitting and combined pipe fitting thereof | |
CN201764125U (en) | Stainless variable diameter straight tube | |
CN217634341U (en) | Straight pipe end anti-drop splicing connection device for inner bushing type inner coating | |
CN214579153U (en) | Novel stop valve | |
CN214789707U (en) | Hot melting pipe hot melting connection structure | |
CN216832288U (en) | Appurtenance convenient to PE union coupling | |
CN209041832U (en) | A kind of electric-smelting pipe joint |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: 611230 north section of Hongye Road, Chongzhou Economic Development Zone, Chengdu, Sichuan Patentee after: Kangtai Plastic Technology Co.,Ltd. Address before: 611230 north section of Hongye Road, Chongzhou Economic Development Zone, Chengdu, Sichuan Patentee before: Kangtai Plastic Technology Group Co.,Ltd. |
|
CP01 | Change in the name or title of a patent holder |